102.02 Contents of Proposal - Progress Clause

From MediaWiki
Revision as of 09:56, 11 April 2017 by JohnsonN23 (talk | contribs) (JohnsonN23 moved page 102.03 Contents of Proposal to 102.02 Contents of Proposal: Needs to match Spec Book numbering)
Jump to navigation Jump to search

Progress Clause

Note: for projects containing structural steel please see Section 707 - Structural Steel Project Scheduling
Spec Book Section 102

The progress clause is intended to specify the construction timing and schedule requirements to the contractor. The progress clause is provided by the Construction Engineer at the Omissions and Errors Check (OEC) meeting. This document provides the project start and completion dates as well as any interim dates (e.g. open to traffic, staging, milestone) The contractor is required to prepare a progress schedule for submittal at the preconstruction meeting that incorporates the project dates as noted in the progress clause. Traffic requirements and liquidated damages are not to be described in detail in the progress clause. However, the progress clause must mention that failure to meet the specified date(s) will result in the assessment of liquidated damages as specified in other contract documents.

If the project involves an expedited schedule, the progress clause is to include the language referenced in Section 102.2.2.1.5 of the Construction Manual.

[top of page]


Critical Path Networks

Critical Path Networks are often needed to develop the Progress Clause for a project. With MDOT-designed projects, the project manager is required to develop a Critical Path Network on any project that includes an Incentive/Disincentive or Special Liquidated Damages clause. It is recommended that the project manager develop a Critical Path Network for projects with the following characteristics:

Critical Path Network Project Characteristics
1

New construction.

2

Major reconstruction or rehabilitation on an existing roadway that will severely disrupt traffic.

3

Unique or experimental work.

4

More than one construction season.

5

Complex staging (multiple stages with traffic shifts).

There may be other projects that do not meet these criteria which should have a Critical Path Network. The project manager will need to evaluate each project separately. The appropriate construction staff Engineer from the Construction Section and the Engineer assigned to the project should be consulted when determining the need for and when developing a Critical Path Network.

Preparation of a Critical Path Network is a requirement on all consultant-designed projects, regardless of the project type or complexity. The Engineer should contact the Design Consultant Coordination Unit for the project's critical path, if they have not received it, to prepare the Progress Clause.

[top of page]


Critical Path - Construction Time Estimates

The following are average production rates for major work items which, when multiplied or divided by the work item quantities on a project, determine the estimated time (in workdays) to complete an item. These rates should be used as guides and adjusted as necessary to reflect project specific issues and concerns or previous work history in the project area.

Drainage
Work Item
Time

Cross Culverts

  • Rural Highways
  • Expressways
  • Large Headwalls
  • Slab or Box Culverts
  • Plowed-In Edge Drain (production type project)
  • Open-Graded Underdrain (production-type project)


130 ft/day

160 ft/day

5 days/unit

5 days/pour

14,800 ft/day

3,940 ft/day

Sewers

  • 0-6 ft (up to 60 inches)
  • 0-6 ft (over 60 inches)
  • 6 ft-over (up to 60 inches)
  • 6 ft-over (over 60 inches)
  • Jacked-In-Place
    • Including excavation pit and set up
  • Tunnels
    • Hand Mining
    • Machine Mining
    • Including excavation pit and set up


130 ft/day

80 ft/day

80 ft/day

65 ft/day

40 ft/day

min. 5 days


25 ft/day

65 ft/day

min. 5 days

Manholes

3 units/day

Catch Basins

4 units/day

Utilities
Work Item
Time

Water Main (up to 16 inches)

  • Flushing, Testing and Chlorination

330 ft/day 4 days

Water Main (20 to 40 inches)

  • Flushing, Testing and Chlorination

80 ft/day 5 days

Order and Deliver 24 inch HP Water Main

50 days/order

Gas Lines

330 ft/day

Earthwork and Grading
Work Item
Metro Exp-Time
Rural-Time

Embankment (CIP)

