=[[#General|General]]=
+
__forcetoc__
 +
 
 +
==[[#General|General]]==
  
 
The Michigan Department of Transportation Construction Contractor Claims Procedure provides a formalized, tiered process for the submittal and review of a Contractor’s claim.  The claim review process involves a formalized administrative procedure.  The goal of the process is to resolve claims at the lowest possible level.  This document will clarify the process and reinforce the level of attention, accountability, and urgency by the Contractor and Department in the claim process.  The time durations within the procedures are intended to be maximum timeframes with any request for an extension to the durations, whether by the Contractor or the Department, documented in writing.
 
The Michigan Department of Transportation Construction Contractor Claims Procedure provides a formalized, tiered process for the submittal and review of a Contractor’s claim.  The claim review process involves a formalized administrative procedure.  The goal of the process is to resolve claims at the lowest possible level.  This document will clarify the process and reinforce the level of attention, accountability, and urgency by the Contractor and Department in the claim process.  The time durations within the procedures are intended to be maximum timeframes with any request for an extension to the durations, whether by the Contractor or the Department, documented in writing.
Line 8: Line 10:
 
* A copy of all notices of intent to file claims (MDOT and local agency) must be provided to TSC Managers and Region Construction Engineers as noted in the procedures.   
 
* A copy of all notices of intent to file claims (MDOT and local agency) must be provided to TSC Managers and Region Construction Engineers as noted in the procedures.   
  
* The claim information must be entered in the central office claim database after receiving Form 1953 from the Contractor.
+
* The Federal Highway Administration (FHWA) Area Engineer must be notified on all Projects of Division Interest (PODI) when a claim meeting is scheduled or an issue is scheduled to be presented to a Dispute Review Board (DRB).  A copy of the DRB claim package is to be provided to the FHWA Area Engineer. FHWA participation in claim payment is not guaranteed.  FHWA must be notified of claim prior to settlement and have opportunity to review claim documentation prior to settlement.  Regulations concerning FHWA participation in claims can be found here in [https://www.ecfr.gov/cgi-bin/text-idx?SID=4dda70efc34f778cb216111b6014fb91&mc=true&node=pt23.1.635&rgn=div5#se23.1.635_1124 23 CFR 635.124]
 
 
* The Federal Highway Administration (FHWA) Area Engineer must be notified on all Projects of Division Interest (PODI) when a claim meeting is scheduled or an issue is scheduled to be presented to a Dispute Review Board (DRB).  A copy of the DRB claim package is to be provided to the FHWA Area Engineer.
 
  
 
* All claim decision letters from the Region Office Review hearings are to be copied to both the Region Construction Engineer and the CFS Construction Contracts Engineer.
 
* All claim decision letters from the Region Office Review hearings are to be copied to both the Region Construction Engineer and the CFS Construction Contracts Engineer.
Line 18: Line 18:
 
This information will replace the claim procedures in section 104 of the construction manual.
 
This information will replace the claim procedures in section 104 of the construction manual.
  
If you have any questions, please contact [mailto:DeBoerM@michigan.gov Michael DeBoer], Construction Contracts Engineer, at  or call him at 517-256-8368.
+
:[//{{SERVERNAME}}/images_construction/d/d6/MDOT_Construction_Contractor_Claims_Procedure_-_Rev._2-2021.pdf MDOT Claims Procedure]
 +
 
 +
If you have any questions, please contact [mailto:DeBoerM@michigan.gov Michael DeBoer], Construction Contracts Engineer, or call him at 517-256-8368.
  
The statewide claims spreadsheet can be found in ProjectWise, under Documents - Statewide Groups - CFS - Statewide Claims Data. 
+
{{top}}
  
[[file:Claims database structure.PNG|250px|ProjectWise folder structure]]
 
  
  
 +
====[[#Claims Process Flowchart|Claims Process Flowchart]]====
 +
[[File:CLAIMS Flowchart DRAFT -SACT Review Complete.pdf|500px|thumbnail|center|Claims Process Flowchart]]
 
<div style="text-align: right;">[mailto:Change?body=http://mdotwiki.state.mi.us/construction/index.php/104.10_Contractor_Claim_for_Extra_Compensation_or_Time_Extension Email this Page]</div>
 
