Difference between revisions of "Main Page"

From MediaWiki
Jump to navigation Jump to search
(→‎Recent Minor Changes: Adjust Format of Minor Change Table to include "Date" and "Compare It")
(→‎Recent Major Changes: Adjust Format of Minor Change Table to include "Date" and "Compare It")
Line 53: Line 53:
 
{| class="wikitable" style="background:orange; color:black"
 
{| class="wikitable" style="background:orange; color:black"
 
|-
 
|-
!Division !! Section !! Summary
+
!Updated!! Division !! Section !! Summary !! What Changed
|-  http://mdotwiki.state.mi.us/construction/index.php/
 
|Division 7  ||[[718_-_Drilled_Shafts#Concrete.2C_Grade_S2.2C_and_Grade_T|<center>718</center>]] ||Text added to provide guidance and emphasis on modified slump requirements for drilled shaft foundations.
 
 
|-
 
|-
|-  http://mdotwiki.state.mi.us/construction/index.php/
+
|<center>3/23/2017</center>||<center>1</center>||<center>[[109_-_Measurement_and_Payment#DOCUMENTING_PRICE_NEGOTIATIONS|109]]</center>||Incorporated information part of '''CA 2015-14''' for DOCUMENTING PRICE NEGOTIATIONS||[https://mdotwiki.state.mi.us/construction/index.php?title=109_-_Measurement_and_Payment&diff=4394&oldid=4317 Compare It]
|Division 1 ||[[103_-_Scope_of_Work#EXTENDING_PROJECT_LIMITS|<center>103</center>]] || Incorporated [http://www.michigan.gov/documents/MDOT_IM05-07_125120_7.pdf?20151002093618 BOH-IM 2005-07] '''Extending Project Limits'''
 
 
|-
 
|-
|Division 1  ||[[103_-_Scope_of_Work#Jobsite_Poster_Compliance_Adjustment|<center>103</center>]] || Incorporated [http://mdotcf.state.mi.us/public/dessssp/spss_source/12SP208(A)v1.pdf guidance for 12SP150(A)-01] '''NON-COMPLIANCE WITH SOIL EROSION AND SEDIMENTATION CONTROL REQUIREMENTS'''
 
|-
 
|Division 8  ||[[819_-_Electrical_and_Lighting#MATERIALS|<center>819</center>]] || Incorporated  [http://www.michigan.gov/documents/mdot/CA_2015-02_482041_7.pdf CA2015-02] '''Electrical Lighting & Conduit''' with minor revision of hyperlink
 
|-
 
|Division 1  ||[[Other#Contract_Administration_and_Oversight_Guidelines_for_Intelligent_Transportation_Systems_Projects|<center>Division 1 Other</center>]] || Incorporated [http://www.michigan.gov/documents/mdot/MDOT_IM11-03_359946_7.pdf BOH-IM 2011-03] '''Contract Administration and Oversight Guidelines for Intelligent Transportation Systems Projects'''
 
|-
 
|Division 1  ||[[107_-_Legal_Relations_and_Responsibility_to_the_Public#Licensed_Electrician_Required_on_Electrical_Work|<center>107</center>]] || Incorporated [http://www.michigan.gov/documents/mdot_IM05-01_113135_7.pdf BOH-IM 2005-01] '''Licensed Electrician Required on Electrical Work'''
 
|-
 
|Division 1  ||[[103_-_Scope_of_Work#Unacceptable_Plant_Adjustment|<center>103</center>]] || Added adjustment language and pay item code
 
|-
 
| Division 8  ||[[811_-_Permanent_Pavement_Markings|<center>811</center>]] || Incorporated[http://www.michigan.gov/mdot/0,1607,7-151-9622_11044_20469---,00.html BOH-IM 2014-07] '''Construction Guidance for Pavement Marking Projects''' (incorporated into the Construction Manual, Division 8, Section 811)
 
|-
 
| Division 8  ||[[803_-_Concrete_Sidewalk,_Ramps,_and_Steps|<center>803</center>]] ||Added video from Federal Aid Essentials - Americans with Disabilities Act (ADA) Requirements for Resurfacing Projects
 