2000 yd3/day

7000 yd3/day

Excavation and/or Embankment (Freeway)

2000 yd3/day

12,000 yd3/day

Excavation and/or Embankment (Reconst)

1000 yd3/day

5000 yd3/day

Embankment (Lightweight Fill)

400 yd3/day

800 yd3/day

Muck (Excavated Waste and Backfill)

2000 yd3/day

Excavation (Widening)

800 yd3/day

Grading (G and DS)

1000 yd3/day

Subbase and Selected Subbase (up to 7.4 m)

800 yd3/day

Subbase and Selected Subbase (7.4 m and over)

600 yd3/day

Subgrade Undercut and Backfill

2000 yd3/day

Subbase and Open-Graded Drainage Course

600 yd3/day

Surfacing - Concrete
Work Item
Time

Concrete Pavement (24 ft)

  • Including Forming and Curing

540 yd2/day

min. 7 days

Pavement (24 ft)

3940 ft/day/course

Concrete Ramps (16 ft)

  • Including Forming and Curing

980 ft/day

min. 7 days

Curb (1 side)

2460 ft/day

Concrete Shoulder - Median

1400 yd2/day

Sidewalk (Patching)

80 yd2/day

Sidewalk

220 yd2/day


Structures
Work Item
Time

Sheeting (Shallow)

100 ft/day

General Excavation at Bridge Site

1000 yd3/day

Excavation for Substructure (Footings)

1 unit/day

Piles (40 ft)

15 piles/day

Substructure (Piers and Abutments)

5 days/unit

Order and Delivery of Beams

  • Plate Girders
  • Rolled Beams

100-120 days/order

90-120 days/order

Concrete Beams

50 days/order

Erection of Structural Steel

3 days/span

Bridge Decks

  • Form and Place Reinforcement (200 ft Structure)
  • Pour Deck Slab (1 1/5 days pour)
  • Cure

15 days

2 days/span

14 days

2 Course Bridge Decks

  • Add 9 days for Second Course Latex
  • Add 12 days for Second Course Low Slump

Sidewalks and Railings

  • Sidewalks and Parapets
  • Slip Formed Barriers

5 days/span

2 days/span

Clean Up

10 days

Pedestrian Fencing

  • Shop Plan Approval and Fabrication
  • Erection

1-2 months

1 week/bridge

Riprap Replacement

  • Bucket Dumped
  • Bucket Dumped and Hand Finished

500 yd3/day

170 - 680 yd3/day


Retaining Walls
Work Item
Time

Retaining Walls

1 panel/day

min. 10 days


Railroad Structures
Work Item
Time

Grade Temporary Runaround

1000 yd3/day

Ballast, Ties and Track

160 ft/day

Place Deck Plates

5 days/span

Waterproof, Shotcrete and Mastic

5 days/span


Railroad Crossing Reconstruction
Work Item
Time

Railroad Crossing Reconstruction

10-15 workdays (depends whether concrete base is involved)


Temporary Railroad Structures
Work Item
Time

Order and Deliver Steel

55 days/order

Erect Steel

1 day/span

Ties and Track

3 days/span


Pump House
Work Item
Time

Structure

30 days/yd

Order and Deliver Electrical and Mechanical Equipment

90 days

Install Electrical and Mechanical Equipment

30 days

Miscellaneous
Work Item
Time

Removing Old Pavement

200 ft/day

Removing Old Pavement for Recycling (24 ft)

1480 ft/day

Crushing Old Concrete for 6A or OGDC

1500 tons/day

Removing Trees (Urban)

15 units/day

Removing Trees (Rural)

