Difference between revisions of "102.02 Contents of Proposal - Progress Clause"

From MediaWiki
Jump to navigation Jump to search
(→‎Progress Clause: Updated Guardrail - Steel Lead Times)
(29 intermediate revisions by 3 users not shown)
Line 2: Line 2:
  
 
==[[#Progress Clause|Progress Clause]]==
 
==[[#Progress Clause|Progress Clause]]==
:''Note: for projects containing structural steel please see [[707_-_Structural_Steel#Project_Scheduling|Section 707 - Structural Steel Project Scheduling]]''
 
<center>[http://mdotcf.state.mi.us/public/specbook/files/2012/102%20Bid%20Sub,%20Award,%20Exec%20Contr.pdf Spec Book Section 102]</center>
 
  
 
The progress clause is intended to specify the construction timing and schedule requirements to the contractor.  The progress clause is provided by the Construction Engineer at the Omissions and Errors Check (OEC) meeting.  This document provides the project start and completion dates as well as any interim dates (e.g. open to traffic, staging, milestone)  The contractor is required to prepare a progress schedule for submittal that incorporates the project dates as noted in the progress clause.  Traffic requirements and liquidated damages are not to be described in detail in the progress clause.  However, the progress clause must mention that failure to meet the specified date(s) will result in the assessment of liquidated damages as specified in other contract documents.
 
The progress clause is intended to specify the construction timing and schedule requirements to the contractor.  The progress clause is provided by the Construction Engineer at the Omissions and Errors Check (OEC) meeting.  This document provides the project start and completion dates as well as any interim dates (e.g. open to traffic, staging, milestone)  The contractor is required to prepare a progress schedule for submittal that incorporates the project dates as noted in the progress clause.  Traffic requirements and liquidated damages are not to be described in detail in the progress clause.  However, the progress clause must mention that failure to meet the specified date(s) will result in the assessment of liquidated damages as specified in other contract documents.
Line 13: Line 11:
 
Progress clause documentation must also take this 12 month acceptance period into account for final project completion dates. The contractor must have time to complete the required measurements and perform any corrective action that is required. It is suggested that an additional 60 days be included on these projects in addition to the 12 month period to allow for completion of corrective action.
 
Progress clause documentation must also take this 12 month acceptance period into account for final project completion dates. The contractor must have time to complete the required measurements and perform any corrective action that is required. It is suggested that an additional 60 days be included on these projects in addition to the 12 month period to allow for completion of corrective action.
  
 +
The table below details the recommended timelines for delivery and procurement of typical long-lead items. When developing the Progress Clause dates, consider these timelines as they can have a significant impact on the constructability of a project. Considerations should also be made for any procurement times associated with unique special provisions where certain manufacturers or products are specified. More information regarding steel superstructure is provided [[102.02_Contents_of_Proposal_-_Progress_Clause#Progress_Clause_for_Steel_Superstructure_Projects|here.]]
  
{{top}}
 
===[[#Boilerplate Progress Clause|Boilerplate Progress Clause]]===
 
 
The file link provided below is intended to serve as a boilerplate document for creating a progress clause.  Text is to be reviewed, deleted, modified, or added before incorporation into the proposal document.
 
 
[[File:Boilerplate Progress Clause Template 12-6-17.docx]]
 
 
The link will take you to a separate page to download the file.
 
 
{{top}}
 
 
===[[#Progress Clauses with Incentive or A+B Schedules|Progress Clauses with Incentive or A+B Schedules]]===
 
 
Incentive special provisions provide monetary amounts for completion of work before specified contract dates.  These special provisions, if applicable, are to be referenced in the progress clause for successfully meeting dates or times, but the specific incentive requirements and monetary amounts are to be included in a unique special provision.  The special provision is to be titled Special Provision for Incentive, (Route (Structure Number)), (Incentive Type).  The structure number is only to be included on bridge projects and if the bridge has an associated incentive.  Incentive types are:  Completion of Work; Interim Completion of Work; and Open to Traffic.  Incentive projects are to include the Special Provision for  [https://mdotcf.state.mi.us/public/dessssp/spss_source/12SP-108A-02.pdf Extension of Time and Increased Costs for Incentive Projects].
 
 
MDOT is phasing out the disincentive terminology.  This language simply references failure to meet the contract incentive requirements.  The disincentive language is not to be used on construction oversight documentation.  Not meeting the incentive requirements will result in the application of liquidated damages and the associated pay item “Liquidated Damages, Other”.
 
 
The calculation of incentive values based on user delay costs must be documented and placed in the appropriate project folder in the ProjectWise directory.
 
 
[[file:Figure 102-2.JPG|thumb|center|600px|Figure 102-2 - Work Day/Completion Date Determination]]
 
 
<div style="text-align: right;">[mailto:Change?body=http://mdotwiki.state.mi.us/construction/index.php/102.02_Contents_of_Proposal Email this Page]</div>
 
{{top}}
 
 
===[[#Determination of Work Days/Completion Date|Determination of Work Days/Completion Date]]===
 
 
Work Day/Completion Date Determination, '''''Figure 102-2''''', shows the worksheet to be used for calculating the estimated time to complete major work items and arrive at the total work days/completion date for completion of all work items.  Anticipated start dates should consider letting date and earliest possible award dates to avoid an unrealistic completion date on calendar day date projects. This worksheet should remain on file at the project office and become part of the permanently retained project files for audit purposes.
 
<div style="text-align: right;">[mailto:Change?body=http://mdotwiki.state.mi.us/construction/index.php/102.02_Contents_of_Proposal Email this Section]</div>
 
{{top}}
 
===[[#Critical Path Networks|Critical Path Networks]]===
 
 
Critical Path Networks are often needed to develop the Progress Clause for a project.  With MDOT-designed projects, the project manager is required to develop a Critical Path Network on any project that includes an Incentive or Special Liquidated Damages clause.  It is recommended that the project manager develop a Critical Path Network for projects with the following characteristics:
 
  
 
{| class="wikitable"
 
{| class="wikitable"
 
|-
 
|-
 
! colspan="2" |
 
! colspan="2" |
<center>'''Critical Path Network Project Characteristics'''</center>
+
<center>'''Typical Long-Lead Items'''</center>
|-
 
|
 
<center>1</center>
 
|
 
New construction.
 
|-
 
|
 
<center>2</center>
 
|
 
Major reconstruction or rehabilitation on an existing roadway that will severely disrupt traffic.
 
|-
 
|
 
<center>3</center>
 
|
 
Unique or experimental work.
 
|-
 
|
 
<center>4</center>
 
|
 
More than one construction season.
 
|-
 
|
 
<center>5</center>
 
|
 
Complex staging (multiple stages with traffic shifts).
 
|}
 
 
 
There may be other projects that do not meet these criteria which should have a Critical Path Network.  The project manager will need to evaluate each project separately.  The appropriate construction staff Engineer from the Construction Section and the Engineer assigned to the project should be consulted when determining the need for and when developing a Critical Path Network.
 