|-
 
| Division 7  ||[[707_-_Structural_Steel|<center>707</center>]] ||Complete re-write compared to the 2003 Construction Manual
 
|-
 
| Division 7  ||[[713_-_Bridge_Rehabilitation,_Steel|<center>713</center>]]  || Complete re-write compared to the 2003 Construction Manual
 
|-
 
|Division 7  ||[[708_-_Precast_Concrete_Beams_(Prestressed)|<center>708</center>]]  || Complete re-write compared to the 2003 Construction Manual
 
|-
 
|Division 7  || [[707_-_Structural_Steel|<center>707</center>]] || Complete re-write compared to the 2003 Construction Manual
 
|-
 
|Division 7  || [[713_-_Bridge_Rehabilitation,_Steel|<center>713</center>]] || Complete re-write compared to the 2003 Construction Manual
 
|-
 
|Division 7  || [[716_-_Shop_Cleaning_and_Coating_Structural_Steel|<center>716</center>]] || Complete re-write compared to the 2003 Construction Manual
 
|-
 
|Division 7  || [[710_-_Waterproofing_and_Protective_Covers|<center>710</center>]] || Complete re-write compared to the 2003 Construction Manual
 
|-
 
|Division 7  || [[712_-_Bridge_Rehabilitation,_Concrete|<center>712</center>]] || Complete re-write compared to the 2003 Construction Manual
 
 
|}
 
|}
  

Revision as of 14:22, 23 March 2017

www.michigan.gov/mdot


CONSTRUCTION MANUAL


Logo.jpg


Bureau of Field Services
Construction Field Services Division
I-96. Cascade Rd. Diverging Diamond Interchange project in Grand Rapids, Kent County.
Construciton on Bridge decks on the Square Lake Rd. Interchange project.
Construction work on the M-1 Rail Woodward Ave.

Foreword

This manual has been prepared to give information and guidance to construction project personnel associated with the Michigan Department of Transportation (MDOT). It is not a part of any contract and therefore is not binding on the contractor. In case of conflict between the Standard Specifications for Construction or contract documents and this manual, the specifications and contract documents will have precedence.


This manual has been revised throughout to incorporate changes brought about by the release of the 2012 Standard Specifications for Construction and by progress in equipment, construction practices, and materials. The format has been established to follow the standard specification outline with divisions and sections set up to facilitate revision and addition of new information as needed.


Additional information about the Wiki Construction Manual and submitting revision suggestions is located in the Help:Contents page.


Since it's release in April of 2014 there are a total of 5,270 registered users of the MDOT Construction Manual.

[top of page]


MDOT Mission Statement

Providing the highest quality integrated transportation services for economic benefit and improved quality of life.

[top of page]


General Information

Current News

With the first release of the MDOT Wiki Construction Manual there are bound to be some errors. If you find an error on a page please contact the Content Manager for that particular Division located here in the Help page. Some sections are still undergoing content revisions, most have been identified by the Content Managers and are noted as such in the Wiki Constrution Manual.


Content will be revised frequently and a way to monitor what changes have occured recently is by using the Recent changes page. This page will show all major and minor edits along with new users that were created. Pretty much everything that goes on in the Construction Manual. For a more specific listing of content changes you will want to see the Recent Major Changes page or Recent Minor Changes page which contain manually updated lists of content changes for specific sections of the Construction Manual.

[top of page]


Recent Major Changes

The table below is a list of Major changes.

Updated Division Section Summary What Changed
3/23/2017
1
109
Incorporated information part of CA 2015-14 for DOCUMENTING PRICE NEGOTIATIONS Compare It


A definition to the types of changes that you might see in the Construction Manual can be found under Content Revision Procedures, Types of Changes.

[top of page]


Recent Minor Changes

The table below is a list of Minor changes.

Updated Division Section Summary What Changed
3/23/2017
1
109
Incorporated information part of CA 2015-14 for DOCUMENTING PRICE NEGOTIATIONS Compare It