30 units/day

Removing Concrete Pavement

540 yd2/day

Removing Sidewalk

300 yd2/day

Removing Curb and Gutter

1480 ft/day

Removing HMA Surface

1910 yd2/day

Conditioning Aggregate

1080 yd2/day

HMA Base Stabilizing

2990 yd2/day

Ditching

1970 ft/day

Trenching for Shoulders

2460 ft/day

Station Grading

2000 ft/day

Clearing

9570 yd2/day

Restoration (Topsoil, Seeding, Fertilizer and Mulch)

1970 yd2/day

Sodding

2510 yd2/day

Seeding

47,800 yd2/day

Guardrail

750 ft/day

Fence (Woven Wire)

1180 ft/day

Fence (Chain Link)

490 ft/day

Cleanup

1970 ft/day

Concrete Median Barrier

  • Cure

980 ft/day

min. 7 days

Reroute Traffic (Add 4 Days if 1st Item)

1 day/move

Concrete Glare Screen

1480 ft/day

Light Foundations

  • Order and Delivery

6 units/day

6-8 weeks/order

Remove Railing and Replace w/Barrier (1-2 Decks at a Time)

4 days/side

Longitudinal Joint Repair

1910 ft/day

Crack Sealing

15,750 ft/day

Joint and Crack Sealing

1640 ft/day

Repairing Pavement Joints - Detail 7 or 8

660 ft/day

Seal Coat

21,000 lane ft/day

Diamond Grinding/Profile Texturing Concrete

3950 yd2/day

Rest Area Building

  • Order Material
  • Construct Building


3 months

9 months

Tower Lights

  • Order and Deliver Towers


100 days

Weigh-In-Motion

  • Order and Deliver Materials
  • Order and Deliver with Installation


1 month-6 wks

3 months

Raised Pavement Markers

300 ea/day

Attenuators

2 ea/day

Shoulder Corrugations, Ground or Cut

5 - 6 miles/side/day

Aggregate Base

3120 yd2/day

Aggregate Shoulder

380 yd2/day

Freeway Signing - 3# Post Type

50 signs/day


Concrete Joint Repair
Work Item
Time

Concrete Joint Repair

(High Production - Project with >1000 patches)

  • Average (6 ft)
  • Large (>6 ft)

50 patches/day

600 yd2/day



Structural Repair
Work Item
Time

Bridge Painting

110 yd2/day

Pin and Hanger Replacement

  • Order Pin and Hanger

3 beams/day

60 days

Scarifying (Including Cleanup)

12,000 yd2/day

Joint Removal (Including Cleanup)

  • Forming and Placement

13 ft/day

12 ft/day

Hydro-Demolishing

980 ft/day

Barrier Removal

  • Placement

50 ft/day

150 ft/day

Hand Chipping (Other than Deck)

0.24 yd3/person/day

Casting Latex Overlay

820 ft/day

Curing Overlay

  • Regular
  • High Early


4 days

1 day

Thrie Beam Retrofit

100 ft/day

Beam End Repairs

  • Welded Repairs
  • Bolted Repairs
  • Bolted Stiffeners (Pair)
  • Grind Beam Ends
  • Welded Stiffeners (Pair)
  • H-Pedestal Repairs
    • Welded Repair
    • Replacement


0.75 days/repair

0.50 days/repair

0.25 days/repair

0.25 days/repair

0.25 days/repair


0.50 days/repair

1 day/each

Deck Removal

280 yd2/day



Surface - HMA
Work Item
Time

Metro-Primary (<20,000 tons)

  • Paving
  • Joints
  • Cold Milling
  • Aggregate Shoulders


600 tons/day

490 ft/day

4070 yd2/day

990 tons/day

Metro-Primary (>20,000 tons)

  • Paving
  • Joints
  • Cold Milling


600 tons/day

650 ft/day

8970 yd2/day

Metro-Interstate (>20,000 tons)

  • Paving
  • Joints
  • Aggregate Shoulders


1210 tons/day

1180 ft/day

990 tons/day

Urban-Primary (<20,000 tons)