 
 
Preparation of a Critical Path Network is a requirement on all consultant-designed projects, regardless of the project type or complexity.  The Engineer should contact the Design Consultant Coordination Unit for the project's critical path, if they have not received it, to prepare the Progress Clause.
 
 
 
{{top}}
 
 
 
===[[#Critical Path - Construction Time Estimates|Critical Path - Construction Time Estimates]]===
 
 
 
The following are average production rates for major work items which, when multiplied or divided by the work item quantities on a project, determine the estimated time (in workdays) to complete an item. These rates should be used as guides and adjusted as necessary to reflect project specific issues and concerns or previous work history in the project area.
 
 
 
{| class="wikitable"
 
|-
 
! colspan="2" |
 
<center>'''Drainage'''</center>
 
 
|-
 
|-
 
!
 
!
 
<center>'''Work Item'''</center>
 
<center>'''Work Item'''</center>
 
!
 
!
<center>'''Time'''</center>
+
<center>'''Lead Time
 +
(includes typical timeframes for development and review of procurement, shop drawings, fabrication, and delivery)
 +
'''</center>
 
|-
 
|-
 
|
 
|
Cross Culverts
+
Steel Plate Girders and Rolled Beams – with flange thicknesses less than three inches
* Rural Highways
 
* Expressways
 
* Large Headwalls
 
* Slab or Box Culverts
 
* Plowed-In Edge Drain (production type project)
 
* Open-Graded Underdrain (production-type project)
 
 
|
 
|
 
+
26 weeks
 
 
130 ft/day
 
 
 
160 ft/day
 
 
 
5 days/unit
 
 
 
5 days/pour
 
 
 
14,800 ft/day
 
 
 
3,940 ft/day
 
|-
 
|
 
Sewers
 
* 0-6 ft (up to 60 inches)
 
* 0-6 ft (over 60 inches)
 
* 6 ft-over (up to 60 inches)
 
* 6 ft-over (over 60 inches)
 
* Jacked-In-Place
 
** Including excavation pit and set up
 
* Tunnels
 
** Hand Mining
 
** Machine Mining
 
** Including excavation pit and set up
 
|
 
 
 
 
 
130 ft/day
 
 
 
80 ft/day
 
 
 
80 ft/day
 
 
 
65 ft/day
 
 
 
40 ft/day
 
 
 
min. 5 days
 
 
 
 
 
25 ft/day
 
 
 
65 ft/day
 
 
 
min. 5 days
 
|-
 
|
 
Manholes
 
|
 
3 units/day
 
|-
 
|
 
Catch Basins
 
|
 
4 units/day
 
|}
 
 
{| class="wikitable"
 
|-
 
! colspan="2" |
 
<center>'''Utilities'''</center>
 
|-
 
!
 
<center>'''Work Item'''</center>
 
!
 
<center>'''Time'''</center>
 
|-
 
|
 
Water Main (up to 16 inches)
 
* Flushing, Testing and Chlorination
 
|
 
330 ft/day
 
4 days
 
 
|-
 
|-
 
|
 
|
Water Main (20 to 40 inches)
+
Bascule, Arch, Tub Girder, High Performance Steel, Plate Girders and Rolled Beams – with flange thicknesses three inches or greater
* Flushing, Testing and Chlorination
 
 
|
 
|
80 ft/day
+
Consult Structural Fabrication Unit
5 days
 
 
|-
 
|-
 
|
 
|
Order and Deliver 24 inch HP Water Main
+
Steel Pipe pile in excess of 14 inches diameter, and HP shapes greater than 14 inches in depth.
 
|
 
|
50 days/order
+
12 weeks
|-
 
|
 
Gas Lines
 
|
 
330 ft/day
 
|}
 
 
 
{| class="wikitable"
 
|-
 
! colspan="3" |
 
<center>'''Earthwork and Grading'''</center>
 
|-
 
!
 
<center>'''Work Item'''</center>
 
!
 
<center>'''Metro Exp-Time'''</center>
 
!
 
<center>'''Rural-Time'''</center>
 
|-
 
|
 
Embankment (CIP)
 
|
 
2000 yd<sup>3</sup>/day
 
|
 
7000 yd<sup>3</sup>/day
 
|-
 
|
 
Excavation and/or Embankment (Freeway)
 
|
 
2000 yd<sup>3</sup>/day
 
|
 
12,000 yd<sup>3</sup>/day
 
|-
 
|
 
Excavation and/or Embankment (Reconst)
 
|
 
1000 yd<sup>3</sup>/day
 
|
 
5000 yd<sup>3</sup>/day
 
|-
 
|
 
Embankment (Lightweight Fill)
 
|
 
400 yd<sup>3</sup>/day
 
|
 
800 yd<sup>3</sup>/day
 
|-
 
|
 
Muck (Excavated Waste and Backfill)
 
|
 
 
 
|
 
2000 yd<sup>3</sup>/day
 
|-
 
|
 
Excavation (Widening)
 
|
 
 
 
|
 
800 yd<sup>3</sup>/day
 
|-
 
|
 
Grading (G and DS)
 
|
 
 
 
|
 
1000 yd<sup>3</sup>/day
 
|-
 
|
 
Subbase and Selected Subbase (up to 7.4 m)
 
|
 
 
 
|
 
800 yd<sup>3</sup>/day
 
|-
 
|
 
Subbase and Selected Subbase (7.4 m and over)
 
|
 
 
 
|
 
600 yd<sup>3</sup>/day
 
|-
 
|
 
Subgrade Undercut and Backfill
 
|
 
 
 
|
 
2000 yd<sup>3</sup>/day
 
|-
 
|
 
Subbase and Open-Graded Drainage Course
 
|
 
 
 
|
 
600 yd<sup>3</sup>/day
 
|}
 
 
 
{| class="wikitable"
 
|-
 
! colspan="2" |
 
<center>'''Surfacing - Concrete'''</center>
 
 
 
|-
 
!
 
