<center><span STYLE="font: 80pt arial;">'''CONSTRUCTION MANUAL'''</span></center>
+
<center><span STYLE="font: 25pt arial;">'''CONSTRUCTION MANUAL'''</span></center>
  
  
 +
<center>[[File:logo.jpg|250px]]</center>
  
<center><span STYLE="font: 50pt arial;">2012</span></center>
 
  
  
 +
<center><span STYLE="font: 20pt arial;">'''Bureau of Field Services'''</span></center>
  
<center>[[File:logo.jpg|100]]</center>
+
<center><span STYLE="font: 15pt arial;">''Construction Field Services Division''</span></center>
  
 +
<span style="float: right;">
 +
<center><span style="float: right;">[[File:DI-06801-092.jpg|450px|thumb|right|Box culvert construction on M-10 in Clare County.]]</span></center>
 +
</span>
  
 +
=[[#MDOT Mission Statement|MDOT Mission Statement]]=
 +
Providing the highest quality integrated transportation services for economic benefit and improved quality of life.
  
  
<center>'''Bureau of Field Services'''</center>
+
=[[Current News|<font color="red">Current News</font>]]=
  
<center>'''Construction Field Services Division '''</center>
+
==[[#New FieldManager Helpdesk Number|New FieldManager Helpdesk Number]]==
 +
The FieldManager Helpdesk activated its new phone number, '''1-844-4MI-MDOT''' (1-844-464-6368). On the new phone menu, you can reach the FieldManager Helpdesk by selecting option 2 for AASHTOWare and then option 3 for FieldManager. The old number was deactivated on May 1st. The new number is part of the new unified help desk solution, MI MDOT Software Support, used to track and resolve software related issues from customers.
 +
[[File:MI MDOT Software Support.png|center|200px]]
  
<center>Text </center>
+
{{top}}
  
== Heading text ==
+
==[[#Recent Major Changes|Recent Major Changes]]==
 +
The table below is a list of Major changes. 
 +
<div style="overflow:auto; height:200px; width:700px">
 +
{| class="wikitable" style="background:orange; color:black"
 +
!Updated!! Division !! Section !! Summary !! What Changed
 +
|-
 +
|<center>6/8/2021</center>||<center>1</center>||<center>[[107.01_Laws_to_be_Observed|107.01]]</center>||Created Section 107.01 Laws to be Observed||[https://mdotwiki.state.mi.us/construction/index.php/107.01_Laws_to_be_Observed View Here]
 +
|-
  
