This DRB Procedured describes the Michigan Department of Transportation (MDOT) procedures for submittal and review of Contractor claims and Contractor performance evaluation appeals using a Dispute Review Board (DRB). The Dispute Review Board (DRB) process is used on projects that have incorporated the Special Provision for Dispute Review Board. The DRB process is used on Contractor claims and Contractor performance evaluation appeals as described within. | This DRB Procedured describes the Michigan Department of Transportation (MDOT) procedures for submittal and review of Contractor claims and Contractor performance evaluation appeals using a Dispute Review Board (DRB). The Dispute Review Board (DRB) process is used on projects that have incorporated the Special Provision for Dispute Review Board. The DRB process is used on Contractor claims and Contractor performance evaluation appeals as described within. | ||
− | The most current DRB Procedures | + | The most current DRB Procedures are published on the website and linked below:<br /> |
− | |||
− | + | [http://www.michigan.gov/documents/mdot/MDOT_DRB_Procedures_After10-06-2017_601636_7.pdf Dispute Review Board (DRB) Operating Procedures (effective for all projects let on and after October 6, 2017)] | |
+ | NOTE: For projects let before October 6, 2017 please reference the applicable DRB procedures linked below. | ||
+ | |||
+ | [http://www.michigan.gov/documents/mdot/MDOT_Contractor_Evaluation_Factors_Rating_Criteria_559990_7.pdf Dispute Review Board (DRB) Operating Procedures (effictive for all projects let on and March 4, 2016 through and including September 6, 2017)]. | ||
[http://www.michigan.gov/documents/mdot/MDOT_DRB_Procedures_After090415_494187_7.pdf Dispute Review Board (DRB) Operating Procedures (effective for projects let on September 4, 2015, through and including March 3, 2016] | [http://www.michigan.gov/documents/mdot/MDOT_DRB_Procedures_After090415_494187_7.pdf Dispute Review Board (DRB) Operating Procedures (effective for projects let on September 4, 2015, through and including March 3, 2016] |
Revision as of 07:55, 28 September 2017
Dispute Review Board (DRB) Procedures
This DRB Procedured describes the Michigan Department of Transportation (MDOT) procedures for submittal and review of Contractor claims and Contractor performance evaluation appeals using a Dispute Review Board (DRB). The Dispute Review Board (DRB) process is used on projects that have incorporated the Special Provision for Dispute Review Board. The DRB process is used on Contractor claims and Contractor performance evaluation appeals as described within.
The most current DRB Procedures are published on the website and linked below:
NOTE: For projects let before October 6, 2017 please reference the applicable DRB procedures linked below.