<center>'''Work Item'''</center>
 
 
 
!
 
<center>'''Time'''</center>
 
 
 
|-
 
|
 
Concrete Pavement (24 ft)
 
 
 
* Including Forming and Curing
 
 
 
|
 
540 yd<sup>2</sup>/day
 
 
 
min. 7 days
 
 
 
|-
 
|
 
Pavement (24 ft)
 
 
 
|
 
3940 ft/day/course
 
 
 
|-
 
|
 
Concrete Ramps (16 ft)
 
 
 
* Including Forming and Curing
 
 
 
|
 
980 ft/day
 
 
 
min. 7 days
 
 
 
|-
 
|
 
Curb (1 side)
 
 
 
|
 
2460 ft/day
 
 
 
|-
 
|
 
Concrete Shoulder - Median
 
 
 
|
 
1400 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Sidewalk (Patching)
 
 
 
|
 
80 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Sidewalk
 
 
 
|
 
220 yd<sup>2</sup>/day
 
 
 
|}
 
 
 
 
 
{| class="wikitable"
 
|-
 
! colspan="2" |
 
<center>'''Structures'''</center>
 
|-
 
!
 
<center>'''Work Item'''</center>
 
!
 
<center>'''Time'''</center>
 
|-
 
|
 
Sheeting (Shallow)
 
|
 
100 ft/day
 
|-
 
|
 
General Excavation at Bridge Site
 
|
 
1000 yd<sup>3</sup>/day
 
|-
 
|
 
Excavation for Substructure (Footings)
 
|
 
1 unit/day
 
|-
 
|
 
Piles (40 ft)
 
|
 
15 piles/day
 
|-
 
|
 
Substructure (Piers and Abutments)
 
|
 
5 days/unit
 
|-
 
|
 
Order and Delivery of Beams
 
* Plate Girders
 
* Rolled Beams
 
|
 
 
 
100-120 days/order
 
 
 
90-120 days/order
 
 
 
 
|-
 
|-
 
|
 
|
 
Concrete Beams
 
Concrete Beams
 
|
 
|
50 days/order
+
8 to 12 weeks
|-
 
|
 
Erection of Structural Steel
 
|
 
3 days/span
 
|-
 
|
 
Bridge Decks
 
* Form and Place Reinforcement (200 ft Structure)
 
* Pour Deck Slab (1 1/5 days pour)
 
* Cure
 
|
 
 
 
15 days
 
 
 
2 days/span
 
 
 
14 days
 
 
 
|-
 
|
 
2 Course Bridge Decks
 
* Add 9 days for Second Course Latex
 
* Add 12 days for Second Course Low Slump
 
|
 
 
 
|-
 
|
 
Sidewalks and Railings
 
* Sidewalks and Parapets
 
* Slip Formed Barriers
 
|
 
 
 
5 days/span
 
 
 
2 days/span
 
 
 
 
|-
 
|-
 
|
 
|
Clean Up
+
Mast Arms / Strain Poles
 
|
 
|
10 days
+
25 weeks
 
|-
 
|-
 
|
 
|
Pedestrian Fencing
+
Concrete Spun Poles
* Shop Plan Approval and Fabrication
 
* Erection
 
 
|
 
|
 
+
14 weeks
1-2 months
 
 
 
1 week/bridge
 
 
 
 
|-
 
|-
 
|
 
|
Riprap Replacement
+
Lighting Towers
* Bucket Dumped
 
* Bucket Dumped and Hand Finished
 
 
|
 
|
 
+
25 weeks
500 yd<sup>3</sup>/day
 
 
 
170 - 680 yd<sup>3</sup>/day
 
 
 
|}
 
 
 
 
 
{| class="wikitable"
 
|-
 
! colspan="2" |
 
<center>'''Retaining Walls'''</center>
 
 
 
|-
 
!
 
<center>'''Work Item'''</center>
 
 
 
!
 
<center>'''Time'''</center>
 
 
 
 
|-
 
|-
 
|
 
|
Retaining Walls
+
Intelligent Transportation Systems (ITS) projects and components
 
 
 
|
 
|
1 panel/day
+
Consult ITS Program Office
 
 
min. 10 days
 
 
 
|}
 
 
 
 
 
{| class="wikitable"
 
|-
 
| colspan="2" |
 
<center>'''Railroad Structures'''</center>
 
 
 
 
|-
 
|-
 
|
 
|
<center>'''Work Item'''</center>
+
Delineator and 3# U-Channel Posts
 
 
 
|
 
|
<center>'''Time'''</center>
+
21 to 34 weeks
 
 
 
|-
 
|-
 
|
 
|
Grade Temporary Runaround
+
Barrier Gates
 
 
 
|
 
|
1000 yd<sup>3</sup>/day
+
5 to 10 weeks - Consult Work Zone Delivery Engineer
 
 
 
|-
 
|-
 
|
 
|
Ballast, Ties and Track
+
Work Zone Speed Trailers
 
 
 
|
 
|
160 ft/day
+
5 to 10 weeks - Consult Work Zone Delivery Engineer
 
 
 
|-
 
|-
 
|
 
|
Place Deck Plates
+
Guardrail - Steel
 
 
 
|
 
|
5 days/span
+
10 Gauge: 8 weeks<br>
 
+
12 Gauge: 8 weeks
 
|-
 
|-
 
|
 
|
Waterproof, Shotcrete and Mastic
+
Controller Cabinet and Detection Equipment
 
 
 
|
 
|
5 days/span
+
8-12 weeks includes procurement and TSMO bench review
 
 
 
|}
 
|}
  
 +
{{top}}
 +
===[[#Boilerplate Progress Clause|Boilerplate Progress Clause]]===
  
{| class="wikitable"
+
The file link provided below is intended to serve as a boilerplate document for creating a progress clause.  Text is to be reviewed, deleted, modified, or added before incorporation into the proposal document.
|-
 
! colspan="2" |
 
<center>'''Railroad Crossing Reconstruction'''</center>
 
 
 
|-
 
!
 