=== SubHeading ===
+
|<center>5/11/2021</center>||<center>1 Supplemental</center>||<center>[[Certified_Office_Technician_Process#Office_Technician_Certification_Requirements|Certified Office Technician Process]]</center>||Clarification of Prerequisites for Office Tech Certification||[https://mdotwiki.state.mi.us/construction/index.php?title=Certified_Office_Technician_Process&type=revision&diff=6216&oldid=6167 Compare Here]
 +
|-
 +
|<center>4/19/2021</center>||<center>1</center>||<center>[[109.07_Final_Inspection,_Acceptance,_and_Final_Payment#Final_Estimates|109.07]]</center>||Updated Final Estimates information||[https://mdotwiki.state.mi.us/construction/index.php?title=109.07_Final_Inspection%2C_Acceptance%2C_and_Final_Payment&type=revision&diff=6151&oldid=5946 Compare Here]
 +
|-
 +
|<center>3/15/2021</center>||<center>1</center>||<center>[[Digital_Calculations_for_Payment|104]]</center>||Created new Digital Calculations for Payment section under Division 1, Section 104||[https://mdotwiki.state.mi.us/construction/index.php/Digital_Calculations_for_Payment View Here]
 +
|-
 +
|<center>2/9/2021</center>||<center>7</center>||<center>[[712_-_Bridge_Rehabilitation,_Concrete#Hydrodemolition|712]]</center>||Added the Site Activation/Deactivation information||[http://mdotwiki.state.mi.us/construction/index.php?title=712_-_Bridge_Rehabilitation%2C_Concrete&diff=6115&oldid=5606 Compare Here]
 +
|-
 +
|<center>2/9/2021</center>||<center>7</center>||<center>[[715_-_Cleaning_and_Coating_Existing_Structural_Steel#Other_Documentation|715]]</center>||Updated information under Item #6, Site Activation/Deactivation||[http://mdotwiki.state.mi.us/construction/index.php?title=715_-_Cleaning_and_Coating_Existing_Structural_Steel&diff=6118&oldid=5598 Compare Here]
 +
|-
 +
|<center>10/19/2020</center>||<center>1 Supplemental</center>||<center>[[Construction_Field_Services_Indirect_Testing_Charges|Construction Field Services Indirect Testing Charges]]</center>||Updated Construction Field Services Indirect Testing codes||[http://mdotwiki.state.mi.us/construction/index.php?title=Construction_Field_Services_Indirect_Testing_Charges&diff=6059&oldid=5659 Compare Here]
 +
|-
 +
|<center>9/28/2020</center>||<center>7</center>||<center>[[700_-_Closure_of_Unsafe_Structures|700]]</center>||Created new section 700-Closure of Unsafe Structures under Division 7.||[http://mdotwiki.state.mi.us/construction/index.php/700_-_Closure_of_Unsafe_Structures View Here]
 +
|-
 +
|<center>9/24/2020</center>||<center>1 Supplemental</center>||<center>[[FieldManager#top|FieldManager]]</center>||Added new item Bi-Annual FieldManager User Account Verification Process||[http://mdotwiki.state.mi.us/construction/index.php/FieldManager#Bi-Annual_FieldManager_User_Account_Verification_Process View Here]
 +
|-
 +
|<center>9/21/2020</center>||<center>1 Supplemental</center>||<center>[[E-Construction#General_Procedures_for_Construction_Records_Retention|E-Construction General Procedures for Construction Records Retention]]</center>||Updated Records Retention content and Training Manual||[http://mdotwiki.state.mi.us/construction/index.php?title=E-Construction&diff=6038&oldid=5982 Compare Here]
 +
|-
 +
|<center>8/12/2020</center>||<center>4</center>||<center>[[Mandrel_Testing_of_Plastic_Pipe|Mandrel Testing of Plastic Pipe]]</center>||A new Mandrel Testing of Plastic Pipe page was created to provide all-inclusive, in-depth descriptions with images. In sections 401 and 402, under Mandrel Testing, there is a link to the new page.||[http://mdotwiki.state.mi.us/construction/index.php/Mandrel_Testing_of_Plastic_Pipe View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1 Supplemental</center>||<center>[[Local_Agency_Program_(LAP)|Local Agency Program (LAP)]]</center>||Updated Local Agency Program (LAP) guidance including an index for program specific project administration instructions labeled as 'LAP Project Considerations' within various sections of the manual||[http://mdotwiki.state.mi.us/construction/index.php?title=Local_Agency_Program_%28LAP%29&diff=5987&oldid=5715 Compare Here]
 +
|-
 +
|<center>8/3/2020</center>||<center>1</center>||<center>[[109.08_Prompt_Payment#Prompt_Payment|109.08]]</center>||Updated MERS User Guide||[http://mdotwiki.state.mi.us/construction/index.php?title=109.08_Prompt_Payment&diff=5997&oldid=5782 Compare Here]
 +
|-
 +
|<center>7/30/2020</center>||<center>1</center>||<center>[[Structural_Fabrication_Quality_Manual|105]]</center>||Created new Structural Fabrication Quality Manual page under Section 105||[http://mdotwiki.state.mi.us/construction/index.php/Structural_Fabrication_Quality_Manual View Here]
 +
|-
 +
|<center>7/28/2020</center>||<center>8</center>||<center>[[812_-_Temporary_Traffic_Control_for_Construction_Zone_Operations#top|812]]</center>||Added new subsection "Overhead Sign Covers" with examples||[http://mdotwiki.state.mi.us/construction/index.php/812_-_Temporary_Traffic_Control_for_Construction_Zone_Operations#OVERHEAD_SIGN_COVERS View Here]
 +
|-
 +
|<center>7/22/2020</center>||<center>1</center>||<center>[[109.05_Payment_for_Contract_Revisions#Materials|109.05]]</center>||Removed Proof of Payment Requirement for Materials in Force Account||[http://mdotwiki.state.mi.us/construction/index.php?title=109.05_Payment_for_Contract_Revisions&diff=5915&oldid=5620 Compare Here]
 +
|-
 +
|<center>7/22/2020</center>||<center>1</center>||<center>[[Materials_Quality_Assurance_Procedures_Manual|105]]</center>||Added 2020 MQAP content||[http://mdotwiki.state.mi.us/construction/index.php/Materials_Quality_Assurance_Procedures_Manual#2020_Summary_of_Revision_to_the_MQAP View Here]
 +
|-
 +
|<center>6/30/2020</center>||<center>1 Supplemental</center>||<center>[[104.07_Contractor_Obligations#Project_.26_Worksite_Safety|104.07]]</center>||Updated content for the Project & Worksite Safety subsection||[http://mdotwiki.state.mi.us/construction/index.php?title=104.07_Contractor_Obligations&action=historysubmit&diff=5871&oldid=5826 Compare Here]
 +
|-
 +
|<center>6/30/2020</center>||<center>1 Supplemental</center>||<center>[[FPR_Frequently_Asked_Questions|FPR Frequently Asked Questions]]</center>||Created a new FPR Frequently Asked Questions page||[http://mdotwiki.state.mi.us/construction/index.php/FPR_Frequently_Asked_Questions View Here]
 +
|-
 +
|<center>6/25/2020</center>||<center>1 Supplemental</center>||<center>[[FHWA_CAP_Action_Plans|FHWA CAP Action Plans]]</center>||Created a new FHWA CAP Action Plans page to address IDR issues||[http://mdotwiki.state.mi.us/construction/index.php/FHWA_CAP_Action_Plans View Here]
 +
|-
 +
|<center>6/24/2020</center>||<center>1 Supplemental</center>||<center>[[Final_Project_Review_Report|Final Project Review Report]]</center>||Created a new Final Project Review Report page||[http://mdotwiki.state.mi.us/construction/index.php/Final_Project_Review_Report View Here]
 +
|-
 +
|<center>6/9/2020</center>||<center>1 Supplemental</center>||<center>[[Interim_File_Review|Interim File Review]]</center>||Created a new Interim File Review page||[http://mdotwiki.state.mi.us/construction/index.php/Interim_File_Review View Here]
 +
|-
 +
|<center>5/13/2020</center>||<center>1 Supplemental</center>||<center>[[109.07_Final_Inspection,_Acceptance,_and_Final_Payment|109.07]]</center>||Removed the e-File Project Review Procedures from Section 109.07||[http://mdotwiki.state.mi.us/construction/index.php?title=109.07_Final_Inspection%2C_Acceptance%2C_and_Final_Payment&diff=5812&oldid=5776 Compare Here]
 +
|-
 +
|<center>5/13/2020</center>||<center>1 Supplemental</center>||<center>[[Letter_to_File|Letter to File]]</center>||Created a new Letter to File page||[http://mdotwiki.state.mi.us/construction/index.php/Letter_to_File View Here]
 +
|-
 +
|<center>5/13/2020</center>||<center>1 Supplemental</center>||<center>[[Project_Closeout_Escalation_of_Accountability|Project Closeout Escalation of Accountability]]</center>||Created a new Project Closeout Escalation of Accountability page||[http://mdotwiki.state.mi.us/construction/index.php/Project_Closeout_Escalation_of_Accountability View Here]
 +
|-
 +
|<center>5/12/2020</center>||<center>1 Supplemental</center>||<center>[[Final_Project_Review|Final Project Review]]</center>||Created a new Final Project Review page||[http://mdotwiki.state.mi.us/construction/index.php/Final_Project_Review View Here]
 +
|-
 +
|<center>4/28/2020</center>||<center>1 Supplemental</center>||<center>[[Certified_Engineer_Process|Certified Engineer Process]]</center>||Created new Certified Engineer Process page||[http://mdotwiki.state.mi.us/construction/index.php/Certified_Engineer_Process View Here]
 +
|-
 +
|<center>4/21/2020</center>||<center>1</center>||<center>[[109.08_Prompt_Payment|109.08]]</center>||Created new Prompt Payment section with flow chart ||[http://mdotwiki.state.mi.us/construction/index.php/109.08_Prompt_Payment View Here]
 +
|-
 +
|<center>2/12/2020</center>||<center>1</center>||<center>[[102.02_Contents_of_Proposal_-_Progress_Clause#Boilerplate_Progress_Clause|102.02]]</center>||Updated to Boilerplate Progress Clause Template [//{{SERVERNAME}}/images_construction/4/40/Boilerplate_Progress_Clause_Template_2-10-20.docx (Revision 2/10/2020)]||[http://mdotwiki.state.mi.us/construction/index.php?title=102.02_Contents_of_Proposal_-_Progress_Clause&diff=5717&oldid=5567 Compare It]
 +
|-
 +
|<center>01/23/2020</center>||<center>1</center>||<center>[[104.07_Contractor_Obligations#Worker_Visibility|104.07]]</center>||Update to Worker Visibility information and photos||[http://mdotwiki.state.mi.us/construction/index.php?title=104.07_Contractor_Obligations&diff=5710&oldid=4920 Compare It]
 +
|-
 +
|<center>01/21/2020</center>||<center>1</center>||<center>[[Preconstruction_Meeting|102]]</center>||Update to Local Agency Boilerplate Preconstruction Meeting Minutes - January 2020||[//{{SERVERNAME}}/images_construction/5/5d/LOCAL_AGENCY_Boilerplate_Preconstruction_Meeting_Minutes_-_January_2020.docx View Here]
 +
|-
 +
|<center>01/21/2020</center>||<center>2</center>||<center>[[208_-_Soil_Erosion_and_Sedimentation_Control_(NPDES)|208]]</center>||Update for entire Soil Erosion and Sedimentation Control (NPDES) section||[http://mdotwiki.state.mi.us/construction/index.php?title=208_-_Soil_Erosion_and_Sedimentation_Control_%28NPDES%29&diff=5694&oldid=5664 Compare It]
 +
|-
 +
|<center>10/22/2019</center>||<center>1 Supplemental</center>||<center>[[Construction_Field_Services_Indirect_Testing_Charges#Inappropriate_Use|Construction Field Services Indirect Testing Charges]]</center>||Update for FY 2020 Indirect Testing Coding||[http://mdotwiki.state.mi.us/construction/index.php?title=Construction_Field_Services_Indirect_Testing_Charges&action=historysubmit&diff=5654&oldid=5400 Compare It]
 +
|-
 +
|<center>9/26/2019</center>||<center>1</center>||<center>[[Materials_Quality_Assurance_Procedures_Manual| 105]]</center>||2019 Summary of revisions to the Materials Quality Assurance Procedures Manual ||[http://mdotwiki.state.mi.us/construction/index.php?title=Materials_Quality_Assurance_Procedures_Manual&diff=5642&oldid=5497 Compare It]
 +
|-
 +
|<center>9/26/2019</center>||<center>8</center>||<center>[[811_-_Permanent_Pavement_Markings#Field_Inspection_and_Processing_of_Progress_Payments|811]]</center>||Permanent Pavement Markings Field Inspection and Processing of Progress Payments: Updated new content ||[http://mdotwiki.state.mi.us/construction/index.php?title=811_-_Permanent_Pavement_Markings&diff=5640&oldid=5632 Compare It]
 +
|-
 +
|<center>9/18/2019</center>||<center>6</center>||<center>[[602_-_Concrete_Pavement_Construction#Load_Transfer_Assemblies|602]]</center>||Load Transfer Assemblies: Updated new content and included Presentation for Load Transfer Assemblies Inspections||[http://mdotwiki.state.mi.us/construction/index.php?title=602_-_Concrete_Pavement_Construction&diff=5629&oldid=5556 Compare It]
 +
|-
 +
|<center>9/18/2018</center>||<center>8</center>||<center>[[811_-_Permanent_Pavement_Markings|811]]</center>||Updated Paint pricing for 2019||[http://mdotwiki.state.mi.us/construction/index.php/811_-_Permanent_Pavement_Markings#UNIFORM_PRICE_ADJUSTMENT.2C_REGULAR_DRY_PAINT_AND_LOW_TEMPERATURE_WATERBORNE_PAINT View Updated Table Here]
 +
|-
 +
|<center>8/30/2019</center>||<center>1</center>||<center>[[Preconstruction_Meeting|102]]</center>||Update to Trunkline Boilerplate Preconstruction Meeting Minutes - 2019||[//{{SERVERNAME}}/images_construction/5/5e/TRUNKLINE_Boilerplate_Preconstruction_Meeting_Minutes_2019_Final.docx View Here]
 +
|-
 +
|<center>8/20/2019</center>||<center>1 Supplemental</center>||<center>[[FieldManager#Standard_Rounding_Convention_Guidance|FieldManager]]</center>||New guidance related to the Standard Rounding Convention ||[http://mdotwiki.state.mi.us/construction/index.php?title=FieldManager&diff=5615&oldid=5386 Compare It]
 +
|-
 +
|<center>7/31/2019</center>||<center>Main Page</center>||<center>Main Page</center>||July update to the Documentation Guide which includes corrections related to density requirements. It also includes updated language related to the [//{{SERVERNAME}}/images_construction/6/6a/Documentation_Guide_Final_Draft_07-29-19.pdf#page=3 "e-Final Project Review Procedures"]||[//{{SERVERNAME}}/images_construction/6/6a/Documentation_Guide_Final_Draft_07-29-19.pdf View Here]
 +
|-
 +
|}
 +
</div>
 +
A definition to the types of changes that you might see in the Construction Manual can be found under [[Content_Revision_Procedures#Types_of_Changes|Content Revision Procedures, Types of Changes]].
  
