402 - Storm Sewers

From MediaWiki
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
402
Storm Sewers


GENERAL DESCRIPTION

Definitions of Terms

Catch Basin: A catch basin is a curbside opening that collects surface runoff.

Curb and Gutter: Curb and gutter is the edge of the paved roadway that collects water and is designed to drain to a catch basins, downspouts, and spillways.

Detention Pond: A detention pond is a temporary storage area that is engineered to control stormwater. Excess stormwater is collected within a detention pond during heavy rain events to help mitigate flooding and erosion downstream. A detention pond typically dries out between rain events.

Outfall: An outfall is the outlet where a storm sewer discharges water to a body of water or basin.

Wet Detention (Retention Pond): A wet detention pond is a permanent storage area for excess stormwater runoff. Excess stormwater is collected in the wet detention pond aiding in the control of erosion. Often, there is a weir or another filtration system within the wet detention pond, which is used for filtering the stormwater as it travels through the pond. Wet detention areas can serve as artificial wetlands for the surrounding area increasing biodiversity. Wet detention areas were often formerly referred to as "Retention Ponds".

Runoff: Runoff is drainage that leaves an area as surface flow and enters a storm sewer system.

Sedimentation: Sedimentation is the process of depositing soils that were eroded by the flow of water.

Storm Sewer System: A storm sewer system is a network of underground pipes designed to collect and discharge water.

Sump: A sump is the lower portion of a catch basin below the outlet pipe that is used to settle out debris and suspended material prior to stormwater exiting the catch basin.

Watershed: A watershed is an area of land that drains to a specific point.

General Overview

Storm sewers are an underground infrastructure system designed to manage excess surface runoff and groundwater from roadways. These systems collect water from various sources, such as curb and gutter, drainage ditches, and underdrain pipes, by utilizing the natural slope of the land to facilitate drainage through gravity. Storm sewer systems discharge untreated water into ditches, basins, streams, or rivers.

The key components of storm sewer systems include:

  1. Inlet: Inlets are typically catch basins with grates to permit water to enter into the system. The grates serve to prevent large objects from entering while facilitating the entry of water and sediment. Catch basins, which have a diameter measuring in inches, allow water to descend into the storm sewer for downstream conveyance. Some catch basins are designed with a sump below the pipe elevation, aiding in sediment settlement to prevent its entry into a body of water.
  2. Pipe: Pipe is the conduit responsible for transporting water to the outlet. Project documents specify the size and class of the pipes.
  3. Outlet: Outlets serve as the endpoint of the storm sewer system pipe.
  4. Outfall Outfalls are where an outlet discharges into a body of water.


Elliptical Pipe Installation at a Drainage Structure

[top of page]


MATERIALS

All materials must meet acceptance requirements in the Materials Source Guide and be listed on the Contractor-provided Material Source Lists in the project files.

Description of Materials

The pipe material and class are noted on the plans. MDOT defines the pipe by class, which is based on the amount of cover over the pipe. Refer to Table 402-1 of the Standard Specifications for Construction for acceptable pipe in each class.

Parts of a Pipe

Common storm sewer pipe materials include:

  • Plastic:
    • Smooth-lined corrugated polypropylene pipe (PPP). Grey in color.
    • Smooth-lined corrugated polyethylene pipe (CPE) Type S. Black in color.
    • Corrugated polyethylene pipe (CPE) Type C. Black in color.
    • Corrugated polyvinylchloride pipe (CPV). White in color.
  • Concrete:
    • Reinforced concrete pipe (RCP).
    • Non-reinforced concrete pipe.
  • Metal:
    • Corrugated metal pipe (CMP).
    • Corrugated and spiral ribbed pipe (CSP).

Each pipe section, regardless of type, must be clearly marked with the following:

  • Pipe class and specification designation (ASTM or AASHTO).
  • Date of manufacture.
  • Name or trademark of the manufacturer.
  • Plant identification.