<center>'''Work Item'''</center>
 
  
!
+
[https://mdotwiki.state.mi.us/images_construction/6/68/Boilerplate_Progress_Clause_Template_June_2021.docx Boilerplate Progress Clause Template June 2021]
<center>'''Time'''</center>
 
  
|-
+
{{top}}
|
 
Railroad Crossing Reconstruction
 
  
|
+
===[[#Progress Clauses with Incentive or A+B Schedules|Progress Clauses with Incentive or A+B Schedules]]===
10-15 workdays (depends whether concrete base is involved)
 
  
|}
+
Incentive special provisions provide monetary amounts for completion of work before specified contract dates.  These special provisions, if applicable, are to be referenced in the progress clause for successfully meeting dates or times, but the specific incentive requirements and monetary amounts are to be included in a unique special provision.  The special provision is to be titled Special Provision for Incentive, (Route (Structure Number)), (Incentive Type).  The structure number is only to be included on bridge projects and if the bridge has an associated incentive.  Incentive types are:  Completion of Work; Interim Completion of Work; and Open to Traffic.  Incentive projects are to include the Special Provision for  [https://mdotcf.state.mi.us/public/dessssp/spss_source/12SP-108A-02.pdf Extension of Time and Increased Costs for Incentive Projects].
  
 +
MDOT is phasing out the disincentive terminology.  This language simply references failure to meet the contract incentive requirements.  The disincentive language is not to be used on construction oversight documentation.  Not meeting the incentive requirements will result in the application of liquidated damages and the associated pay item “Liquidated Damages, Other”.
  
{| class="wikitable"
+
The calculation of incentive values based on user delay costs must be documented and placed in the appropriate project folder in the ProjectWise directory.
|-
 
| colspan="2" |
 
<center>'''Temporary Railroad Structures'''</center>
 
  
|-
+
<div style="text-align: right;">[mailto:Change?body=http://mdotwiki.state.mi.us/construction/index.php/102.02_Contents_of_Proposal Email this Page]</div>
|
+
{{top}}
<center>'''Work Item'''</center>
 
 
 
|
 
<center>'''Time'''</center>
 
 
 
|-
 
|
 
Order and Deliver Steel
 
 
 
|
 
55 days/order
 
  
|-
+
===[[#Progress Clause for Steel Superstructure Projects|Progress Clause for Steel Superstructure Projects]]===
|
+
This document provides guidance to the TSC construction/project engineer in determining contract milestones for the progress clause in projects requiring steel beams or steel girders, and large format steel foundation piling. This formation is to be used to estimate timeframes for the progress clause for the order and delivery of steel piling, and beams/girders after the project award.
Erect Steel
 
  
|
+
Once a bridge project is awarded, the contractor will place an order with a structural steel fabricator. The structural steel fabricator will then need to place an order with a steel mill for the required plates and shapes.  The steel mills produce heats of different types and sizes of steel.  For example, a mill may produce 36-inch rolled beams one week and piling the following week, and other mills may exclusively produce plates, but only roll certain thicknesses once or twice a month.  Structural steel rolled in a given heat is typically already devoted to an already placed order, and the mill rolling typically occurs between four to twelve weeks after the order has been placed.  Many factors influence when a fabricator can take delivery from a mill, including demand from other states’ bridge programs, demand from other domestic and international industries, cost, availability, and stockpiles of raw material; and production status of mills around the country.  Fabricators do not stockpile most types of beams or plate steel.  This is consistent with the just-in-time concept of manufacturing common in industry today.
1 day/span
 
  
|-
+
For some small orders or certain types of steel, such as pin and hangers (link plates and pins), fabricators can purchase the needed steel through warehouses or they may have their own supply.  For emergencies, such as from a high load impact, fabricators can purchase the needed steel items from national warehouses.  However, the cost of this steel may be much higher, and is not economically feasible (to the fabricator or the state) for large orders.
|
 
Ties and Track
 
  
|
+
The table below details the recommended timelines in which steel delivery to the project site can be expected.
3 days/span
 
  
|}
 
  
 
+
<center>'''Table 707.1'''</center>
{| class="wikitable"
+
{| class="wikitable" style="margin: auto;"
 
|-
 
|-
! colspan="2" |
+
! Work Item – Order and Delivery of Steel Beams !! Time
<center>'''Pump House'''</center>
 
 
 
 
|-
 
|-
!
+
| Plate Girders and Rolled Beams – with flange thicknesses less than three inches
<center>'''Work Item'''</center>
+
|| 26 weeks after award
 
 
!
 
<center>'''Time'''</center>
 
 
 
|-
 
|
 
Structure
 
 
 
|
 
30 days/yd
 
 
 
 
|-
 
|-
|
+
| Bascule, Arch, Tub Girder, High Performance Steel (HPS Grade 70 or 100), Plate Girders and Rolled Beams – with flange thicknesses three inches or greater|| Consult Structural Fabrication Unit(*)
Order and Deliver Electrical and Mechanical Equipment
 
 
 
|
 
90 days
 
 
 
 
|-
 
|-
|
+
|Pipe pile in excess of 14 inches nominal diameter, and HP shapes greater than 14 inches in depth.
Install Electrical and Mechanical Equipment
+
||12 weeks after award
 
 
|
 
30 days
 
 
 
 
|}
 
|}
  
{| class="wikitable"
 
|-
 
! colspan="2" |
 
<center>'''Miscellaneous'''</center>
 
  
|-
+
:*Contact the Operations Field Services Division’s Structural Fabrication Unit ([mailto:MDOT-StructuralFabrication@michigan.gov MDOT-StructuralFabrication@michigan.gov]) for assistance in developing the timeframes for order and delivery of steel in preparing the progress clause.
!
 
<center>'''Work Item'''</center>
 
  
!
 
