==[[#CONSTRUCTION|CONSTRUCTION]]==
 
==[[#CONSTRUCTION|CONSTRUCTION]]==
  
<span style="color: red"> -Reserved- </span>
+
===[[#Overband Delay Periods|Overband Delay Periods]]===
 +
 
 +
a. Stand Alone Overband Crack Fill
 +
 
 +
b. Micro-Surfacing Preparation – Industry recommends a delay period of 3 days between overband pretreatment and placement of micro-surfacing.
 +
 
 +
c. Chip Seal Preparation– Industry recommends a delay period of 7-14 days between overband pretreatment and placement of chip seal.
 +
 
 +
d. Paver Placed Surface Seal Preparation – It is recommended to allow 14 days between overband pretreatment and paver placed surface seal.
 +
 
 +
e. HMA Ultra-Thin Overlay Preparation– It is recommended to allow 14 days between overband pretreatment and ultra-thin overlay.
  
 
{{top}}
 
{{top}}

Revision as of 11:40, 27 June 2014

502
HMA Crack Treatment
2012 STANDARD SPECIFICATIONS FOR CONSTRUCTION - SECTION 502


GENERAL

-Reserved-

[top of page]


MATERIALS

Overband (Alternate 1)

Field blended liquid mixture for overband (Alternate 1) is no longer allowed. All overband material must be from the Qualified Products List (Alternative 2).

[top of page]


CONSTRUCTION

Overband Delay Periods

a. Stand Alone Overband Crack Fill

b. Micro-Surfacing Preparation – Industry recommends a delay period of 3 days between overband pretreatment and placement of micro-surfacing.

c. Chip Seal Preparation– Industry recommends a delay period of 7-14 days between overband pretreatment and placement of chip seal.

d. Paver Placed Surface Seal Preparation – It is recommended to allow 14 days between overband pretreatment and paver placed surface seal.

e. HMA Ultra-Thin Overlay Preparation– It is recommended to allow 14 days between overband pretreatment and ultra-thin overlay.

[top of page]


MEASUREMENT AND PAYMENT

-Reserved-