  • Paving
  • Joints
  • Cold Milling
  • Rubblizing
  • Aggregate Shoulders


710 tons/day

330 ft/day

2030 yd2/day

2030 yd2/day

500 tons/day

Urban-Primary (>20,000 tons)

  • Paving
  • Joints
  • Cold Milling
  • Aggregate Shoulders


1100 tons/day

390 ft/day

2030 yd2/day

550 tons/day

HMA Shoulders (1 Side per Course)

2460 ft/day

Urban-Interstate (>20,000 tons)

  • Paving
  • Joints
  • Cold Milling
  • Rubblizing
  • Aggregate Shoulders


1320 tons/day

720 ft/day

2030 yd2/day

6940 yd2/day

710 tons/day

Rural-Primary (<20,000 tons)

  • Paving
  • Joints
  • Cold Milling
  • Crush and Shape
  • Aggregate Shoulders


710 tons/day

390 ft/day

650 tons/day

12,000 yd2/day

710 tons/day

Rural-Primary (>20,000 tons)

  • Paving
  • Joints
  • Cold Milling
  • Crush and Shape


1210 tons/day

490 ft/day

880 tons/day

12,000 yd2/day

Rural-Interstate (>20,000 tons)

  • Paving
  • Joints


1410 tons/day

720 ft/day

[top of page]


Determination of Work Days/Completion Date

Work Day/Completion Date Determination, Figure 102-2, shows the worksheet to be used for calculating the estimated time to complete major work items and arrive at the total work days/completion date for completion of all work items. Anticipated start dates should consider letting date and earliest possible award dates to avoid an unrealistic completion date on calendar day date projects. This worksheet should remain on file at the project office and become part of the permanently retained project files for audit purposes.

[top of page]


Examples of Progress Clauses

Figures 102-3 and 102-4 are examples of Progress Clauses for Work Day Projects with normal schedules (i.e. routine, non-expedited schedules, four day work week). Figure 102-5 is an example of a Progress Clause for a Calendar Date Project with a normal work week. Figure 102-6 is an example of a Calendar Date Project with an expedited schedule (i.e. five day work week). It is important to include the standard “boilerplate” language associated with expedited schedules starting with the paragraph “No extensions of time will be allowed...” and ending with the paragraph “Any extra costs incurred by the Contractor...” when preparing the Progress Clause.

[top of page]


Draft Boilerplate Progress Clause

The file link provided below is intended to serve as a boilerplate document for creating a progress clause. Text is to be reviewed, deleted, modified, or added before incorporation into the proposal document.

File:Draft Boilerplate Progress Clause May 31 2016.docx

The link will take you to a separate page to download the file.

[top of page]


Progress Clauses with Incentive/Disincentive (I/D) or A+B Schedules

Incentive special provisions provide monetary amounts for completion of work before specified contract dates. These special provisions, if applicable, are to be referenced in the progress clause for successfully meeting dates or times, but the specific incentive requirements and monetary amounts are to be included in a unique special provision. The special provision is to be titled Special Provision for Incentive, (Route (Structure Number)), (Incentive Type). The structure number is only to be included on bridge projects and if the bridge has an associated incentive. Incentive types are: Completion of Work; Interim Completion of Work; and Approved for Traffic. Incentive projects are to include the Special Provision for Extension of Time and Extra Cost for Incentive/Disincentive Projects (12SP108(A)). BOHIM 2002-14 provides guidelines that must be followed during project development, when proposing changes to incentive/liquidated damage contract provisions and when making final incentive/liquidated damage determinations.

MDOT is phasing out the disincentive terminology. This language simply references failure to meet the contract incentive requirements. The disincentive language is not to be used on construction oversight documentation. Not meeting the incentive requirements will result in the application of liquidated damages and the associated pay item “Liquidated Damages, Other”.

The calculation of incentive values based on user delay costs must be documented and placed in the appropriate project folder in the ProjectWise directory.