<center>'''Time'''</center>
 
  
|-
+
For plate girders and rolled beams with flange thicknesses less than three inches, the recommended time from award to delivery at the project site is based on the following:
|
 
Removing Old Pavement
 
  
|
+
* Up to three months for steel delivery from mill to fabricator,
200 ft/day
+
* Up to two months for fabrication,
 +
* Up to one month for submittal and approval of requests for information (RFI’s) and shop drawings, and shipping of the fabricated product to the project site.
  
|-
+
Smaller diameter pipe pile and pile shapes such as HP12 and HP14 are rolled by multiple steel mills on a regular basis and should be readily available. For pile sections greater than 14 inches in diameter or depth, such as HP16 and HP18 shapes, and 16 inch diameter pipe pile, there are fewer mills to choose from and the rolling schedules are less frequent. Therefore, the recommended time frame for those shapes is 12 weeks after award. This is based only on delivery since fabrication time and shop drawings are not required.
|
 
Removing Old Pavement for Recycling (24 ft)
 
  
|
+
While in many cases for structural steel, delivery can occur before the 26 week time frame, there are many variables which can influence steel delivery and frequently they cannot be determined at the time the progress clause is written. In addition to the factors influencing delivery of steel from the mill to the fabricator, the contractor that is awarded the contract and the fabricator they choose can affect the timeline. The fabricator chosen by the contractor may have less work or greater production capabilities than another fabricator. Some fabricators may try to book their production schedules such that by late winter or early spring they are fully booked through the summer or into fall. For this reason jobs let in the spring may have fewer fabricators available to complete the work and the jobs can be difficult to complete in one season especially if designed for part-width construction. In addition, the timeline to deliver steel beams for stage one of a part-width project may take the majority of the recommended timeline for delivery of both stages as the fabricator may elect to apply some aspects of fabrication to both stages instead of completing stage one in total before starting on stage two. The mill order and other milestones may take equal time whether they include one or both stages.
1480 ft/day
 
  
|-
+
For the reasons outlined above, it is recommended that the table above be used when developing progress clauses for projects with steel superstructures or large format piling. Careful consideration is to be made on projects with staged construction, or interim completion or interim open to traffic dates.
|
 
Crushing Old Concrete for 6A or OGDC
 
  
|
+
If you have any questions please contact the Structural Fabrication Unit at [mailto:MDOT-StructuralFabrication@michigan.gov MDOT-StructuralFabrication@michigan.gov].
1500 tons/day
 
  
|-
+
{{top}}
|
 
Removing Trees (Urban)
 
  
|
+
===[[#Contract Time Determination (CTD)|Contract Time Determination (CTD)]]===
15 units/day
+
Please refer to the Department’s [https://gcc01.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.michigan.gov%2Fmdot%2F0%2C4616%2C7-151-9622_11044_11367-501232--%2C00.html&data=04%7C01%7CMcGowanR%40michigan.gov%7Cbcaf79ee7a5d4c1783c408d8b19a8360%7Cd5fb7087377742ad966a892ef47225d1%7C0%7C0%7C637454624619662213%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=W4SdF1O0XxNFzTyXBnwA9qehoSym%2F1sJhmHEB%2FG3BGU%3D&reserved=0 Construction Scheduling Website.]
  
|-
+
{{top}}
|
 
Removing Trees (Rural)
 
  
|
+
===[[#Construction Time Estimates - Production Rates|Construction Time Estimates - Production Rates]]===
30 units/day
 
  
|-
+
The file link provided below contains production rates for major work items. The link will prompt you to download the file.
|
 
Removing Concrete Pavement
 
  
|
+
[//{{SERVERNAME}}/images_construction/a/a4/MDOT_Production_Rates.pdf MDOT Production Rates]
540 yd<sup>2</sup>/day
 
  
|-
+
[[File:MDOT Production Rates Image 07272020.jpg|center|600px|link=//{{SERVERNAME}}/images_construction/a/a4/MDOT_Production_Rates.pdf]]
|
 
Removing Sidewalk
 
  
|
+
These rates should be used as guides and adjusted as necessary to reflect project specific conditions (accessibility, site, traffic, region, quantities, etc.) and previous work history in the area. The rates include a low, average, and high production rate estimate which should serve as helpful guidance to both Design & Construction Engineers when developing and administering the project (evaluating schedules, progress clauses, force accounts, extra work, etc.). The rate range is intended to reflect & capture around 80% of typical projects, with the allowance that some outliers will exist due to extenuating project circumstances.
300 yd<sup>2</sup>/day
 
  
|-
+
{{top}}
|
 
Removing Curb and Gutter
 
  
|
+
===[[#LAP Project Considerations | LAP Project Considerations]]===
1480 ft/day
 
  
|-
+
Local agencies utilize the following boilerplate when developing their progress schedule:
|
 
Removing HMA Surface
 
  
|
+
::[https://mdotwiki.state.mi.us/images_construction/4/49/Progress_Clause_Template_LAP_projects_2020_Specs_FINAL_05192021_726007_7.pdf LAP PROJECT Boilerplate Progress Clause Template May 2021]
1910 yd<sup>2</sup>/day
 
  
|-
+
Local agencies are encouraged to utilize the resources in this section, such as product lead time and order and delivery estimate considerations when developing their progress schedule.  Anticipated start dates should consider letting date and award timeframes to avoid setting unrealistic starting or completion expectations.  Typically, MDOT let contracts are awarded within 49 days of letting.  Progress clause start dates should take this into account.
|
 
Conditioning Aggregate
 
  
|
+
Local agencies should keep in mind the lower rate estimates in MDOT Production Rates are often more applicable to the scale and complexity of LAP projects.
1080 yd<sup>2</sup>/day
 
  
|-
 
|
 
HMA Base Stabilizing
 
  
|
 
2990 yd<sup>2</sup>/day
 
  
|-
 
|
 
Ditching
 
  
|
 
1970 ft/day
 
  
|-
 
|
 
Trenching for Shoulders
 
  
|
 
2460 ft/day
 
  
|-
 
|
 
Station Grading
 
  
|
+
<div style="text-align: right;">[mailto:Change?body=http://mdotwiki.state.mi.us/construction/index.php/102.02_Contents_of_Proposal Email this Page]</div>
2000 ft/day
 
 
 
|-
 
|
 
Clearing
 
 
 
|
 
9570 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Restoration (Topsoil, Seeding, Fertilizer and Mulch)
 
 
 
|
 
1970 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Sodding
 
 
 
|
 
2510 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Seeding
 
 
 
|
 
47,800 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Guardrail
 
 
 
|
 
750 ft/day
 
 
 
|-
 
|
 
Fence (Woven Wire)
 
 
 
|
 
1180 ft/day
 
 
 
|-
 
|
 
Fence (Chain Link)
 
 
 
|
 
490 ft/day
 
 
 
|-
 
|
 
Cleanup
 
 
 
|
 
1970 ft/day
 
 
 
|-
 
|
 
Concrete Median Barrier
 
 
 
* Cure
 
 
 
|
 
980 ft/day
 
 
 
min. 7 days
 
 
 
|-
 
|
 
Reroute Traffic (Add 4 Days if 1st Item)
 
 
 
|
 
1 day/move
 
 
 
|-
 
|
 
Concrete Glare Screen
 
 
 
|
 
1480 ft/day
 
 
 
|-
 
|
 
Light Foundations
 
 
 