The marking is either painted on the inside or scribed on outside of concrete pipes, and is painted on the outside of metal and plastic pipe.

Pipe Identification Markings
Concrete Sewer Pipe Manufacturer Classification

To aid in the joining of pipe segments and to seal the pipe so the joints do not leak, lubricant and gaskets are used.

Example of Pipe Gasket Seal Lubricant
Concrete Sewer Pipe with Rubber Gasket

Any of these materials found with defects prior to or during installation are to be rejected and removed from the project site. Any damage caused by the Contractor’s operation to existing storm sewers that are intended to be salvaged must be removed and replaced with similar material without damage or defects at no cost to the contract.

Plastic Pipe (PPP, CPE, and CPV)

Plastic pipe is more susceptible to shipping and storage deformation than concrete or metal pipe. Improper lifting and storage can lead to misshapen sections that are difficult to lay at a proper grade if the curve is placed vertically, and difficult to lay at a proper alignment if the curve is laid horizontally. Plastic pipe should not be deformed (out-of-round) or have blemishes in the extrusion. It should not have gouges or tears on the exterior, the interior, or the bell ends. Plastic pipes should have protective gaskets installed on the spigot ends. Gaskets should be clean and not dried out during installation.

Polypropylene Storm Sewer Pipe

Concrete Pipe

Concrete pipe is precast by a manufacturer and is made of cementitious materials, aggregates, and in most cases steel reinforcement.

Reinforced Concrete Pipe Rejection Criteria Per 909.04.A and AASHTO M170/M242
  • Fractures or cracks passing through the shell, except for a single end crack that does not exceed the depth of the joint.
  • Defects that indicate imperfect proportioning, mixing or molding.
  • Defects which indicate honeycombed or open texture.
  • Damaged or cracked ends where such damage would prevent making a satisfactory joint.
  • Exposed circumferential steel reinforcement that would indicate misalignment of the reinforcing.
  • Any continuous crack having a surface width of 0.01 inch (0.25 mm) or more and extending for a length of 12 inches (300 mm) or more, regardless of position in the wall of the pipe.
  • Small imperfections in manufacture or damage during handling. These may be repaired as long as repairs are sound and properly finished and cured.

Metal Pipe (CMP and CSP)

Corrugated metal pipe should not be out-of-round, exhibit deviation from a straight alignment, or have dents or bends in the metal that can create loose, poorly formed joints. Bruised or broken zinc, aluminum, or polymer coating must be repaired by the Contractor in accordance with the manufacturer’s specifications at no cost to the contract.

Damaged Polymer-Coated CSP

Bedding and Backfill

Bedding material is comprised of granular material Class IIA, or Michigan Series 34R if undercuts are required. The material used is determined by the existing subgrade material at the bottom of the trench.

Backfill material varies depending on what is above the storm sewer being installed and the type of pipe that is used. Typical backfill consists of granular Class II, IIAA, III, or IIIA material, suitable excavated material, or a concrete encasement. Refer to the Standard Plan R-83 series for details.

34R Aggregate
46G Aggregate
Class II Sand

[top of page]


EQUIPMENT

The following equipment can be used for storm sewer work:

  • Excavator
  • Backhoe
  • Front end loader
  • Trench box
  • Occasionally, a bulldozer and a vibratory roller for aggregate compaction
  • Plate compactor
  • Ho-Pac attachment
  • Gas powered rammer tamping machine
  • Air powered pogo thumper hammer
  • Sand/stone box
  • Portable concrete mixer
  • Cement/mortar mixing tub
  • Portable generator
  • Electric submersible pump
  • Trash pump
  • Pipe laser with target
  • Transit or laser level
  • Leveling/grade pole
  • Electric impact wrench
  • Pipe/spud bar
  • Small hand tools (shovel, level, pipe “cutoff” saw, etc.)
  • Direct tap machine for sewer tap

Description of Equipment

Typically, an excavator is used to remove existing storm sewers and dig the trench for new storm sewer. A laser or other acceptable alignment device is used to install the storm sewer pipe to proper grade as it is laid in the trench by the excavator. A front-end loader or excavator is used to place backfill around the pipe to be compacted in layers by a Ho-Pac or other compaction equipment. In some cases, with a large trench, a truck will dump the backfill material directly into the trench to be graded by a bulldozer before compaction.