 +
{{top}}
  
<center></center>
+
==[[#Recent Minor Changes|Recent Minor Changes]]==
 +
The table below is a list of Minor changes. 
 +
<div style="overflow:auto; height:200px; width:700px">
 +
{| class="wikitable" style="background:yellow; color:black"
 +
|-
 +
!Updated!! Division !! Section !! Summary !! What Changed
 +
|-
 +
|<center>6/8/2021</center>||<center>1</center>||<center>[[102.02_Contents_of_Proposal_-_Progress_Clause#LAP_Project_Considerations|102.02]]</center>||Updated Progress Clause Template for LAP Projects (May 2021) document||[https://mdotwiki.state.mi.us/images_construction/4/49/Progress_Clause_Template_LAP_projects_2020_Specs_FINAL_05192021_726007_7.pdf View Here]
 +
|-
 +
|<center>6/8/2021</center>||<center>1 Supplemental</center>||<center>[[Certified_Engineer_Process#Current_Certified_Engineers|Current Certified Engineers]]</center>||Updated certified engineer list to June 2021||[https://mdotwiki.state.mi.us/images_construction/1/11/Engineer_certification_list_-_JUNE_2021.pdf View Here]
 +
|-
 +
|<center>5/24/2021</center>||<center>1 Supplemental</center>||<center>[[E-Signature|E-Signature]]</center>||Edited FHWA Electronic Signature information.||[https://mdotwiki.state.mi.us/construction/index.php?title=E-Signature&type=revision&diff=6262&oldid=6260 Compare Here]
 +
|-
 +
|<center>5/20/2021</center>||<center>1 Supplemental</center>||<center>[[E-Signature|E-Signature]]</center>||Added E-Signature Guidance for FHWA staff as non-MDOT users.||[https://mdotwiki.state.mi.us/construction/index.php?title=E-Signature&type=revision&diff=6260&oldid=6171 Compare Here]
 +
|-
 +
|<center>4/28/2021</center>||<center>1 Supplemental</center>||<center>[[Local_Agency_Program_(LAP)#Local_Agency_Program_Assistance.2FResources|Local Agency Program]]</center>||Updated FieldManager contact info (web address and e-mail).||[https://mdotwiki.state.mi.us/construction/index.php?title=Local_Agency_Program_%28LAP%29&type=revision&diff=6153&oldid=5987 Compare Here]
 +
|-
 +
|<center>3/17/2021</center>||<center>8</center>||<center>[[811_-_Permanent_Pavement_Markings#Material_Documentation|811]]</center>||Updated information on the Permanent Pavement Markings, Material Documentation section.||[https://mdotwiki.state.mi.us/construction/index.php?title=811_-_Permanent_Pavement_Markings&type=revision&diff=6141&oldid=6047 Compare Here]
 +
|-
 +
|<center>3/3/2021</center>||<center>2</center>||<center>[[208_-_Soil_Erosion_and_Sedimentation_Control_(NPDES)#Contractor_Obligation|208]]</center>||Revised to add requirement to notify CFS resource specialist when Form 1568 for Project Staging or Excess Material Location on MDOT ROW is approved||[https://mdotwiki.state.mi.us/construction/index.php?title=208_-_Soil_Erosion_and_Sedimentation_Control_%28NPDES%29&type=revision&diff=6130&oldid=5694 Compare Here]
 +
|-
 +
|<center>2/8/2021</center>||<center>1 Supplemental</center>||<center>[[Certified_Engineer_Process#Current_Certified_Engineers|Certified Engineer List]]</center>||Updated the Certified Engineer List as of February 2021.||[http://mdotwiki.state.mi.us/construction/index.php/Certified_Engineer_Process#Current_Certified_Engineers View Here]
 +
|-
 +
|<center>2/2/2021</center>||<center>1</center>||<center>[[104.10_Contractor_Claim_for_Extra_Compensation_or_Time_Extension#General|104.10]]</center>||Updated the MDOT Claims Procedure with a revised version.||[http://mdotwiki.state.mi.us/construction/index.php?title=104.10_Contractor_Claim_for_Extra_Compensation_or_Time_Extension&diff=6107&oldid=5896 Compare Here]
 +
|-
 +
|<center>1/6/2021</center>||<center>1</center>||<center>[[102.02_Contents_of_Proposal_-_Progress_Clause|102.02]]</center>||Replace the two current subsections; Determination of Work Days and Critical Path Networks, with single section titled [[102.02_Contents_of_Proposal_-_Progress_Clause#Contract_Time_Determination_.28CTD.29|“Contract Time Determination”]]||[http://mdotwiki.state.mi.us/construction/index.php?title=102.02_Contents_of_Proposal_-_Progress_Clause&diff=6096&oldid=6094 Compare Here]
 +
|-
 +
|<center>1/5/2021</center>||<center>1</center>||<center>[[102.02_Contents_of_Proposal_-_Progress_Clause|102.02]]</center>||Added Controller Cabinet and Detection Equipment to Typical Long-Lead Items Table||[http://mdotwiki.state.mi.us/construction/index.php?title=102.02_Contents_of_Proposal_-_Progress_Clause&diff=6094&oldid=6045 Compare Here]
 +
|-
 +
|<center>1/5/2021</center>||<center>4</center>||<center>[[402_-_Storm_Sewers#Illicit_Connections|402]]</center>||Update related to Illicit Connections||[http://mdotwiki.state.mi.us/construction/index.php?title=402_-_Storm_Sewers&diff=6092&oldid=6020 Compare Here]
 +
|-
 +
|<center>11/30/2020</center>||<center>1 Supplemental</center>||<center>[[FieldManager#Inspector.27s_Daily_Report_.28IDR.29|Inspector's Daily Report]]</center>||Updated instructions||[http://mdotwiki.state.mi.us/construction/index.php?title=FieldManager&diff=6084&oldid=6043 Compare Here]
 +
|-
 +
|<center>10/29/2020</center>||<center>[[Naming_Convention#Standard_Naming_Convention_for_Documents|E-Construction]]</center>||<center>[[Naming_Convention#Standard_Naming_Convention_for_Documents|Standard Naming Convention for Documents]]</center>||Updated Naming Convention Table to reflect recent changes. Also included updated [//{{SERVERNAME}}/images_construction/0/08/Standard_Naming_Convention_Revised_10-29-2020.pdf PDF] and [//{{SERVERNAME}}/images_construction/8/8a/Standard_Naming_Convention_Revised_10-29-2020.xlsx XLSX] files (Rev 10-29-20)||[http://mdotwiki.state.mi.us/construction/index.php?title=E-Construction&diff=6063&oldid=6058 Compare It]
 +
|-
 +
|<center>9/24/2020</center>||<center>8</center>||<center>[[811_-_Permanent_Pavement_Markings#Uniform_Price_Adjustment.2C_Regular_Dry_Paint_and_Low_Temperature_Waterborne_Paint|811]]</center>||Updated Permanent Pavement Markings payment table to include 2020 prices||[http://mdotwiki.state.mi.us/construction/index.php?title=811_-_Permanent_Pavement_Markings&diff=6047&oldid=5647 Compare Here]
 +
|-
 +
|<center>9/24/2020</center>||<center>1</center>||<center>[[102.02_Contents_of_Proposal_-_Progress_Clause|102.02]]</center>||Added Guardrail-Steel to the Long-Lead item table||[http://mdotwiki.state.mi.us/construction/index.php?title=102.02_Contents_of_Proposal_-_Progress_Clause&diff=6045&oldid=5947 Compare Here]
 +
|-
 +
|<center>9/15/2020</center>||<center>Disadvantaged Business Enterprises (DBE)</center>||<center>[[Disadvantaged_Business_Enterprises_(DBE)#Title_VI_Coordinator|Disadvantaged Business Enterprises (DBE)]]</center>||Updated contact information for MDOT's Title VI Coordinator to [mailto:CurryO@michigan.gov Orlando Curry]  517-241-7462||[http://mdotwiki.state.mi.us/construction/index.php?title=Disadvantaged_Business_Enterprises_%28DBE%29&diff=6034&oldid=5825 View Here]
 +
|-
 +