<div style="text-align: right;">[mailto:Change?body=http://mdotwiki.state.mi.us/construction/index.php/104.10_Contractor_Claim_for_Extra_Compensation_or_Time_Extension Email this Page]</div>
 
 
{{top}}
 
{{top}}
  
=[[#MICHIGAN DEPARTMENT OF TRANSPORTATION CLAIMS PROCEDURE (Revised 2016)|MICHIGAN DEPARTMENT OF TRANSPORTATION CLAIMS PROCEDURE (Revised 2016)]]=
+
==[[#LAP Project Considerations | LAP Project Considerations]]==
The [http://www.michigan.gov/documents/mdot/MDOT_Claims_Procedure_571598_7.pdf MDOT Claims Procedure Manual] is published on the MDOT website.
 
{{top}}
 
  
 +
LAP projects will follow [http://mdotwiki.state.mi.us/construction/index.php/104.10_Contractor_Claim_for_Extra_Compensation_or_Time_Extension Contractor Claim for Extra Compensation or Time Extension] guidance.  Locals are highly encouraged to work with their DR to resolve claim issues at the lowest possible level.
  
====[[#Claims Process Flowchart|Claims Process Flowchart]]====
 
[[File:CLAIMS Flowchart DRAFT -SACT Review Complete.pdf|500px|thumbnail|center|Claims Process Flowchart]]
 
 
<div style="text-align: right;">[mailto:Change?body=http://mdotwiki.state.mi.us/construction/index.php/104.10_Contractor_Claim_for_Extra_Compensation_or_Time_Extension Email this Page]</div>
 
<div style="text-align: right;">[mailto:Change?body=http://mdotwiki.state.mi.us/construction/index.php/104.10_Contractor_Claim_for_Extra_Compensation_or_Time_Extension Email this Page]</div>
 
{{top}}
 
{{top}}
 +
 
[[Category:Construction Manual]]
 
[[Category:Construction Manual]]
 
[[Category:Division 1]]
 
[[Category:Division 1]]
 
[[Category:Section 104]]
 
[[Category:Section 104]]

Revision as of 11:26, 25 October 2021

Email this Page


General

The Michigan Department of Transportation Construction Contractor Claims Procedure provides a formalized, tiered process for the submittal and review of a Contractor’s claim. The claim review process involves a formalized administrative procedure. The goal of the process is to resolve claims at the lowest possible level. This document will clarify the process and reinforce the level of attention, accountability, and urgency by the Contractor and Department in the claim process. The time durations within the procedures are intended to be maximum timeframes with any request for an extension to the durations, whether by the Contractor or the Department, documented in writing.

Construction Field Services (CFS) and Region Construction Engineers will be monitoring and tracking all claims. The procedures for the reporting and tracking of claims are as follows:

  • A copy of all notices of intent to file claims (MDOT and local agency) must be provided to TSC Managers and Region Construction Engineers as noted in the procedures.
  • The Federal Highway Administration (FHWA) Area Engineer must be notified on all Projects of Division Interest (PODI) when a claim meeting is scheduled or an issue is scheduled to be presented to a Dispute Review Board (DRB). A copy of the DRB claim package is to be provided to the FHWA Area Engineer. FHWA participation in claim payment is not guaranteed. FHWA must be notified of claim prior to settlement and have opportunity to review claim documentation prior to settlement. Regulations concerning FHWA participation in claims can be found here in 23 CFR 635.124
  • All claim decision letters from the Region Office Review hearings are to be copied to both the Region Construction Engineer and the CFS Construction Contracts Engineer.

Please send all (project, region and central office) claim decision letters to the contractor by certified mail. The Return Receipt is to be placed in the project file. This documentation will be used when determining if subsequent appeals are timely. If you receive what appears to be an untimely appeal from a contractor, contact the Attorney General’s Office (517-373-1479) for recommended action.

This information will replace the claim procedures in section 104 of the construction manual.

MDOT Claims Procedure

If you have any questions, please contact Michael DeBoer, Construction Contracts Engineer, or call him at 517-256-8368.

[top of page]



Claims Process Flowchart

Claims Process Flowchart
Email this Page

[top of page]


LAP Project Considerations

LAP projects will follow Contractor Claim for Extra Compensation or Time Extension guidance. Locals are highly encouraged to work with their DR to resolve claim issues at the lowest possible level.