Pictures of Equipment

Excavator with Plate Compactor Attachment (Ho-Pac)
Pipe Laser
Bulldozer
Laser Transit
Portable Concrete Mixer
Plate Compactor
Jumping Jack Compactor
Cutoff Saws

[top of page]


PRECONSTRUCTION

Prior to the start of construction, the Inspector should perform the following:

  1. Inspect the pipe upon arrival to the site.
    • Verify the pipe meets the requirements contained in the plans, specifications, and any addenda.
      • The pipe must be accompanied by the manufacturer’s certification, tested stock reports, or other requirements as specified in the Materials Quality Assurance Procedures Manual.
      • Review the cover over the top of the pipe as called for in the plans and verify against the pipe chart (Table 402-1 of the Standard Specifications for Construction) for acceptable pipe installation depth and class.
    • Visually inspect the pipe for defects originating from the manufacturing process or occurring during delivery and unloading at the site per the criteria detailed in the materials section for each type of storm sewer pipe. Any damaged pipe should be promptly rejected by the Engineer.
      • Inspect the bell and spigot end of the pipe to ensure there are no chips or cracks that might impede a watertight joint connection.
      • Inspect plastic storm sewer pipe to ensure it does not exhibit deformities that would hinder water flow.
      • Using survey paint, mark any rejected pipe with an “R” to indicate rejection of the pipe. It is good practice to mark both the inside and outside of the pipe.
  2. Verify the survey stakes are placed according to the plans and the appropriate invert elevations, rim elevations, and pipe and structure IDs are labeled on the stakes.
    • Ensure proper offset stakes are placed as stakes placed in the location of the proposed sewer will be removed when excavation begins.
  3. Verify existing underground utility markings.
    • Take note of any potential utility crossings and reference the plans and profiles to ensure minimum clearances are met.
  4. Review the plans and the Special Provision for Maintenance of Traffic. There may be restrictions or staging requirements for installation of the storm sewer. Installation restrictions are typically associated with staging requirements on a project and access to side streets and driveways.
  5. Hold an onsite meeting with the Contractor to discuss:
    • The construction method that will be used to complete the work.
    • Required traffic control measures, proximity of traffic to the work area, and maintaining driveways during construction.
    • Communication required if impacting residents or businesses during installation.
      • Residents and businesses should be contacted if there will be disruptions to services. Coordination by the Contractor with impacted users may be required if disruption is necessary.
    • Review of local ordinances.
    • Disposal of excavated material and material stockpile locations. The Contractor should provide authorization letters to the Engineer noting material stockpile and disposal locations.
    • Soil erosion and sedimentation control measures that will be utilized to minimize soil erosion and subsequent sedimentation.
    • Methods for securing the site during work operations and at the end of each workday.
      • Including maintaining appropriate cover over the top of the pipe to minimize damage to the pipe from construction traffic.
Delivery of Storm Sewer Pipe


A review of the proposed sewer depth on the profile sheets should be compared to all known existing utilities that will be crossed, and any other proposed utilities and structures to be built, with attention paid to elevation conflicts. The size of the storm sewer must be considered. The plan invert elevation might not be in conflict, but the height of the pipe above the invert might be. Likewise, an elevation shot on “top” of an existing utility needs to consider the size of the utility below the top.

Example:

The proposed invert of a 12” concrete pipe is 100.00 at the outlet and 100.50 at the inlet. The storm sewer is 100’ long. A 6” gas main exists at the middle of the run (50’ out) with a top-of-pipe elevation of 101.50.