* Order and Delivery
 
 
 
|
 
6 units/day
 
 
 
6-8 weeks/order
 
 
 
|-
 
|
 
Remove Railing and Replace w/Barrier (1-2 Decks at a Time)
 
 
 
|
 
4 days/side
 
 
 
|-
 
|
 
Longitudinal Joint Repair
 
 
 
|
 
1910 ft/day
 
 
 
|-
 
|
 
Crack Sealing
 
 
 
|
 
15,750 ft/day
 
 
 
|-
 
|
 
Joint and Crack Sealing
 
 
 
|
 
1640 ft/day
 
 
 
|-
 
|
 
Repairing Pavement Joints - Detail 7 or 8
 
 
 
|
 
660 ft/day
 
 
 
|-
 
|
 
Seal Coat
 
 
 
|
 
21,000 lane ft/day
 
 
 
|-
 
|
 
Diamond Grinding/Profile Texturing Concrete
 
 
 
|
 
3950 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Rest Area Building
 
 
 
* Order Material
 
* Construct Building
 
 
 
|
 
 
 
 
 
3 months
 
 
 
9 months
 
 
 
|-
 
|
 
Tower Lights
 
 
 
* Order and Deliver Towers
 
 
 
|
 
 
 
 
 
100 days
 
 
 
|-
 
|
 
Weigh-In-Motion
 
 
 
* Order and Deliver Materials
 
* Order and Deliver with Installation
 
 
 
|
 
 
 
 
 
1 month-6 wks
 
 
 
3 months
 
 
 
|-
 
|
 
Raised Pavement Markers
 
 
 
|
 
300 ea/day
 
 
 
|-
 
|
 
Attenuators
 
 
 
|
 
2 ea/day
 
 
 
|-
 
|
 
Shoulder Corrugations, Ground or Cut
 
 
 
|
 
5 - 6 miles/side/day
 
 
 
|-
 
|
 
Aggregate Base
 
 
 
|
 
3120 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Aggregate Shoulder
 
 
 
|
 
380 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Freeway Signing - 3# Post Type
 
 
 
|
 
50 signs/day
 
 
 
|}
 
 
 
 
 
{| class="wikitable"
 
|-
 
! colspan="2" |
 
<center>'''Concrete Joint Repair'''</center>
 
 
 
|-
 
!
 
<center>'''Work Item'''</center>
 
 
 
!
 
<center>'''Time'''</center>
 
 
 
|-
 
|
 
Concrete Joint Repair
 
 
 
(High Production - Project with &gt;1000 patches)
 
 
 
* Average (6 ft)
 
* Large (&gt;6 ft)
 
 
 
|
 
50 patches/day
 
 
 
600 yd<sup>2</sup>/day
 
 
 
|}
 
 
 
 
 
 
 
 
 
{| class="wikitable"
 
|-
 
! colspan="2" |
 
<center>'''Structural Repair'''</center>
 
 
 
|-
 
!
 
<center>'''Work Item'''</center>
 
 
 
!
 
<center>'''Time'''</center>
 
 
 
|-
 
|
 
Bridge Painting
 
 
 
|
 
110 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Pin and Hanger Replacement
 
 
 
* Order Pin and Hanger
 
 
 
|
 
3 beams/day
 
 
 
60 days
 
 
 
|-
 
|
 
Scarifying (Including Cleanup)
 
 
 
|
 
12,000 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Joint Removal (Including Cleanup)
 
 
 
* Forming and Placement
 
 
 
|
 
13 ft/day
 
 
 
12 ft/day
 
 
 
|-
 
|
 
Hydro-Demolishing
 
 
 
|
 
980 ft/day
 
 
 
|-
 
|
 
Barrier Removal
 
 
 
* Placement
 
 
 
|
 
50 ft/day
 
 
 
150 ft/day
 
 
 
|-
 
|
 
Hand Chipping (Other than Deck)
 
 
 
|
 
0.24 yd<sup>3</sup>/person/day
 
 
 
|-
 
|
 
Casting Latex Overlay
 
 
 
|
 
820 ft/day
 
 
 
|-
 
|
 
Curing Overlay
 
 
 
* Regular
 
* High Early
 
 
 
|
 
 
 
 
 
4 days
 
 
 
1 day
 
 
 
|-
 
|
 
Thrie Beam Retrofit
 
 
 
|
 
100 ft/day
 
 
 
|-
 
|
 
Beam End Repairs
 
 
 
* Welded Repairs
 
* Bolted Repairs
 
* Bolted Stiffeners (Pair)
 
* Grind Beam Ends
 
* Welded Stiffeners (Pair)
 
* H-Pedestal Repairs
 
** Welded Repair
 
** Replacement
 
 
 
|
 
 
 
 
 
0.75 days/repair
 
 
 
0.50 days/repair
 
 
 
0.25 days/repair
 
 
 
0.25 days/repair
 
 
 
0.25 days/repair
 
 
 
 
 
 
 
0.50 days/repair
 
 
 
1 day/each
 
 
 
|-
 
|
 
Deck Removal
 
 
 
|
 
280 yd<sup>2</sup>/day
 
 
 
|}
 
 
 
 
 
 
 
 
 
{| class="wikitable"
 
|-
 
! colspan="2" |
 
<center>'''Surface - HMA'''</center>
 
 
 
|-
 
!
 
<center>'''Work Item'''</center>
 
 
 
!
 
<center>'''Time'''</center>
 
 
 
|-
 
|
 
Metro-Primary (&lt;20,000 tons)
 
 
 
* Paving
 
* Joints
 
* Cold Milling
 
* Aggregate Shoulders
 
 
 
|
 
 
 
 
 
600 tons/day
 
 
 
490 ft/day
 
 
 
4070 yd<sup>2</sup>/day
 
 
 
990 tons/day
 
 
 
|-
 
|
 
Metro-Primary (&gt;20,000 tons)
 
 
 
* Paving
 
* Joints
 
* Cold Milling
 
 
 
|
 
 
 
 
 
600 tons/day
 
 
 
650 ft/day
 
 
 
8970 yd<sup>2</sup>/day
 
 
 
|-
 
|
 
Metro-Interstate (&gt;20,000 tons)
 
 
 
* Paving
 
* Joints
 
* Aggregate Shoulders
 
 
 
|
 
 
 
 
 
1210 tons/day
 
 
 
