Difference between revisions of "504 - Micro-Surfacing"

From MDOT Wiki
Jump to: navigation, search
(Created page with " <center><span STYLE="font: 60pt arial;">'''504'''</span></center> <center><span STYLE="font: 40pt arial;">'''Micro-Surfacing'''</span></center> <center>[http://mdotcf.state...")
 
(MEASUREMENT AND PAYMENT)
 
(6 intermediate revisions by 2 users not shown)
Line 7: Line 7:
  
  
==GENERAL==
+
==[[#GENERAL|GENERAL]]==
  
 
<span style="color: red"> -Reserved- </span>
 
<span style="color: red"> -Reserved- </span>
  
 +
{{top}}
  
==MATERIALS==
+
==[[#MATERIALS|MATERIALS]]==
  
 
<span style="color: red"> -Reserved- </span>
 
<span style="color: red"> -Reserved- </span>
  
 +
{{top}}
  
==CONSTRUCTION==
+
==[[#CONSTRUCTION|CONSTRUCTION]]==
  
<span style="color: red"> -Reserved- </span>
+
===[[#Surface Preparation|Surface Preparation]]===
  
 +
Before placing the mixture, the Contractor shall thoroughly clean the existing surface of all loose materials, vegetation, dirt, dust, mud and other objectionable materials.  The Contractor also shall remove all pavement markings using an abrasion method.
  
==MEASUREMENT AND PAYMENT==
+
Centerline rumble strips must be adequately filled to allow for the regrinding of the rumbles at the end of the project.  This can be done using two different methods.  The first method is to make a separate pass to fill the rumbles prior to the leveling course.  The second method is to extend each pass; leveling and top course for each lane, over the centerline rumbles essentially filling them 4 times.
 +
 
 +
{{top}}
 +
 
 +
==[[#MEASUREMENT AND PAYMENT|MEASUREMENT AND PAYMENT]]==
 +
 
 +
 
 +
===[[#Delayed Acceptance|Delayed Acceptance]]===
  
 
<span style="color: red"> -Reserved- </span>
 
<span style="color: red"> -Reserved- </span>
 +
 +
{{top}}
 +
 +
[[Category:Construction Manual]]

Latest revision as of 11:45, 27 June 2014

504
Micro-Surfacing
2012 STANDARD SPECIFICATIONS FOR CONSTRUCTION - SECTION 504


Contents

[edit] GENERAL

-Reserved-

[top of page]


[edit] MATERIALS

-Reserved-

[top of page]


[edit] CONSTRUCTION

[edit] Surface Preparation

Before placing the mixture, the Contractor shall thoroughly clean the existing surface of all loose materials, vegetation, dirt, dust, mud and other objectionable materials. The Contractor also shall remove all pavement markings using an abrasion method.

Centerline rumble strips must be adequately filled to allow for the regrinding of the rumbles at the end of the project. This can be done using two different methods. The first method is to make a separate pass to fill the rumbles prior to the leveling course. The second method is to extend each pass; leveling and top course for each lane, over the centerline rumbles essentially filling them 4 times.

[top of page]


[edit] MEASUREMENT AND PAYMENT

[edit] Delayed Acceptance

-Reserved-

[top of page]


Personal tools
Namespaces

Variants
Actions
Navigation
Division 2 - Earthwork
Division 3 - Base Courses
Division 4 - Drainage Features
Division 5 - HMA Pavements and Surface Treatments
Division 6 - PCC Pavement Mixtures
Division 7 - Structures
Division 8 - Incidental Construction
Toolbox