101.5 - 0.5’ = 101.00 at the bottom of the gas pipe.

Calculate the pipe grade using rise/run.

0.5’ rise/100’ run = 0.005’ rise per foot.

0.005 x 50’ = 0.25 rise to the point where the gas main crosses.

Invert 100.00 + 0.25 = 100.25 at 50’ out + 12” (pipe size), + 0.25 pipe thickness = 101.50 at the top of the sewer 50’ out.

There is an elevation conflict between the proposed 12” storm sewer and the existing 6” gas main.

Example Drawing of Anticipated Utility Conflict

[top of page]


CONSTRUCTION

Trench Excavation

Construction of a storm sewer begins with trench excavation. Excavation may include the removal of existing storm sewer and drainage structures. These removal quantities should be recorded as called for in the specifications.

There are many factors that determine the safe and proper width of a pipe trench. Refer to OSHA Regulation 1926, Subpart P, Excavations, for all applicable sloping, shoring, and soil classification safety standards for excavation. Existing soil material, groundwater elevation, utilities, trees (roots), and proximity of paved surfaces (roads, sidewalks, and curbs and gutters) and buildings may all be considered by the Contractor when deciding how the trench will be excavated.

In accordance with Subpart P, soil can be classified as 3 different types:

  1. Type A: A cohesive soil with unconfined compressive strength of 1.5 ton per square foot (tsf) or greater. Examples include clay, silty clay, sandy clay, clay loam, and in some cases silty clay loan and sandy clay loam. Cemented soils like caliche and hardpan are also considered Type A soils. However, the soil cannot be classified as Type A if one or more of the following conditions are met:
    • The soil is fissured.
    • The soil is subject to vibration from heavy traffic, pile driving, or similar effects.
    • The soil has been previously disturbed.
    • The soil is part of a sloped, layered system where the layers dip into the excavation on a slope of 4H:1V or greater.
    • The material is subject to factors that would require it to be classified as a less stable material.
  2. Type B: A cohesive soil with unconfined compressive strength greater than 0.5 tsf but less than 1.5 tsf. Granular cohesionless soils include angular gravel (crushed rock), silt, silt loam, sandy loam, and in some cases silty clay loam and sandy clay loam. Other characteristics include:
    • Previously disturbed soils except those which would otherwise be classified as Type C.
    • Soil that meets the compressive strength or cementation requirements for Type A but is fissured or subject to vibration.
    • Dry rock that is not stable.
    • Material that is part of a sloped, layered system where the layers dip into the excavation on a slope less steep than 4H:1V, but only if the material would be otherwise classified as Type B.
  3. Type C: A cohesive soil with an unconfined compressive strength less than 0.5 tsf. Examples include gravel, sand, and loamy sand. Other characteristics include:
    • Submerged soil or soil from which water is freely seeping.
    • Submerged rock that is not stable.
    • Material in a sloped, layered system where the layers dip into the excavation on a slope of 4H:1V or steeper.

Following are various sloping requirements in accordance with OSHA regulations.

Sloping Requirements by Soil Type
Maximum Allowable Slope with Support System by Soil Type
Maximum Allowable Slope with Support System by Soil Type
Maximum Allowable Slopes by Soil Type


The width of the trench should be sufficient to enable a worker to place and compact material under the pipe haunches. The Standard Plan R-83 series provides direction for minimum trench width as a function of the pipe size.

Trench boxes and/or sheeting can be used to “steepen” the banks of a trench. By limiting the width of the trench, the Contractor can minimize excavation and backfill quantities and avoid conflicts with existing utilities, tree roots, and removal of more pavements than otherwise necessary. Some sheeting systems or cofferdams require “engineering” due to depth of material retained. Refer to Subsection 704.03.A of the Standard Specifications for Construction, which describes the design for sheeting and cofferdams for retaining soil in a trench greater than 6 feet deep.

