Difference between revisions of "Extending Project Limits"

From MediaWiki
Jump to navigation Jump to search
(New Page Fracturing)
 
(5 intermediate revisions by 2 users not shown)
Line 1: Line 1:
<center><span STYLE="font: 30pt arial;">'''103.02 Extending Project Limits'''</span></center>
 
<center><span STYLE="font: 20pt arial;">103 Scope of the Work</span></center>
 
 
<center>[http://mdotcf.state.mi.us/public/specbook/files/2012/103%20Scope%20of%20Work.pdf 2012 STANDARD SPECIFICATIONS FOR CONSTRUCTION - SECTION 103]</center>
 
<center>[http://mdotcf.state.mi.us/public/specbook/files/2012/103%20Scope%20of%20Work.pdf 2012 STANDARD SPECIFICATIONS FOR CONSTRUCTION - SECTION 103]</center>
 +
<div style="text-align: center;">[mailto:Change?body=http://mdotwiki.state.mi.us/construction/index.php/Extending_Project_Limits Email this Page]</div>
 +
__forcetoc__
  
 +
==[[#Extending Project Limits | Extending Project Limits]]==
 +
 
 
As a rule, project limits should not be extended. Extending project limits after a project is advertised and subsequently awarded, may jeopardize federal funding and compromise the integrity of the competitive bidding process. Adequate project scoping should eliminate the need for project limit extensions.
 
As a rule, project limits should not be extended. Extending project limits after a project is advertised and subsequently awarded, may jeopardize federal funding and compromise the integrity of the competitive bidding process. Adequate project scoping should eliminate the need for project limit extensions.
  
Line 31: Line 33:
  
 
{{top}}
 
{{top}}
 +
 +
===[[#LAP Project Considerations | LAP Project Considerations]]===
 +
 +
LAP projects are subject to [http://mdotwiki.state.mi.us/construction/index.php?title=Extending_Project_Limits&action=edit#Extending_Project_Limits Extending Project Limits] guidance.
 +
 +
If an extenuating circumstance arises, the engineer and LRC must notify the DR immediately for assistance in following the process. 
 +
 +
{{top}}
 +
<div style="text-align: right;">[mailto:Change?body=http://mdotwiki.state.mi.us/construction/index.php/Extending_Project_Limits Email this Page]</div>
  
 
[[Category: Construction Manual]]
 
[[Category: Construction Manual]]
 
[[Category: Division 1]]
 
[[Category: Division 1]]
 
[[Category: Section 103]]
 
[[Category: Section 103]]

Revision as of 15:41, 29 July 2020

2012 STANDARD SPECIFICATIONS FOR CONSTRUCTION - SECTION 103
Email this Page


Extending Project Limits

As a rule, project limits should not be extended. Extending project limits after a project is advertised and subsequently awarded, may jeopardize federal funding and compromise the integrity of the competitive bidding process. Adequate project scoping should eliminate the need for project limit extensions.

If a project limit extension becomes necessary, the project engineer must comply with the National Environmental Protection Act, Michigan law, and requirements as set forth by the State Transportation Commission and the State Administrative Board. The Federal Highway Administration’s (FHWA) Michigan Division, must be consulted whenever a federally funded project’s limits are proposed to be extended, regardless of cost or oversight responsibilities. Failure to obtain environmental clearance from FHWA prior to extending project limits will result in a loss of federal funds for the additional work, and may result in a loss of federal funds for the entire project.

The region engineer shall approve the initiation of the procedures and the request for the project limit extension. This approval, with supporting justification, must accompany the contract modification for the extension.

If the additional work is equal to or less than $100,000, the existing contract modification procedures apply. Contract modifications involving project limit extensions must be processed through the Construction and Technology Support Area (C&T)’s Construction Contracts Unit. The Engineer of Construction and Technology and C&T’s two region liaisons will determine whether the request will be denied or accepted for further processing. The Engineer of Construction and Technology will notify the requestor of a denial or acceptance within five business days.

If the additional work is greater than $100,000 on existing contracts, Michigan law requires the work must be competitively bid and approved by the State Transportation Commission and the State Administrative Board before work is started. The department may consider an exception if an alternative to competitive bidding is in the public’s best interest.

MDOT must give 90 days notice to the State Transportation Commission, and both the Senate and House Transportation Appropriations Subcommittees before work is started on projects that qualify for the exception. The region engineer must provide documentation that sets forth the public interest findings. An exception to the 90-day-notice requirement applies only if the department determines emergency action is required. The region engineer must provide documentation that sets forth justification for an emergency determination.

If it becomes necessary to consider extending an existing project beyond the original project limits, project administration must comply with the above procedures. The region engineer must provide documentation that sets forth the public interest findings or justification for an emergency determination. Send the documentation to C&T’s Construction Contracts Unit. They will review it and submit it for approval from the Attorney General, State Transportation Commission, and/or State Administrative Board.

[top of page]


LAP Project Considerations

LAP projects are subject to Extending Project Limits guidance.

If an extenuating circumstance arises, the engineer and LRC must notify the DR immediately for assistance in following the process.