|<center>8/11/2020</center>||<center>1 Supplemental</center>||<center>[[Certified_Engineer_Process|Certified Engineer Process]]</center>||Updated Record Certification List with added Consultants||[http://mdotwiki.state.mi.us/construction/index.php/Certified_Engineer_Process#Current_Certified_Engineers View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1 Supplemental</center>||<center>[[FieldManager#LAP_Project_Considerations|FieldManager]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/FieldManager#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1 Supplemental</center>||<center>[[Plans,_Proposal,_Input,_Review_and_Evaluation#LAP_Project_Considerations|Plans, Proposal, Input, Review and Evaluation]]</center>||Added 'LAP Project Considerations' to the section under Design/Construction Package Evaluation||[http://mdotwiki.state.mi.us/construction/index.php/Plans,_Proposal,_Input,_Review_and_Evaluation#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1 Supplemental</center>||<center>[[Plans,_Proposal,_Input,_Review_and_Evaluation#LAP_Project_Considerations_2|Plans, Proposal, Input, Review and Evaluation]]</center>||Added 'LAP Project Considerations' to the section under Post-Construction Reviews||[http://mdotwiki.state.mi.us/construction/index.php/Plans,_Proposal,_Input,_Review_and_Evaluation#LAP_Project_Considerations_2 View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[Preconstruction_Meeting#LAP_Project_Considerations|102]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/Preconstruction_Meeting#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[102.01_Prequalification_of_Bidders#LAP_Project_Considerations|102.01]]</center>||Added 'LAP Project Considerations' to the section under Processing of Contractor Performance Evaluations||[http://mdotwiki.state.mi.us/construction/index.php/102.01_Prequalification_of_Bidders#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[102.02_Contents_of_Proposal_-_Progress_Clause#LAP_Project_Considerations|102.02]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/102.02_Contents_of_Proposal_-_Progress_Clause#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[Extending_Project_Limits#LAP_Project_Considerations|103]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/Extending_Project_Limits#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[103.02_Contract_Revisions#LAP_Project_Considerations|103.02]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/103.02_Contract_Revisions#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[103.02_Contract_Revisions#LAP_Project_Considerations|103.02]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/103.02_Contract_Revisions#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[104.10_Contractor_Claim_for_Extra_Compensation_or_Time_Extension#LAP_Project_Considerations|104.10]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/104.10_Contractor_Claim_for_Extra_Compensation_or_Time_Extension#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[108.07_Extension_of_Time_on_Work_Day_Contracts|108.07]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/108.07_Extension_of_Time_on_Work_Day_Contracts View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[Project_Delays_Due_to_a_Utility_Company#LAP_Project_Considerations|108]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/Project_Delays_Due_to_a_Utility_Company#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations|109.07]]</center>||Added 'LAP Project Considerations' to the section under Final Inspection, Acceptance, and Final Payment-Acceptance of work||[http://mdotwiki.state.mi.us/construction/index.php/109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations_2|109.07]]</center>||Added 'LAP Project Considerations' to the section under Final Inspection, Acceptance, and Final Payment-Pay Estimate and Inactive Project Notification||[http://mdotwiki.state.mi.us/construction/index.php/109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations_2 View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations_3|109.07]]</center>||Added 'LAP Project Considerations' to the section under Final Estimates||[http://mdotwiki.state.mi.us/construction/index.php/109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations_3 View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations_4|109.07]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations_4 View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations_5|109.07]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations_5 View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1</center>||<center>[[109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations_6|109.07]]</center>||Added 'LAP Project Considerations' to the section under Required Signature on Construction Pay Estimates||[http://mdotwiki.state.mi.us/construction/index.php/109.07_Final_Inspection,_Acceptance,_and_Final_Payment#LAP_Project_Considerations_6 View Here]
 +
|-
 +
|<center>8/4/2020</center>||<center>1 Supplemental</center>||<center>[[E-Construction#LAP_Project_Considerations|e-Construction]]</center>||Added 'LAP Project Considerations' to the section||[http://mdotwiki.state.mi.us/construction/index.php/E-Construction#LAP_Project_Considerations View Here]
 +
|-
 +
|<center>7/27/2020</center>||<center>1</center>||<center>[[102.02_Contents_of_Proposal_-_Progress_Clause#Construction_Time_Estimates_-_Production_Rates|102.02]]</center>||Updated MDOT Production Rates link. Old link did not work properly.||[http://mdotwiki.state.mi.us/construction/index.php/102.02_Contents_of_Proposal_-_Progress_Clause#Construction_Time_Estimates_-_Production_Rates View Here]
 +
|-
 +
|<center>7/22/2020</center>||<center>1 Supplemental</center>||<center>[[FieldManager|FieldManager]]</center>||Updated Content for Showing Detail Calculations on Inspector’s Daily Report and Added Rounding Convention Example||[http://mdotwiki.state.mi.us/construction/index.php?title=FieldManager&diff=5938&oldid=5875 Compare Here]
 +
|-
 +
|<center>6/30/2020</center>||<center>1 Supplemental</center>||<center>[[FPR_Frequently_Asked_Questions#How_is_the_Final_Project_Review_Report_updated.3F|FPR Frequently Asked Questions]]</center>||Added FPR Report User Guide link to FPR FAQ page||[http://mdotwiki.state.mi.us/construction/index.php?title=FPR_Frequently_Asked_Questions&diff=5868&oldid=5867 Compare Here]
 +
|-
 +
|<center>6/30/2020</center>||<center>1 Supplemental</center>||<center>[[Final_Project_Review|Final Project Review]]</center>||Added FAQs link for Final Project Review to page||[http://mdotwiki.state.mi.us/construction/index.php?title=Final_Project_Review&diff=5859&oldid=5849 Compare Here]
 +
|-
 +
|<center>6/24/2020</center>||<center>1 Supplemental</center>||<center>[[Project_Closeout_Escalation_of_Accountability|Project Closeout Escalation of Accountability]]</center>||Added links to the new Final Project Review Report page||[http://mdotwiki.state.mi.us/construction/index.php?title=Project_Closeout_Escalation_of_Accountability&diff=5845&oldid=5815 Compare Here]
 +
|-
 +
|<center>6/17/2020</center>||<center>1 Supplemental</center>||<center>[[Certified_Engineer_Process|Certified Engineer Process]]</center>||Reformatted the Certified Engineer Renewal Process for clarity||[http://mdotwiki.state.mi.us/construction/index.php?title=Certified_Engineer_Process&diff=5841&oldid=5840 Compare Here]
 +
|-
 +
|<center>6/9/2020</center>||<center>1 Supplemental</center>||<center>[[Final_Project_Review|Final Project Review]]</center>||Updated Final Project Review page with Interim File Review link||[http://mdotwiki.state.mi.us/construction/index.php?title=Final_Project_Review&diff=5831&oldid=5813 Compare Here]
 +
|-
 +
|<center>06/01/2020</center>||<center>1 Supplemental</center>||<center>[[Certified_Engineer_Process#Current_Certified_Engineers|Certification Programs]]</center>||Updated Engineer Record Certification List||[//{{SERVERNAME}}/images_construction/e/e7/Eng_Record_Cert_list_06-01-2020.pdf View Here]
 +
|-
 +
|<center>5/1/2020</center>||<center>1 Supplemental</center>||<center>[[Dispute_Review_Board_(DRB)| Dispute Review Board (DRB)]]</center>||Added updated DRB Procedures to include those let on and after 6-5-2020/Removed older links||[http://mdotwiki.state.mi.us/construction/index.php?title=Dispute_Review_Board_%28DRB%29&diff=5792&oldid=5137 Compare Here]