The trench must be excavated and graded to the proper alignment and grade, leaving room for at least 4 inches of granular material as a bedding layer below the pipe. The bedding material must be graded uncompacted uniformly so the entire length of the pipe is firmly supported. If the pipe has bells that are larger in diameter than the barrel of the pipe, the surface of the bedding at the location of the bell can be lowered, so the bell is not propped up creating a void beneath the barrel or a misalignment of the pipe. The Contractor should not adjust the grade of the as-placed pipe in the trench with an excavator or other equipment.

Where rock or unyielding hardpan is encountered in the storm sewer trench, it should be excavated to a minimum of 6 inches below the proposed bottom of the pipe, backfilled with granular material Class IIIA, and compacted. The Standard Plan R-83 series provides details for bedding and filling around storm sewers in various applications and should be strictly followed. Backfill should be thoroughly compacted under the haunches of the pipe to provide uniform bearing throughout.

Trench Box being used to Install Storm Sewer

Dewatering

Dewatering of the trench may be required if either the groundwater elevation or water in the existing ditches is inundating the trench bottom. If pumps are employed to control the water, proper soil erosion and sedimentation control should be employed as well. Running the discharge of a pump through a filter bag is a common requirement. In some cases, multiple filter bags may be required. Direct discharge of pumped water to a watercourse is prohibited.

Undercutting

Undercutting the proposed trench bottom may be required if the material in the bottom is unstable and will not sufficiently support the pipe. Trench undercutting has a separate pay item (Trench Undercut and Backfill) that must be calculated by the cubic yard. Refer to Subsection 402.04.E of the Standard Specifications for Construction for construction details and method of payment, respectively. The additional depth below the intended trench bottom must be backfilled with Michigan Series 6A, 17A, or 46G aggregate. Granular material (Class I, II, or III) and other “suitable material” are not acceptable and not included in the pay item.

Bedding

Storm sewer should be placed on suitable bedding material. Soft or spongy materials do not provide a firm bed for storm sewers. Excavation and bedding for storm sewers must be in accordance with Subsection 401.03 of the Standard Specifications for Construction. Storm sewer bedding must be constructed uncompacted using a minimum 4-inch layer of granular Class III or IIIA material in accordance with the details in the Standard Plan R-83 series.

Pipe Placement

Pipe laying typically begins at the outlet end and proceeds uphill with the bells on the higher end. Sometimes storm sewers must be laid backwards from the inlet end downhill. In this case, the pipe bells should still be laid to the higher end of the individual pipe sections.

The first piece of pipe laid should be set to the plan invert elevation and reasonably at the plan grade. Typically, a pipe laser is used to control the alignment and the grade by directing the beam at a target placed in the pipe. The plan grade is entered into the pipe laser and the laser is directed in the plan alignment of the storm sewer by sighting the centerline of the opposite end where the target is placed, which is measured from the offset stakes. By checking the invert elevation of the first pipe with the “cut/fill” of the offset stakes and checking the invert elevation (rise/run) periodically throughout the pipe laying operation, the Inspector will know if the plan elevations are being maintained.

The Contractor should not use a backhoe bucket or other excavation equipment to adjust the grade of the pipe. If the grade needs to be increased or decreased, the end of the pipe should be lifted to remove excess material or add additional material. Using a backhoe bucket or other excavation equipment to adjust the grade will damage the pipe.

The Inspector should verify the pipe sections are pushed home completely during installation. Ensure the Contractor does not forcefully slam the pipe connections together.

Prior to backfilling, all pipe joints must be wrapped with a non-woven geotextile blanket. The fabric must have a minimum width of 36 inches, be centered on the joint, and overlap on the ends by at least 12 inches.

The joints of CMP are different than the description above because there are no bells and spigots. The ends of the pipe sections are joined using couplers made of an open steel band that is passed around the joint and then secured with a bolted connection. To make the joint watertight, a gasket must be placed around the pipe between the coupler and the pipe. After the bolt(s) have been tightened on the coupler, the joint is wrapped, as described above, with geotextile blanket.

