Difference between revisions of "Dispute Review Board (DRB)"
JohnsonN23 (talk | contribs) m (deleted duplicate content) |
JohnsonN23 (talk | contribs) m |
||
Line 3: | Line 3: | ||
This DRB Procedured describes the Michigan Department of Transportation (MDOT) procedures for submittal and review of Contractor claims and Contractor performance evaluation appeals using a Dispute Review Board (DRB). The Dispute Review Board (DRB) process is used on projects that have incorporated the Special Provision for Dispute Review Board. The DRB process is used on Contractor claims and Contractor performance evaluation appeals as described within. | This DRB Procedured describes the Michigan Department of Transportation (MDOT) procedures for submittal and review of Contractor claims and Contractor performance evaluation appeals using a Dispute Review Board (DRB). The Dispute Review Board (DRB) process is used on projects that have incorporated the Special Provision for Dispute Review Board. The DRB process is used on Contractor claims and Contractor performance evaluation appeals as described within. | ||
− | The most current DRB Procedures (Effictice for all projects let on and after March 4, 2016) are published on the website and linked below: | + | The most current DRB Procedures (Effictice for all projects let on and after March 4, 2016) are published on the website and linked below:<br /> |
[http://www.michigan.gov/documents/mdot/MDOT_Contractor_Evaluation_Factors_Rating_Criteria_559990_7.pdf Dispute Review Board (DRB) Operating Procedures (effictive for all projects let on and after March 4, 2016)]. | [http://www.michigan.gov/documents/mdot/MDOT_Contractor_Evaluation_Factors_Rating_Criteria_559990_7.pdf Dispute Review Board (DRB) Operating Procedures (effictive for all projects let on and after March 4, 2016)]. | ||
Revision as of 12:08, 1 June 2017
Dispute Review Board (DRB) Procedures
This DRB Procedured describes the Michigan Department of Transportation (MDOT) procedures for submittal and review of Contractor claims and Contractor performance evaluation appeals using a Dispute Review Board (DRB). The Dispute Review Board (DRB) process is used on projects that have incorporated the Special Provision for Dispute Review Board. The DRB process is used on Contractor claims and Contractor performance evaluation appeals as described within.
The most current DRB Procedures (Effictice for all projects let on and after March 4, 2016) are published on the website and linked below:
Dispute Review Board (DRB) Operating Procedures (effictive for all projects let on and after March 4, 2016).
NOTE: For projects let before March 4, 2016 please reference the applicable DRB procedures linked below.