 +
|-
 +
|<center>4/30/2020</center>||<center>1 Supplemental</center>||<center>[[Certified_Office_Technician_Process| Certified Office Technician Process]]</center>||Edited page to reflect only Certified Technician Process information||[http://mdotwiki.state.mi.us/construction/index.php?title=Certified_Office_Technician_Process&diff=5787&oldid=5720 Compare Here]
 +
|-
 +
|<center>4/29/2020</center>||<center>1</center>||<center>[[109.07_Final_Inspection,_Acceptance,_and_Final_Payment#Non-Payment_Claims| 109.07]]</center>||Removed "Review of Prompt Payment Complaints" section as it's now its own page||[http://mdotwiki.state.mi.us/construction/index.php?title=109.07_Final_Inspection%2C_Acceptance%2C_and_Final_Payment&diff=5776&oldid=5730 Compare Here]
 +
|-
 +
|<center>4/27/2020</center>||<center>1</center>||<center>[[101.04_-_Inspector%27s_Daily_Reports|101.04 Inspector Daily Reports]]<hr>[[FieldManager|FieldManager]]</center>||Updated Helpdesk number from 517-322-1556 to '''1-844-4MI-MDOT''' (1-844-464-6368) in these sections along with the Main page [http://mdotwiki.state.mi.us/construction/index.php/Main_Page#New_FieldManager_Helpdesk_Number Current News] area above
 +
||[http://mdotwiki.state.mi.us/construction/index.php?title=101.04_-_Inspector%27s_Daily_Reports&diff=5765&oldid=1534 Compare Here]<hr>[http://mdotwiki.state.mi.us/construction/index.php?title=FieldManager&diff=5764&oldid=5713 Compare Here]
 +
|-
 +
|<center>4/22/2020</center>||<center>1</center>||<center>[[102.18_Subletting_Contract_Work_to_Disadvantaged_Business_Enterprises_(DBEs)#Prompt_Payment| 102.18]]</center>||Added the newly created Prompt Payment link to Section 102.18||[http://mdotwiki.state.mi.us/construction/index.php?title=102.18_Subletting_Contract_Work_to_Disadvantaged_Business_Enterprises_%28DBEs%29&diff=5757&oldid=5164 Compare Here]
 +
|-
 +
|<center>4/15/2020</center>||<center>1</center>||<center>[[105.01_Quality_and_Scope_of_Supply| 105.01]]</center>||Changed Density Control Manual to Density Testing and Inspection Manual||[http://mdotwiki.state.mi.us/construction/index.php?title=105.01_Quality_and_Scope_of_Supply&diff=5747&oldid=5745 Compare Here]
 +
|-
 +
|<center>4/14/2020</center>||<center>1</center>||<center>[[105.01_Quality_and_Scope_of_Supply| 105.01]]</center>||Changed Density Control Handbook to Density Control Manual||[http://mdotwiki.state.mi.us/construction/index.php?title=105.01_Quality_and_Scope_of_Supply&diff=5745&oldid=4928 Compare Here]
 +
|-
 +
|<center>3/30/2020</center>||<center>1</center>||<center>[[Prevailing_Wage_Oversight_Procedures#JOBSITE_POSTING| 107]]</center>||Updated Jobsite Poster||[http://mdotwiki.state.mi.us/construction/index.php/Prevailing_Wage_Oversight_Procedures#JOBSITE_POSTING View Here]
 +
|-
 +
|<center>3/20/2020</center>||<center>1</center>||<center>[[Process_for_Documenting_Certified_Materials_in_FieldManager| 105]]</center>||Deleted information no longer applicable, or is covered in other documents/Renamed section due to changes||[http://mdotwiki.state.mi.us/construction/index.php?title=Process_for_Documenting_Certified_Materials_in_FieldManager&diff=5737&oldid=4931 Compare It]
 +
|-
 +
|<center>3/18/2020</center>||<center>1</center>||<center>[[108.01_Subcontracting_of_Contract_Work| 108.01]]</center>||Updated links to the new 1302-Fed form.||[http://mdotwiki.state.mi.us/construction/index.php?title=108.01_Subcontracting_of_Contract_Work&diff=5734&oldid=4975 Compare Here]
 +
|-
 +
|<center>2/21/2020</center>||<center>1</center>||<center>[[103.02_Contract_Revisions#General_Contract_Modification_Information| 103.02]]</center>||General Contract Modification Information Format Revision||[http://mdotwiki.state.mi.us/construction/index.php?title=103.02_Contract_Revisions&diff=5728&oldid=5714 Compare It]
 +
|-
 +
|<center>2/13/2020</center>||<center>[[Naming_Convention#Standard_Naming_Convention_for_Documents|E-Construction]]</center>||<center>[[Naming_Convention#Standard_Naming_Convention_for_Documents|Standard Naming Convention for Documents]]</center>||Updated Naming Convention Table to reflect recent changes. Also included updated [//{{SERVERNAME}}/images_construction/d/d5/Standard_Naming_Convention_Revised_2-13-20.pdf PDF] and [//{{SERVERNAME}}/images_construction/a/a1/Standard_Naming_Convention_Revised_2-13-20.xlsx XLSX] files (Rev 2-13-20)||[http://mdotwiki.state.mi.us/construction/index.php?title=E-Construction&diff=5726&oldid=5576 Compare It]
 +
|-
 +
|<center>02/13/2020</center>||<center>1 Supplemental</center>||<center>[[Certified_Engineer_Process|Certified Engineer Process]]</center>||Updated Engineer Record Certification List||[//{{SERVERNAME}}/images_construction/7/7a/Eng_Record_Cert_list_02-13-2020.pdf View Here]
 +
|-
 +
|<center>01/22/2020</center>||<center>Prevailing Wage Oversight Procedures</center>||<center>[[Prevailing_Wage_Oversight_Procedures#JOBSITE_POSTING| Jobsite Posting]]</center>||Updated contact information on the Title VI Poster and Coordinator site information||[http://mdotwiki.state.mi.us/construction/index.php?title=Prevailing_Wage_Oversight_Procedures&diff=5703&oldid=5036 Compare It]
 +
|-
 +
|<center>11/12/2019</center>||<center>2</center>||<center>[[208_-_Soil_Erosion_and_Sedimentation_Control_(NPDES)#Notification_2| 208]]</center>||Soil Erosion and Sedimentation Control Notifications: Updated Notice of Coverage (NOC) and Notice of Termination (NOT) charts||[http://mdotwiki.state.mi.us/construction/index.php?title=208_-_Soil_Erosion_and_Sedimentation_Control_%28NPDES%29&diff=5663&oldid=5586 Compare It]
 +
|-
 +
|<center>10/29/2019</center>||<center>1 Supplemental</center>||<center>[[Construction_Field_Services_Indirect_Testing_Charges#Eligibility_and_Use|Indirect Testing Charges - Eligibility and Use]]</center>||Updated first bullet information for clarity and to include examples||[http://mdotwiki.state.mi.us/construction/index.php?title=Construction_Field_Services_Indirect_Testing_Charges&diff=5659&oldid=5654 Compare It]
 +
|-
 +
|<center>10/28/2019</center>||<center>1 Supplemental</center>||<center>[[Certified_Engineer_Process|Certified Engineer Process]]</center>||Updated Engineer Record Certification List||[//{{SERVERNAME}}/images_construction/4/45/Eng_Record_Cert_list_10-23-19.pdf View Here]
 +
|-
 +
|<center>10/3/2019</center>||<center>8</center>||<center>[[811_-_Permanent_Pavement_Markings#Pavement_Marking_Turn_Arrows|811]]</center>||Removal of references to outdated paint marking turn arrows||[http://mdotwiki.state.mi.us/construction/index.php?title=811_-_Permanent_Pavement_Markings&diff=5647&oldid=5640 Compare It]
 +
|-
 +
|<center>8/22/2019</center>||<center>1</center>||<center>[[107.09_Archeological_and_Historical_Findings|107.09]]</center>||Update related to the process for archeological findings||[http://mdotwiki.state.mi.us/construction/index.php?title=107.09_Archeological_and_Historical_Findings&diff=5618&oldid=4933 Compare It]
 +
|-
 +
|<center>7/11/2019</center>||<center>2</center>||<center>[[208_-_Soil_Erosion_and_Sedimentation_Control_(NPDES)|208]]</center>||Added 2 flowcharts for Notice of Coverage (NOC) and Notice of Termination (NOT) in section 208 between “Notification” and “Training”. Also updated language to reflect recent name change of the "Michigan Department of Environmental Quality (MDEQ)" to the "Michigan Department of Environment, Great Lakes, and Energy (EGLE)"||[http://mdotwiki.state.mi.us/construction/index.php?title=208_-_Soil_Erosion_and_Sedimentation_Control_%28NPDES%29&diff=5586&oldid=5241 Compare It]
 +
|-
 +
|}
 +
</div>
  