Joint Types of CMP Pipe

Elliptical concrete pipe should be installed with the lift holes on the top of the pipe. The manufacturer’s marks designating the top and bottom of the pipe should not be more than 5 degrees from the vertical plane through the longitudinal axis of the pipe. After installation, the lift holes should be sealed with suitable concrete plugs and waterproofed. Flow velocities within a pipe must be sufficient to prevent sedimentation at an approximate flow of 2 feet per second (fps). The minimum pipe slopes to provide a self-cleaning velocity are detailed in the following table:

Diameter (inches) Storm (fps) Sanitary (fps)
12 0.33 0.17
15 0.25 0.14
18 0.22 0.12
21 0.21 0.12
24 0.17 0.10
30 0.15 0.08
36-42 0.12 0.07
48 0.10 0.06
54-60 0.09 0.05
66-78 0.08 -
84 0.07 -
Concrete Sewer Being Set in Trench Box
Concrete Sewer Placement at Drainage Structure


Watertight Joints

All pipe joint assemblies for use in storm sewers must be selected from the Qualified Products List.

Proper installation of the required rubber gaskets is crucial for performance and joint integrity of every RCP pipe segment and manhole. Equalization of each gasket, as well as proper utilization of the supplier-furnished/approved joint lubricant on the pipe joints, is necessary. The o-ring stretch can be equalized by running a smooth, round object (inserted between gasket and spigot) around the entire circumference three times. Installation methods may vary depending on the pipe/manhole supplier. Following are installation procedures for two common types of gaskets.

Concrete Sewer Set on Granular Bedding with Fabric-Wrapped Joints
Installation Procedure for O-Ring Gasket (Source: Press-Seal Corporation)
Installation Procedure for Type 4 Gaskets (Source: Press-Seal Corporation)

Backfilling

Backfilling around the pipe must be completed in accordance with the Standard Plan R-83 series. The type of trench excavation and pipe type will dictate the backfill material. For example, pipe underneath a roadway will constitute granular material around and above the pipe, whereas pipe placed outside of the roadway in the greenbelt can typically have suitable excavated material placed above the pipe once granular material is placed to the spring line of the pipe. Additional bedding can be compacted in place up the midpoint of the utility and under the pipe’s spring point. The Contractor should use hand-operated compactors to achieve the required compaction. Backfill will be placed in maximum lifts in accordance with Section 402 of the Standard Specifications for Construction using an approved trench backfill material as indicated in the project plans.

It is important to backfill the pipe as soon as possible after placement so that runoff is directed through and not alongside the pipe. This will reduce the possibility of the pipe becoming undercut and getting displaced. When the pipe is within the influence of the roadbed, all granular material Class II, III, or IIIA (as specified) should be placed in layers not more than 10 inches thick, and each layer is to be compacted to 95% of the maximum unit weight. Backfill for pipe outside the influence of the roadbed should be placed as detailed on the plans and compacted thoroughly. Backfill should be brought up along both sides of the pipe at the same time so the pipe is not displaced. Regardless of the equipment used for backfill compaction, a maximum lift of 10 inches can be placed and compacted at one time.

Backfill material for corrugated plastic pipe will be granular material Class IIIA to a minimum of 12 inches above the pipe, except that no stones larger than 1 inch in diameter are allowed within 6 inches of the pipe. Staking or other methods to restrain the pipe may be necessary during the backfilling operation to maintain the line and grade of the pipe.

To prevent damage to the pipe during construction activities, a minimum of 3 feet of cover must be maintained at all times, except when trimming for final grade.