1180 ft/day
 
 
 
990 tons/day
 
 
 
|-
 
|
 
Urban-Primary (&lt;20,000 tons)
 
 
 
* Paving
 
* Joints
 
* Cold Milling
 
* Rubblizing
 
* Aggregate Shoulders
 
 
 
|
 
 
 
 
 
710 tons/day
 
 
 
330 ft/day
 
 
 
2030 yd<sup>2</sup>/day
 
 
 
2030 yd<sup>2</sup>/day
 
 
 
500 tons/day
 
 
 
|-
 
|
 
Urban-Primary (&gt;20,000 tons)
 
 
 
* Paving
 
* Joints
 
* Cold Milling
 
* Aggregate Shoulders
 
 
 
|
 
 
 
 
 
1100 tons/day
 
 
 
390 ft/day
 
 
 
2030 yd<sup>2</sup>/day
 
 
 
550 tons/day
 
 
 
|-
 
|
 
HMA Shoulders (1 Side per Course)
 
 
 
|
 
2460 ft/day
 
 
 
|-
 
|
 
Urban-Interstate (&gt;20,000 tons)
 
 
 
* Paving
 
* Joints
 
* Cold Milling
 
* Rubblizing
 
* Aggregate Shoulders
 
 
 
|
 
 
 
 
 
1320 tons/day
 
 
 
720 ft/day
 
 
 
2030 yd<sup>2</sup>/day
 
 
 
6940 yd<sup>2</sup>/day
 
 
 
710 tons/day
 
 
 
|-
 
|
 
Rural-Primary (&lt;20,000 tons)
 
 
 
* Paving
 
* Joints
 
* Cold Milling
 
* Crush and Shape
 
* Aggregate Shoulders
 
 
 
|
 
 
 
 
 
710 tons/day
 
 
 
390 ft/day
 
 
 
650 tons/day
 
 
 
12,000 yd<sup>2</sup>/day
 
 
 
710 tons/day
 
  
|-
 
|
 
Rural-Primary (&gt;20,000 tons)
 
 
* Paving
 
* Joints
 
* Cold Milling
 
* Crush and Shape
 
 
|
 
 
 
1210 tons/day
 
 
490 ft/day
 
 
880 tons/day
 
 
12,000 yd<sup>2</sup>/day
 
 
|-
 
|
 
Rural-Interstate (&gt;20,000 tons)
 
 
* Paving
 
* Joints
 
 
|
 
 
 
1410 tons/day
 
 
720 ft/day
 
 
|}
 
<div style="text-align: right;">[mailto:Change?body=http://mdotwiki.state.mi.us/construction/index.php/102.02_Contents_of_Proposal Email this Page]</div>
 
{{top}}
 
 
[[Category:Construction Manual]]
 
[[Category:Construction Manual]]
 
[[Category:Division 1]]
 
[[Category:Division 1]]
 
[[Category:Section 102]]
 
[[Category:Section 102]]
 
[[Category:Pre-Construction]]
 
[[Category:Pre-Construction]]

Revision as of 15:38, 30 August 2021

Email this Page

Progress Clause

The progress clause is intended to specify the construction timing and schedule requirements to the contractor. The progress clause is provided by the Construction Engineer at the Omissions and Errors Check (OEC) meeting. This document provides the project start and completion dates as well as any interim dates (e.g. open to traffic, staging, milestone) The contractor is required to prepare a progress schedule for submittal that incorporates the project dates as noted in the progress clause. Traffic requirements and liquidated damages are not to be described in detail in the progress clause. However, the progress clause must mention that failure to meet the specified date(s) will result in the assessment of liquidated damages as specified in other contract documents.

If the project involves an expedited schedule, the progress clause is to include the language referenced in the Boilerplate Progress Clause.

The Special Provision for High-Tension Cable Barrier, 12SP807(F), requires corrective action for end terminal foundation movement exceeding one inch within 12 months of final cable tensioning. This requirement dictates that high-tension cable barrier projects must have delayed final acceptance. The final acceptance date must occur after the 12 month acceptance period for the barrier and after any corrective work required of the contractor. This will ensure specification compliance and allow the completion of any corrective actions.

Progress clause documentation must also take this 12 month acceptance period into account for final project completion dates. The contractor must have time to complete the required measurements and perform any corrective action that is required. It is suggested that an additional 60 days be included on these projects in addition to the 12 month period to allow for completion of corrective action.

The table below details the recommended timelines for delivery and procurement of typical long-lead items. When developing the Progress Clause dates, consider these timelines as they can have a significant impact on the constructability of a project. Considerations should also be made for any procurement times associated with unique special provisions where certain manufacturers or products are specified. More information regarding steel superstructure is provided here.


Typical Long-Lead Items
Work Item
Lead Time

(includes typical timeframes for development and review of procurement, shop drawings, fabrication, and delivery)

Steel Plate Girders and Rolled Beams – with flange thicknesses less than three inches

26 weeks

Bascule, Arch, Tub Girder, High Performance Steel, Plate Girders and Rolled Beams – with flange thicknesses three inches or greater

Consult Structural Fabrication Unit

Steel Pipe pile in excess of 14 inches diameter, and HP shapes greater than 14 inches in depth.

12 weeks

Concrete Beams

8 to 12 weeks

Mast Arms / Strain Poles

25 weeks

Concrete Spun Poles

14 weeks

Lighting Towers

25 weeks

Intelligent Transportation Systems (ITS) projects and components

Consult ITS Program Office

Delineator and 3# U-Channel Posts

21 to 34 weeks

Barrier Gates

5 to 10 weeks - Consult Work Zone Delivery Engineer

Work Zone Speed Trailers

5 to 10 weeks - Consult Work Zone Delivery Engineer

Guardrail - Steel

10 Gauge: 8 weeks
12 Gauge: 8 weeks

Controller Cabinet and Detection Equipment

8-12 weeks includes procurement and TSMO bench review

[top of page]


Boilerplate Progress Clause

The file link provided below is intended to serve as a boilerplate document for creating a progress clause. Text is to be reviewed, deleted, modified, or added before incorporation into the proposal document.