<center></center>
+
{{top}}
  
<center></center>
+
=[[#Preamble|Preamble]]=
  
<center></center>
+
This manual provides guidance to administrative, engineering, and technical staff.  Engineering practice requires that professionals use a combination of technical skills and judgment in decision making.  Engineering judgment is necessary to allow decisions to account for unique site-specific conditions and considerations to provide high quality products, within budget, and to protect the public health, safety, and welfare.  This manual provides the general operational guidelines; however, it is understood that adaptation, adjustments, and deviations are sometimes necessary.  Innovation is a key foundational element to advance the state of engineering practice and develop more effective and efficient engineering solutions and materials.  As such, it is essential that our engineering manuals provide a vehicle to promote, pilot, or implement technologies or practices that provide efficiencies and quality products, while maintaining the safety, health, and welfare of the public.  It is expected when making significant or impactful deviations from the technical information from these guidance materials, that reasonable consultations with experts, technical committees, and/or policy setting bodies occur prior to actions within the timeframes allowed.  It is also expected that these consultations will eliminate any potential conflicts of interest, perceived or otherwise.  MDOT Leadership is committed to a culture of innovation to optimize engineering solutions.
 +
The National Society of Professional Engineers Code of Ethics for Engineering is founded on six fundamental canons.  Those canons are provided below.
 +
Engineers, in the fulfillment of their professional duties, shall:
 +
::#Hold paramount the safety, health, and welfare of the public.
 +
::#Perform Services only in areas of their competence.
 +
::#Issue public statement only in an objective and truthful manner.
 +
::#Act for each employer or client as faithful agents or trustees.
 +
::#Avoid deceptive acts.
 +
::#Conduct themselves honorably, reasonably, ethically and lawfully so as to enhance the honor, reputation, and usefulness of the profession.
  
<center></center>
 
  
<center>'''FOREWORD'''</center>
+
This manual has been revised throughout to incorporate changes brought about by the release of the 2012 Standard Specifications for Construction and by progress in equipment, construction practices, and materials. The format has been established to follow the standard specification outline with divisions and sections set up to facilitate revision and addition of new information as needed.
  
<center></center>
 
  
<center></center>
+
Additional information about the Wiki Construction Manual and submitting revision suggestions is located in the [[Help:Contents]] page.
  
This manual has been prepared to give information and guidance to construction project personnel associated with the Michigan Department of Transportation (MDOT).  In case of conflict between the Standard Specifications for Construction or contract documents and this manual, the specifications and contract documents will have precedence.
 
  
 
+
{{top}}
 
+
[[Category:Construction Manual]]
This manual has been revised throughout to incorporate changes brought about by the release of the 2012 Standard Specifications for Construction and by progress in equipment, construction practices, and materials. The format has been established to follow the standard specification outline with divisions and sections set up to facilitate revision and addition of new information as needed.
 
 
 
 
 
Testing the changes to wiki page.
 
 
 
 
 
<center>'''MDOT ''''''Mission'''''' Statement:'''</center>
 
 
 
 
 
 
 
<center>Providing the highest quality integrated transportation services</center>
 
 
 
<center>for economic benefit and improved quality of life.</center>
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
<center>'''
 
 
 
'''TABLE OF CONTENTS'''</center>
 
 
 
 
 
 
 
 
 
 
 
'''General - Contract Administration'''
 
 
 
 
 
 
 
[[Division 1 – General Provisions]]
 
 
 
[[101 - General Project Administration|101    Terms, Format, and Definitions]]
 
 
 
102    Bid Submission, Award, and Execution of Contract
 
 
 
103    Scope of the Work
 
 
 
104    Control of the Work
 
 
 
105    Control of Materials
 
 
 
106    Quality Assurance Acceptance Program
 
 
 
107    Legal Relations and Responsibilities to the Public
 
 
 
108    Prosecution and Progress
 
 
 
109    Measurement and Payment
 
 
 
150    Mobilization
 
 
 
 
 
 
 
'''Division 2 - Earthwork'''
 
 
 
201    Clearing
 
 
 
202    Removing Trees, Stumps, and Corduroy
 
 
 
203    Removing Drainage Structures, Culverts, and Sewers
 
 
 
204    Removing Miscellaneous Structures, and Materials
 
 
 
205    Roadway Earthwork
 
 
 
206    Excavation and Backfill for Structures
 
 
 
207    Obliterating Roadway
 
 
 
208    Soil Erosion and Sedimentation Control
 
 
 
209    Project Cleanup
 
 
 
 
 
 
 
'''Division 3 - Bases'''
 
 
 