Jacked-in-Place

Jacked-in-place storm sewer is used when it is desired to place a drainage feature without disturbing the roadbed or railroad above the pipe. The excavation should not be more than approximately 1 inch greater than the outside diameter of the pipe. The pipe should be advanced with the hole to prevent caving and subsidence of the grade. A steel cutting edge or shield may be attached to the front section of pipe to form and cut the required opening for the pipe. Steel casings are always used for jacked-in-place pipe installed under a railroad.

Frequent checks of the line and grade should be made to ensure the pipe is going in the proper direction. Steel casing must meet the requirements listed in Table 909-18 of the Standard Specifications for Construction. Adjoining sections should have a tight joint without larger irregularities between the 2 sections. Prior to welding, the steel around the joint should be properly prepared. The steel casing sections must have a fully welded joint which is watertight and capable of withstanding handling and installation stresses. Field welding should be conducted using the shielded metal arc welding process and using E6011 or E7018 electrodes.

Full circular pipe reinforcement is required when concrete pipe is directly jacked-in-place. All joints must have a proper seal. For larger pipes, the joints are to be thoroughly wetted, filled with mortar, and wiped smooth. Voids between the excavation and the pipe are filled using approved grout and grouting methods.

INSPECTION & TESTING

Inspection

The Inspector should utilize, at a minimum, the following tools to perform the required inspection:

  • 100-foot tape measure or longer
  • 25-foot tape measure
  • Measuring wheel
  • Chaining pin
  • 6-foot stick ruler
  • 4-foot level
  • Working plans
  • As-built sheets to update the plans
  • Survey equipment
  • Camera

The Inspector should take the following steps during construction:

  1. Verify the correct pipe, gaskets, and geotextile blanket are used per the plans and MSLs.
  2. Verify the pipe is free of defects or damage.
    • Using survey paint, mark any rejected pipe with an “R” to indicate rejection of the pipe. It is good practice to mark both the inside and outside of the pipe.
  3. Observe installation of pipe, fittings, and appurtenances in accordance with manufacturer’s recommendations.
  4. Monitor excavation of the trench to ensure the pipe meets the elevation requirements shown on the plans.
    • If the bell end of the pipe is significantly larger than the spigot, ensure the trench is excavated appropriately so the entire pipe is supported by the bottom of the trench.
  5. Verify that all pipe bedding and backfill of excavated trenches is clean, dry, and meets design requirements.
  6. Verify there is no debris in the pipe before installation.
  7. Verify pipes have lift holes facing the top and the lift holes are filled with concrete plugs and waterproofing prior to backfilling.
  8. When the Contractor is connecting two pipes, ensure:
    • The pipe bell is clean.
    • The required joint gasket is installed.
      • Verify the correct gasket is used as one manufacturer’s specific gasket may not fit a different manufacturer’s pipe.
      • Verify the Contractor lubricates the gasket immediately prior to assembly.
    • The joint is seated properly.
    • A minimum of 12 inches of overlap of the geotextile blanket is obtained on each pipe.
  9. Verify the coupler of CMP pipe have been fully bolted prior to backfilling.
  10. Obtain grade shots and document the grades on the as-built plans.
  11. Verify passing density shots are obtained on each lift of backfill material.
  12. Record the density testing results of the backfill material in accordance with the Density Testing and Inspection Manual using the field established maximum density for the material being tested. The minimum testing frequency is shown in Appendix K (backfill) of this manual. The testing frequencies listed are minimums that are satisfactory for acceptance. However, it is emphasized that project conditions normally require more frequent testing for proper density control.

Video Inspection

Storm sewer video inspection must be conducted after installation in accordance with Subsection 402.03.J of the Standard Specifications for Construction. Video inspection is performed by the Contractor. It is required for all types of storm sewers, with the following exceptions:

  • Driveway culverts.
  • Culvert extensions of less than 50 feet.
  • Extensions of existing catch basin leads of less than 20 feet.
  • New culverts of less than 50 feet.

The purpose of the video inspection is to determine any damage or installation defects to the sewer, including pipe deformation, cracking, joint separation, corrosion, perforation, excessive siltation, excessive ponding of water, or any discernable feature observed in the video.

