Difference between revisions of "502 - HMA Crack Treatment"

From MediaWiki
Jump to navigation Jump to search
Line 37: Line 37:
 
==[[#MEASUREMENT AND PAYMENT|MEASUREMENT AND PAYMENT]]==
 
==[[#MEASUREMENT AND PAYMENT|MEASUREMENT AND PAYMENT]]==
  
<span style="color: red"> -Reserved- </span>
+
Overband Crack Fill and HMA Crack Treatment are now paid for by the lane mile (Lnmi).  All shoulder work is considered incidental.  A lane mile is defined in the Lane Mile Inventory document which can be found online at  http://www.michigan.gov/mdot/0,4616,7-151-9621_15757---,00.html
 
 
 
{{top}}
 
{{top}}
  
 
[[Category:Construction Manual]]
 
[[Category:Construction Manual]]

Revision as of 11:41, 27 June 2014

502
HMA Crack Treatment
2012 STANDARD SPECIFICATIONS FOR CONSTRUCTION - SECTION 502


GENERAL

-Reserved-

[top of page]


MATERIALS

Overband (Alternate 1)

Field blended liquid mixture for overband (Alternate 1) is no longer allowed. All overband material must be from the Qualified Products List (Alternative 2).

[top of page]


CONSTRUCTION

Overband Delay Periods

a. Stand Alone Overband Crack Fill

b. Micro-Surfacing Preparation – Industry recommends a delay period of 3 days between overband pretreatment and placement of micro-surfacing.

c. Chip Seal Preparation– Industry recommends a delay period of 7-14 days between overband pretreatment and placement of chip seal.

d. Paver Placed Surface Seal Preparation – It is recommended to allow 14 days between overband pretreatment and paver placed surface seal.

e. HMA Ultra-Thin Overlay Preparation– It is recommended to allow 14 days between overband pretreatment and ultra-thin overlay.

[top of page]


MEASUREMENT AND PAYMENT

Overband Crack Fill and HMA Crack Treatment are now paid for by the lane mile (Lnmi). All shoulder work is considered incidental. A lane mile is defined in the Lane Mile Inventory document which can be found online at http://www.michigan.gov/mdot/0,4616,7-151-9621_15757---,00.html