301    Subbase
 
 
 
302    Aggregate Base Course
 
 
 
303    Open-Graded Drainage Courses
 
 
 
304    Rubblizing Portland Cement Concrete Pavement
 
 
 
305    HMA Base Crushing and Shaping
 
 
 
306    Aggregate Surface Course
 
 
 
307    Aggregate Shoulders and Approaches
 
 
 
308    Geotextile for Base
 
 
 
 
 
 
 
'''Division 4 - Drainage Features'''
 
 
 
401    Pipe Culverts
 
 
 
402    Storm Sewers
 
 
 
403    Drainage Structures
 
 
 
404    Underdrains
 
 
 
405    Pump Station Construction
 
 
 
406    Precast Three-Sided, Arch, AND Box Culverts
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
'''Division 5 - Hot Mix Asphalt Pavements and Surface Treatments'''
 
 
 
501    Plant Produced Hot Mix Asphalt
 
 
 
502    HMA Crack Treatment
 
 
 
503    Paver Placed Surface Seal
 
 
 
504    Micro-Surfacing
 
 
 
505    Chip Seals
 
 
 
506    Slurry Seal
 
 
 
 
 
 
 
'''Division 6 - Portland Cement Concrete Pavements'''
 
 
 
601    Portland Cement Concrete for Pavements
 
 
 
602    Concrete Pavement Construction
 
 
 
603    Concrete Pavement Restoration
 
 
 
604    Contractor Quality Control for Concrete
 
 
 
605    Quality Assurance (Acceptance) for Concrete
 
 
 
 
 
 
 
'''Division 7 - Structures'''
 
 
 
701    Portland Cement Concrete for Structures
 
 
 
702    Mortar and Grout
 
 
 
703    Mortar and Concrete Patching, Repair, and Resurfacing Mixtures
 
 
 
704    Steel Sheet Piling and Cofferdams
 
 
 
705    Foundation Piling
 
 
 
706    Structural Concrete Construction
 
 
 
707    Structural Steel Construction
 
 
 
708    Prestressed Concrete
 
 
 
709    Timber Structures
 
 
 
710    Waterproofing and Protective Covers
 
 
 
711    Bridge Railings
 
 
 
712    Bridge Rehabilitation - Concrete
 
 
 
713    Bridge Rehabilitation - Steel
 
 
 
714    Temporary Structures and Approaches
 
 
 
715    Cleaning and Coating Existing Structural Steel
 
 
 
716    Shop Cleaning and Coating Structural Steel
 
 
 
717    Downspouts and Drains
 
 
 
718    Drilled Shafts
 
 
 
 
 
 
 
'''Division 8 - Incidental Construction'''
 
 
 
801    Concrete Driveways
 
 
 
802    Concrete Curb, Gutter, and Dividers
 
 
 
803    Concrete Sidewalks, Sidewalk Ramps, and Steps
 
 
 
804    Concrete Barriers, Glare Screens, and Foundations for Light Standards and Sign Supports
 
 
 
805    Hot Mix Asphalt Curb
 
 
 
806    Shared Use Paths
 
 
 
807    Guardrail, Guardrail Terminals, and Miscellaneous Posts
 
 
 
808    Fencing
 
 
 
809    Field Office
 
 
 
810    Permanent Traffic Signs and Supports
 
 
 
811    Permanent Pavement Markings
 
 
 
812    Temporary Traffic Control for Construction Zone Operations
 
 
 
813    Slope Protection
 
 
 
814    Paved Ditches
 
 
 
815    Landscaping
 
 
 
816    Turf Establishment
 
 
 
817    Landscape Mowing
 
 
 
818    Dune Grass Planting
 
 
 
819    Electrical and Lighting
 
 
 
820    Traffic Signals
 
 
 
821    Preservation of Land Monuments, Control Points, and Property Corners
 
 
 
822    Ground or Cut Shoulder Corrugations
 
 
 
823    Water Mains
 
 
 
824    Contractor Staking
 
 
 
 
 
 
 
'''Division 9 - Materials'''
 
 
 
901    Cement and Lime
 
 
 
902    Aggregates
 
 
 
903    Admixtures and Curing Materials for Concrete
 
 
 
904    Asphaltic Materials
 
 
 
905    Steel Reinforcement
 
 
 
906    Structural Steel
 
 
 
907    Fencing Materials
 
 
 
908    Miscellaneous Metal Products
 
 
 
909    Drainage Products
 
 
 
910    Geosynthetics
 
 
 
911    Water
 
 
 
912    Timber and Lumber
 
 
 
913    Masonry Units
 
 
 
914    Joint and Waterproofing Materials
 
 
 
915    Bridge Coating Systems
 
 
 
916    Erosion and Sedimentation Control Materials
 
 
 
917    Turf and Landscaping Materials
 
 
 
918    Electrical and Lighting Materials
 
 
 
919    Permanent Traffic Sign and Support Materials
 
 
 
920    Permanent Pavement Marking Materials
 
 
 
921    Permanent Traffic Signal Materials
 
 
 
922    Temporary Traffic Control Materials
 
 
 
923    Water Main Materials
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
'''
 
 
 
'''Construction Manual Format'''
 
 
 
 
 
 
 
'''Section AAA.01        '''General'''
 
 
 
    Brief Description
 
 
 
 
 
 
 
'''Section AAA.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section AAA.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section AAA.04        '''Post Construction Considerations'''
 
 
 
# Acceptance of Materials
 
# Audit Requirements
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
'''
 
 
 
'''Section 001 – Contract Administration'''
 
 
 
 
 
 
 
'''Section 001.01        '''General'''
 
 
 
    Brief Description
 
 
 
 
 
 
 
'''Section 001.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
 
 
 
 
 
 
Constructability Reviews
 
 
 
A constructability review by both development and delivery staff is essential in ensuring that those items with the greatest potential for impacting project cost or delays are addressed during plan preparation.  To facilitate these reviews and provide accountability, constructability checklists have been developed.  Review procedures have been incorporated into the Scoping Manual and the Road Design Manual.  In addition, Program/Project Management System (P/PMS) network tasks have been developed to track preliminary and final constructability reviews for all road and bridge projects.
 
 
 
 
 
 
 
Preliminary Constructability Review
 
 
 
The Checklist for Constructability Review – Early Project Scoping (Form 1961) must be completed, signed by both development and delivery staff, and included as a part of the Scoping Package turned in during the Call for Projects process (which is prior to beginning preliminary plan development).  Further guidance on Preliminary Constructability Reviews can be found in Chapter 7 and Appendix B-10 of the Scoping Manual and Section 14.30 of the Road Design Manual.
 
 
 
 
 
 
 
Final Constructability Review
 
 
 
The Checklist for Constructability Review – Project Development Phase (Form 1960) must be completed and signed by both development and delivery staff prior to plan completion. The Final Constructability Review will be performed after the Plan Review, in conjunction with the development of final plans and specifications. The P/PMS task for Final Constructability Review (3860) must be included in all networks.  Further guidance on Final Constructability Reviews can be found in Section 14.50 of the Road Design Manual.
 
 
 
 
 
 
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 001.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
 
 
 
 
 
 
Pay Estimates
 
 
 
All pay estimates require an original signature by the delivery engineer no later than 48 hours after generation. This signature may be delegated to the assistant delivery engineer if they have been assigned to the project. However, anytime an assistant delivery engineer signs an estimate, their signature must include “signed for” under the typed name of the official delivery engineer in responsible charge of the project. A signed original must be kept in the project files and/or digitally signed pay estimates in the project’s electronic construction directory within ProjectWise.
 