For sewers installed under pavement, the inspection should be conducted after the required backfill compaction of the trench has been achieved, and between 5 and 10 working days prior to pavement surfacing or completion of final grade, except as otherwise approved by the Engineer.

For sewers not installed under pavement, the video inspection should be conducted as close to project completion as possible, while still allowing sufficient time for corrective action determined to be necessary from the video inspection and as directed by the Engineer.

All video inspection must be of acceptable quality for the Engineer to review. The camera should provide sufficient lighting and have sufficient underwater capability to provide a clear picture during the inspection. Camera magnification must always be indicated on the screen during video inspection. The camera must allow tilting and panning for the inspection of joints, cracks, and other defects. If the Engineer determines the video quality to be unsatisfactory, re-inspection of the pipes may be required at no cost to the contract. Re-inspection may also be required if the joints or defects are not fully inspected during the initial video inspection, at no cost to the contract.

If defects are found during video inspection, the Contractor is to submit a corrective action plan to the Engineer for review and approval. Only after the plan is approved, may the Contractor begin corrective action work.

Testing

For evaluation of aggregate materials, use only certified aggregate sampling and testing technicians. Refer to the Procedures for Aggregate Inspection manual and project specifications for testing requirements and frequencies. The Engineer should track the approved testing of installed aggregate and coordinate with the respective testing lab to ensure the required number of aggregate tests for the project are being completed. Perform density testing on compacted backfill. All backfill, regardless of material used, is to be compacted to 95% of the maximum unit weight. The Inspector should ensure the minimum number of required density tests are being performed per the Density Testing and Inspection Manual.

To ensure excessive deformation of the pipe will not occur after backfilling and compaction, mandrel testing must be performed on a sample of all plastic pipes. Refer to Division 4 Supplemental Information of the Construction Manual for more information on mandrel testing of plastic pipe.

[top of page]


MEASUREMENT, DOCUMENTATION & PAYMENT

Measurement and Payment

In situ material from the job site may be used for backfilling after the Contractor completes gradation testing of samples taken from an onsite stockpile. The respective MDOT material lab will confirm the gradation of the onsite material meets the requirements for the desired backfill material.

Refer to Subsection 402.04 of the Standard Specifications for Construction for direction regarding measurement and payment for storm sewers.

In general, storm sewer is paid by the linear foot for the size storm sewer being installed. Excavation, dewatering, joint wrapping, and backfill are incidental to the storm sewer pay item. The cost to restrain the pipe during backfilling and provide temporary cover to protect the pipe from damage will be included with the appropriate item of work and not paid for separately. End sections and existing storm sewer removals are paid for separately.

Documentation

The primary report required for the payment of storm sewer is the Daily Work Report (DWR). The Inspector should note in the remarks section of the report the condition of the base material during placement, material verification, and equipment and manpower used. The invert elevations at both the inlet and the outlet ends as well as the final length of the storm sewer should be recorded for as-built records.

Additional documentation once the work is completed should include:

  1. Station to station length and width being paid on this date.
  2. Survey or other approved methods for verification the storm sewer was constructed in conformance with the project documents.
  3. Volume and tonnage of bedding and backfill material placed.
  4. Video records of pipe inspections.

Form 1900, Aggregate Inspection Daily Report, will need to be completed for every sublot of aggregate to track gradation acceptance. Form 0582B, Moisture & Density Determination - Nuclear Method, is used to record density testing results.

Delivery tickets must be verified for the source of material against the approved Material Source List. Each ticket must include the required information. Refer to Subsection 109.01.B.6 of the Standard Specifications for Construction for the information required on each ticket.

[top of page]


LOCAL AGENCY PROJECTS

Local agency projects sometimes have details and specifications for storm sewer construction. These standards are to be followed while working on a Local Agency Project.

[top of page]


RAIL PROJECTS

-Reserved-

[top of page]