==MATERIALS==
 
==MATERIALS==
Line 55: Line 56:
 
The asphalt emulsion must be a certified product and be supplied by a certified supplier.  The Contractor must maintain quality control and uniformity in testing procedures.  The Contractor must submit to the Engineer a daily report showing the test results, as well as other information addressed in subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/506%20Slurry%20Seal.pdf 506.02.A.1.c] of the Standard Specifications for Construction.
 
The asphalt emulsion must be a certified product and be supplied by a certified supplier.  The Contractor must maintain quality control and uniformity in testing procedures.  The Contractor must submit to the Engineer a daily report showing the test results, as well as other information addressed in subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/506%20Slurry%20Seal.pdf 506.02.A.1.c] of the Standard Specifications for Construction.
  
 +
{{top}}
  
 
==CONSTRUCTION==
 
==CONSTRUCTION==
Line 70: Line 72:
 
Placement is not permitted if there is rain, or threatening weather, and temperatures are forecast to be below 32°F (0°C) within 24 hours of completion of work.  The chip seal will not be applied if the air or pavement surface temperature is below 55°F (13°C).
 
Placement is not permitted if there is rain, or threatening weather, and temperatures are forecast to be below 32°F (0°C) within 24 hours of completion of work.  The chip seal will not be applied if the air or pavement surface temperature is below 55°F (13°C).
  
 +
{{top}}
  
 
===Equipment===
 
===Equipment===
Line 77: Line 80:
 
The pressure distributor shall meet the same requirements as discussed in [[502 - HMA Construction Practices|Section 502]] of this manual.
 
The pressure distributor shall meet the same requirements as discussed in [[502 - HMA Construction Practices|Section 502]] of this manual.
  
 +
{{top}}
  
 
====Chip Spreader====
 
====Chip Spreader====
Line 82: Line 86:
 
The chip spreader shall be self-propelled, equipped with pneumatic tires and a screen to remove oversize material.  It shall be capable of uniformly spreading the cover material at the designated rate.
 
The chip spreader shall be self-propelled, equipped with pneumatic tires and a screen to remove oversize material.  It shall be capable of uniformly spreading the cover material at the designated rate.
  
 +
{{top}}
  
 
====Roller====
 
====Roller====
Line 87: Line 92:
 
A self-propelled, pneumatic tired roller weighing more than 8 tons shall be used.
 
A self-propelled, pneumatic tired roller weighing more than 8 tons shall be used.
  
 +
{{top}}
  
 
====Miscellaneous Equipment====
 
====Miscellaneous Equipment====
Line 92: Line 98:
 
A power broom and all necessary hand tools, thermometers, etc. shall be provided.
 
A power broom and all necessary hand tools, thermometers, etc. shall be provided.
  
 +
{{top}}
  
 
==MEASUREMENT AND PAYMENT==
 
==MEASUREMENT AND PAYMENT==
Line 101: Line 108:
  
 
It is very important that sufficient rolling be done to embed the cover material into the HMA emulsion and that any loose material be broomed off before allowing traffic onto the new surface.
 
It is very important that sufficient rolling be done to embed the cover material into the HMA emulsion and that any loose material be broomed off before allowing traffic onto the new surface.
 +
 +
{{top}}

Revision as of 13:49, 25 June 2013

505
Chip seal
2012 STANDARD SPECIFICATIONS FOR CONSTRUCTION - SECTION 505


GENERAL

Pre-Paving Meeting

A pre-paving conference between the Contractor and the Engineer should be held on site prior to beginning work.

Items to be Discussed at the Pre-Paving Conference
1

The detailed work schedule.

2

The traffic control plan.

3

Equipment calibration and adjustments.

4

Overall safety plan.

5

Any special items within the contract.

6

Exchange list of key personnel assigned to the project.

[top of page]


MATERIALS

The asphalt emulsion must be a certified product and be supplied by a certified supplier. The Contractor must maintain quality control and uniformity in testing procedures. The Contractor must submit to the Engineer a daily report showing the test results, as well as other information addressed in subsection 506.02.A.1.c of the Standard Specifications for Construction.

[top of page]


CONSTRUCTION

The surface shall have all dirt, debris and vegetation removed. The asphalt emulsion shall not be placed until the surface is approved by the Engineer.

The asphalt emulsion shall be uniformly applied at an application temperature between 145°F (63°C) and 190°F (88°C). At no time during the operation shall the asphalt emulsion distributor be more than 150 feet (45 m) ahead of the chip spreader.

Immediately following the application of the asphalt emulsion, the chips shall be uniformly spread over the surface at the specified rate.

The rolling shall be done before the asphalt emulsion has cured. At no time shall there be more than 150 feet (45 m) of unrolled cover material. No cover material shall be left unrolled for more than 5 minutes.

Brooming shall be performed within 24 hours of application. Brooming may begin within 6 hours of the application.

Placement is not permitted if there is rain, or threatening weather, and temperatures are forecast to be below 32°F (0°C) within 24 hours of completion of work. The chip seal will not be applied if the air or pavement surface temperature is below 55°F (13°C).

[top of page]


Equipment

Equipment shall be safe, environmentally acceptable and capable of producing a product that meets the specifications.

The pressure distributor shall meet the same requirements as discussed in Section 502 of this manual.

[top of page]


Chip Spreader

The chip spreader shall be self-propelled, equipped with pneumatic tires and a screen to remove oversize material. It shall be capable of uniformly spreading the cover material at the designated rate.

[top of page]


Roller

A self-propelled, pneumatic tired roller weighing more than 8 tons shall be used.

[top of page]


Miscellaneous Equipment

A power broom and all necessary hand tools, thermometers, etc. shall be provided.

[top of page]


MEASUREMENT AND PAYMENT

Delayed Acceptance

This type of project has a 30 day delayed acceptance procedure. Any major problems with the project will have to be corrected before the project will be accepted. The inspector must observe the operation to ensure that the Contractor is following all safety rules and has proper traffic control. The surfacing operation is the responsibility of the Contractor. However, if the inspector observes a nonuniform surface, safety violations or traffic control violations, the Contractor must be notified immediately. If the Contractor does not correct these violations, the project should be stopped.

It is very important that sufficient rolling be done to embed the cover material into the HMA emulsion and that any loose material be broomed off before allowing traffic onto the new surface.