[top of page]


Contractor Furnished Detailed Progress Schedule, Form 1130

A requirement of the Progress Clause (written by the Engineer and included in the project proposal) is that the low bidder(s) meet with MDOT representatives to work out a detailed Progress Schedule. The low bidder(s) submits their detailed Progress Schedule on Progress Schedule, Form 1130. This Progress Schedule is presently a requirement for contract award and is most often submitted by the Contractor for approval at the preconstruction meeting. All pages of the Progress Schedule shall be signed by all parties. If a Critical Path Network (CPN) is required or allowed under the Progress Clause, the MDOT Region Engineer will assure that the CPN meets the requirements of the Progress Clause. The CPN shall also be signed by all parties involved. If the Progress Schedule is acceptable, the Region Engineer will sign the original form and mail to MDOT Contract Services Division, Contracts Awards Section, P.O. Box 30050, Lansing, MI 48909. Timely handling and submission of this Progress Schedule is essential for the prompt award of the contract.

The Progress Schedule will include, as a minimum, the starting and completion dates for major items of work and the final project completion date specified in the bidding proposal. If an open to traffic date is specified in the bidding proposal, or if the bidding proposal specifies other controlling dates, these also should be included in the Progress Schedule. Recently, a number of Progress Schedules have been approved with “Contract Award” as the first controlling work item and with a start date that has already past or may pass before possible contract award. These Progress Schedules should not be approved as they may result in additional time and/or costs to the contract. The “Contract Award” is an action by the department and is not a work item of the contractor. It is acceptable for the contractor to list “Contract Award” as the first item on form 1130 as long as there is no date given. The first work item listed (after “Contract Award” if the contractor chooses to list this) shall contain an anticipated start date with an asterisk and “*Start work on date as noted or within 10 days of contract award” in the REMARKS section of form 1130.

On Form 1130, overlapping dates or workdays for start complete of the controlling items may be allowed if sufficient justification is included in the submitted Contractor's Progress Schedule. There can be the same start date for completing an item and starting the next.

On workday projects, there has to be a statement on Form 1130 as to when the Contractor will start work (e.g. "Start work within 10 days of award" or "Start by June 16, 1998").

The completion date (day) for the final controlling item should match the contract completion date (day).

The named Subcontractor(s) for specialty and/or designated items (if designated in the proposal) which materially affect the work schedule will be required to sign the Progress Schedule to indicate their approval of the scheduled dates of work set forth in the Progress Schedule.

If the proposal Progress Clause requires that a Critical Path Network be submitted by the Contractor, the Critical Path should be reviewed by the Engineer, approved and dated by the Contractor and the Region Engineer, and attached to the Progress Schedule, Form 1130, before submittal to the Construction Section's Construction Management Unit.

Since the detailed Progress Schedule is part of the contract documents, no changes can be made on the completed form without prior signatories dating and initialing the change. Figure 102-7 is an example of a completed Progress Schedule for a calendar date project. Figure 102-8 is an example of a completed Progress Schedule for a work day project.

Figure 102-2 - Work Day/Completion Date Determination

EXAMPLE PROGRESS CLAUSE
WORK DAY PROJECT - NORMAL SCHEDULE

PROGRESS CLAUSE: Start work within ten (10) days after receiving Notice of Award, or on the date agreed upon with the Engineer. In no case shall any work be commenced prior to the receipt of formal notice of award by MDOT.

This contract will be completed in _____ working days. Working days will be charged starting on the date that work is started, or date agreed, whichever is earlier.

The lower bidder(s) for the work covered in the proposal will be required to meet with department representatives to work out a detailed Progress Schedule. The schedule for this meeting will be set after the low bidder is determined.

The named Subcontractor(s) for Designated and/or Specialty Items, as shown in the proposal, is recommended to be at the scheduled meeting if such items materially affect the work schedule.

The Resident Engineer will arrange the time and place for the meeting.