Boilerplate Progress Clause Template June 2021

[top of page]


Progress Clauses with Incentive or A+B Schedules

Incentive special provisions provide monetary amounts for completion of work before specified contract dates. These special provisions, if applicable, are to be referenced in the progress clause for successfully meeting dates or times, but the specific incentive requirements and monetary amounts are to be included in a unique special provision. The special provision is to be titled Special Provision for Incentive, (Route (Structure Number)), (Incentive Type). The structure number is only to be included on bridge projects and if the bridge has an associated incentive. Incentive types are: Completion of Work; Interim Completion of Work; and Open to Traffic. Incentive projects are to include the Special Provision for Extension of Time and Increased Costs for Incentive Projects.

MDOT is phasing out the disincentive terminology. This language simply references failure to meet the contract incentive requirements. The disincentive language is not to be used on construction oversight documentation. Not meeting the incentive requirements will result in the application of liquidated damages and the associated pay item “Liquidated Damages, Other”.

The calculation of incentive values based on user delay costs must be documented and placed in the appropriate project folder in the ProjectWise directory.

Email this Page

[top of page]


Progress Clause for Steel Superstructure Projects

This document provides guidance to the TSC construction/project engineer in determining contract milestones for the progress clause in projects requiring steel beams or steel girders, and large format steel foundation piling. This formation is to be used to estimate timeframes for the progress clause for the order and delivery of steel piling, and beams/girders after the project award.

Once a bridge project is awarded, the contractor will place an order with a structural steel fabricator. The structural steel fabricator will then need to place an order with a steel mill for the required plates and shapes. The steel mills produce heats of different types and sizes of steel. For example, a mill may produce 36-inch rolled beams one week and piling the following week, and other mills may exclusively produce plates, but only roll certain thicknesses once or twice a month. Structural steel rolled in a given heat is typically already devoted to an already placed order, and the mill rolling typically occurs between four to twelve weeks after the order has been placed. Many factors influence when a fabricator can take delivery from a mill, including demand from other states’ bridge programs, demand from other domestic and international industries, cost, availability, and stockpiles of raw material; and production status of mills around the country. Fabricators do not stockpile most types of beams or plate steel. This is consistent with the just-in-time concept of manufacturing common in industry today.

For some small orders or certain types of steel, such as pin and hangers (link plates and pins), fabricators can purchase the needed steel through warehouses or they may have their own supply. For emergencies, such as from a high load impact, fabricators can purchase the needed steel items from national warehouses. However, the cost of this steel may be much higher, and is not economically feasible (to the fabricator or the state) for large orders.

The table below details the recommended timelines in which steel delivery to the project site can be expected.


Table 707.1
Work Item – Order and Delivery of Steel Beams Time
Plate Girders and Rolled Beams – with flange thicknesses less than three inches 26 weeks after award
Bascule, Arch, Tub Girder, High Performance Steel (HPS Grade 70 or 100), Plate Girders and Rolled Beams – with flange thicknesses three inches or greater Consult Structural Fabrication Unit(*)
Pipe pile in excess of 14 inches nominal diameter, and HP shapes greater than 14 inches in depth. 12 weeks after award


  • Contact the Operations Field Services Division’s Structural Fabrication Unit (MDOT-StructuralFabrication@michigan.gov) for assistance in developing the timeframes for order and delivery of steel in preparing the progress clause.


For plate girders and rolled beams with flange thicknesses less than three inches, the recommended time from award to delivery at the project site is based on the following:

  • Up to three months for steel delivery from mill to fabricator,
  • Up to two months for fabrication,
  • Up to one month for submittal and approval of requests for information (RFI’s) and shop drawings, and shipping of the fabricated product to the project site.

Smaller diameter pipe pile and pile shapes such as HP12 and HP14 are rolled by multiple steel mills on a regular basis and should be readily available. For pile sections greater than 14 inches in diameter or depth, such as HP16 and HP18 shapes, and 16 inch diameter pipe pile, there are fewer mills to choose from and the rolling schedules are less frequent. Therefore, the recommended time frame for those shapes is 12 weeks after award. This is based only on delivery since fabrication time and shop drawings are not required.

While in many cases for structural steel, delivery can occur before the 26 week time frame, there are many variables which can influence steel delivery and frequently they cannot be determined at the time the progress clause is written. In addition to the factors influencing delivery of steel from the mill to the fabricator, the contractor that is awarded the contract and the fabricator they choose can affect the timeline. The fabricator chosen by the contractor may have less work or greater production capabilities than another fabricator. Some fabricators may try to book their production schedules such that by late winter or early spring they are fully booked through the summer or into fall. For this reason jobs let in the spring may have fewer fabricators available to complete the work and the jobs can be difficult to complete in one season especially if designed for part-width construction. In addition, the timeline to deliver steel beams for stage one of a part-width project may take the majority of the recommended timeline for delivery of both stages as the fabricator may elect to apply some aspects of fabrication to both stages instead of completing stage one in total before starting on stage two. The mill order and other milestones may take equal time whether they include one or both stages.

For the reasons outlined above, it is recommended that the table above be used when developing progress clauses for projects with steel superstructures or large format piling. Careful consideration is to be made on projects with staged construction, or interim completion or interim open to traffic dates.

If you have any questions please contact the Structural Fabrication Unit at MDOT-StructuralFabrication@michigan.gov.

[top of page]


Contract Time Determination (CTD)

Please refer to the Department’s Construction Scheduling Website.

[top of page]


Construction Time Estimates - Production Rates

The file link provided below contains production rates for major work items. The link will prompt you to download the file.

MDOT Production Rates

MDOT Production Rates Image 07272020.jpg

These rates should be used as guides and adjusted as necessary to reflect project specific conditions (accessibility, site, traffic, region, quantities, etc.) and previous work history in the area. The rates include a low, average, and high production rate estimate which should serve as helpful guidance to both Design & Construction Engineers when developing and administering the project (evaluating schedules, progress clauses, force accounts, extra work, etc.). The rate range is intended to reflect & capture around 80% of typical projects, with the allowance that some outliers will exist due to extenuating project circumstances.

[top of page]


LAP Project Considerations

Local agencies utilize the following boilerplate when developing their progress schedule:

LAP PROJECT Boilerplate Progress Clause Template May 2021

Local agencies are encouraged to utilize the resources in this section, such as product lead time and order and delivery estimate considerations when developing their progress schedule. Anticipated start dates should consider letting date and award timeframes to avoid setting unrealistic starting or completion expectations. Typically, MDOT let contracts are awarded within 49 days of letting. Progress clause start dates should take this into account.

Local agencies should keep in mind the lower rate estimates in MDOT Production Rates are often more applicable to the scale and complexity of LAP projects.





Email this Page