Figure 102-3

Work Day Project - Normal Schedule


EXAMPLE PROGRESS CLAUSE

WORK DAY PROJECT - NORMAL SCHEDULE

PROGRESS CLAUSE: After receiving Notice of Award, start work on the date agreed upon with the Engineer, which date shall be no later than __________ . In no case shall any work be commenced prior to receipt of formal notice of award by MDOT.

This contract shall be completed in _____ working days. Working days will be charged starting on the date that work is started, or on __________ , whichever is earlier.

The low bidder(s) for the work covered by this proposal will be required to meet with department representatives to work out a detailed Progress Schedule. The schedule for this meeting will be set after the low bidder is determined.

The named Subcontractor(s) for Designated and/or Specialty Items, as shown in the proposal, is recommended to be at the scheduled meeting if such items materially affect the work schedule.

The Resident Engineer will arrange the time and place for the meeting.

Figure 102-4

Work Day Project - Normal Schedule


EXAMPLE PROGRESS CLAUSE

CALENDAR DATE PROJECT - NORMAL SCHEDULE

PROGRESS CLAUSE: Start work within ten (10) days after receiving Notice of Award of Contract, or on or before the date designated as the starting date in the Detailed Progress Schedule. In no case shall any work be commenced prior to receipt of formal notice of award by MDOT.

Staging Dates ______________________________ .

Open to Traffic on or before __________(Date)__________.

The entire project shall be completed on or before __________(Date)__________.

The low bidder(s) for the work covered by this proposal will be required to meet with MDOT representatives to work out a detailed Progress Schedule. The schedule for this meeting will be set after the low bidder is determined.

The named Subcontractor(s) for Designated and/or Specialty Items, as shown in the proposal, is recommended to be at the scheduled meeting if such items materially affect the work schedule.

The Resident Engineer will arrange the time and place for the meeting.

Figure 102-5

Calendar Date Project - Normal Schedule


EXAMPLE PROGRESS CLAUSE

CALENDAR DATE PROJECT - EXPEDITED SCHEDULE

PROGRESS CLAUSE: Start work within ten (10) days after receiving Notice of Award of Contract or on or before the date designated as the starting date in the Detailed Progress Schedule. In no case shall any work be commenced prior to receipt of formal notice of award by MDOT.

This project is on an expedited schedule. The Contractor is expected to mobilize sufficient manpower and equipment and to work the required overtime to maintain the expedited schedule.

The entire project shall be completed on or before ______(Date)______ .

Failure to complete all work on this project by ______(Date)______ will result in the assessment of Liquidated Damages in accordance with subsection 108.11 of the Standard Specifications for Construction. Liquidated Damages will continue to be assessed for each calendar day that this work remains incomplete, even if these days extend beyond the normal seasonal shut down date of No. 15th.

No extensions of time will be allowed for increases in contract quantities, or extra work, unless it can be shown that such increases or extras affect the critical item of work.

No extensions of time will be granted for labor disputes, unless it can be shown that such disputes are industry-wide.

No extensions of time will be granted for delays in delivery of critical materials, unless the delay can be shown to be industry-wide and the delay affects the critical item of work.

Any extra costs incurred by the Contractor due to cold weather protection, winter grading, sufficient manpower and equipment necessary to maintain the expedited schedule, and/or meet the completion date, and any overtime utilized will not be paid for separately, but be included in the bid items/price.

The low bidder(s) to the work covered in this proposal will be required to meet with MDOT representatives to work out a detailed Progress Schedule. The schedule for this meeting will be set after the low bidder is determined.

The named Subcontractor(s) for Designated and/or Specialty Items, as shown in the proposal, is recommended to be at the scheduled meeting if such items materially affect the work schedule.

The Resident Engineer will arrange the time and place for the meeting.

Figure 102-6 Calendar Date Project - Expedited Schedule

Figure 102-7 - Example - Calendar Date Project Progress Schedule
Figure 102-8 - Example - Work Day Progress Schedule