 
 
 
 
 
 
Prevailing Wage Quality Assurance Review Procedures
 
 
 
There are three levels of quality assurance (QA) reviews within the construction administration process to ensure proper procedures and documentation is used in the oversight of the prevailing wage program. The levels include:
 
 
 
    • Local agency project oversight
 
 
 
    • Transportation Service Center (TSC) project oversight
 
 
 
    • Statewide program oversight
 
 
 
 
 
 
 
The following procedures outline the process for QA reviews for prevailing wage oversight. Conduct QA reviews each construction season at each level to verify appropriate oversight is being accomplished and documented on federal and state prevailing wage projects. It is recommended the QA review take place during the active portion of the construction project. This allows for implementation of corrective action, if necessary, for the remainder of the project and subsequent projects. Document and discuss all deficiencies and issues found during the QA review with the delivery engineer. Do follow-up reviews to assess if the deficiencies and issues have been addressed. MDOT Form 1965, Prevailing Wage Quality Assurance Review Checklist, is available to assist with the QA review, and is available on MDOT’s Web site. You can use the form for each level of review. Upon completion of the QA review, prepare a cover letter summarizing the findings and attach the completed checklist(s) to it; distribute as indicated on the checklist form.
 
 
 
 
 
 
 
Local Agency Level
 
 
 
The TSC delivery engineer is responsible for performing the QA review at the local agency project level. In some regions, the region coordinator for prevailing wage, local agency engineer or local agency technician may assist the delivery engineer. Complete a minimum of one QA review for each local agency that has a construction project during the year. Additional reviews may be necessary if problems are found with the program oversight and documentation by the agency or their consultant. If TSC personnel complete the QA review, forward a copy of the review findings to the region coordinator for information, and for coordination with the TSC of possible follow-up actions. The region coordinator is to forward a copy of the findings to the Construction and Technology (C&T) Division’s prevailing wage compliance specialist.
 
 
 
 
 
 
 
TSC Level
 
 
 
The region coordinator for prevailing wage is responsible for conducting QA reviews for each delivery engineer in each TSC. Review a minimum of 10 percent of each delivery engineer’s projects, with a minimum of one project if the engineer has ten projects or less. The region coordinator is to forward a copy of the findings to the C&T Division’s prevailing wage compliance specialist.
 
 
 
 
 
 
 
Statewide Level
 
 
 
The C&T Division’s prevailing wage compliance specialist is responsible for conducting QA reviews to assess the prevailing wage compliance program for consistency and uniformity across all areas of the state, and to determine training needs for the TSCs and local agencies. This assessment will be completed using the reports provided by the various region coordinators for prevailing wage, and by conducting independent QA reviews across the state. A minimum of one review will be completed in each region. In addition, one consultant administered project will be selected for QA review. Additional reviews may be added based on the findings from the statewide review and/or the information contained in the review findings provided by the region coordinators for prevailing wage.
 
 
 
 
 
 
 
Wage Rate Interviews
 
 
 
Construction engineers are required to conduct annual wage rate interviews on all prevailing wage federal and state funded projects during the construction season.  Contractors are to instruct their employees to cooperate during the interviews and provide the requested information.  Per the prevailing wage oversight procedures, wage rate interviews (WRI) are required to be performed at least once for each contractor and subcontractor when they are on the job, throughout the life of the project, for both state and federally funded projects.  Conduct the interviews each season with a representative sample of the work force for each contractor and subcontractor on the project.  Include each classification and group in the interview process.  Operators of equipment and trucks whose ownership is not clearly identified should be interviewed.  Use Form 1156-T1 (Field Review) for this purpose. This form is available on MDOT’s Web site at:
 
 
 
[http://mdotwas1.mdot.state.mi.us/public/webforms/public/1156-T1.pdf http://mdotwas1.mdot.state.mi.us/public/webforms/public/1156-T1.pdf]
 
 
 
 
 
 
 
These interviews are to assure that all operators, laborers and other skilled trades are paid the base hourly rate and fringe benefits as specified in the project proposal.
 
 
 
 
 
 
 
The engineer will compare the wages and the work classifications documented on Form 1156-T1 with the certified payrolls, IDRs, inspector’s observations, diaries, documentation in the project files, and prevailing wage compliance requirements in the contract.  Form 1156-T1 must be used and properly completed.
 
 
 
 
 
 
 
The construction engineer must resolve any deficiencies or discrepancies (i.e., an employee is not paid the prevailing wages and fringe benefits, as stated in the proposal) utilizing the prevailing wage oversight procedures in BOH IM 2009-07.  If the problem cannot be resolved or additional information is needed, contact the Prevailing Wage Compliance Specialist in the Division of Construction Field Services.  If additional worker information is needed, fill out Form 1156-T2 for documentation.  This form is available on MDOT’s Web site at:
 
 
 
[http://mdotwas1.mdot.state.mi.us/public/webforms/public/1156-T2.pdf http://mdotwas1.mdot.state.mi.us/public/webforms/public/1156-T2.pdf]
 
 
 
 
 
 
 
Oversight of Maintenance Funded Projects (M Jobs)
 
 
 
These projects require the use of FieldManager for record keeping and documentation.  Projects in this category are let under the MDOT Standard Specifications for Construction and the referenced manuals and guides. Oversight and documentation requirements for these projects are the same as any state or federally funded construction project. The same procedures for inspection, pay item documentation, quality control/quality assurance testing, and materials testing must be followed.  The procedures for final inspection/acceptance and submission of the final estimate remain the same as for standard construction projects. In order to process the final estimate, the project records will need to have a final estimate review in accordance with Bureau of Highways Instructional Memorandum 2011-4, Final Estimate Review Procedure, unless the overseeing engineer is certified under the current MDOT Engineer Certification Program.
 
 
 
 
 
 
 
Procedure for Establishing a Modified Original Work Item in FieldManager
 
 
 
Use a modified original pay item only in the event that a work item appearing on the original contract needs to be established in another project or category within the same contract.
 
 
 
 
 
 
 
You must use the following original work item information:
 
 
 
• Item code
 
 
 
• Item description
 
 
 
• Bid unit price
 
 
 
 
 
 
 
The following comment must be added to the contract modification – New Items – Reason field: “The item code, item description and unit price for this modified original have been verified against the original contract item and are correct.”
 
 
 
 
 
 
 
One original work item may be used multiple times to establish multiple modified original items. Modified original items are not extra work or adjustments.
 
 
 
 
 
 
 
Extras and adjustments are excluded from this procedure, as they must be established as extra and adjustments to other projects and categories within the respective contract.
 
 
 
 
 
 
 
Documenting Price Negotiations
 
 
 
Federal regulation states, “The SHA (State Highway Agency) shall perform and adequately document a cost analysis of each negotiated contract change or negotiated extra work order”.  In addition, cost analysis documentation is required for all adjustments to the contract. Base payment for the work on one of the following:
 
 
 
 
 
 
 
1. Negotiated unit prices
 
 
 
When using negotiated unit prices the analysis, justification and documentation should include all applicable information from the following:
 
 
 
::* Unit prices from an adjacent project
 
::* Similar items on the existing contract
 
::* Favorable comparison with weighted average unit prices for recent contracts in the general area
 
::* Cost analysis based on materials labor and equipment to be used for the work
 
::* Quantity of work to be completed; small quantities tend to have higher unit costs
 
::* Other factors such as weather impacts, staging issues, scheduling issues and similar impacts to support the negotiated price is reasonable
 
 
 
 
 
 
 
The following statements are examples of language to include in the justifications for negotiated prices on the contract modification, as applicable:
 
 
 
::* Unit price was taken from an adjacent project, (Job Number)
 
::* Unit price was taken from a similar item on the existing contract
 
::* The unit price is reasonable when compared with weighted average unit prices in the general vicinity for ____ Quarter, (Year)
 
::* Unit price was negotiated based on material, labor and equipment costs; see analysis in file ____
 
::* Backup documentation for unit price analysis can be found in file ____ in the project files
 
::* Other statements as applicable to document the negotiated unit price
 
 
 
Subsection ??109.05.C??? of the 2012 Standard Specifications for Construction contain additional information on price negotiations.
 
 
 
 
 
 
 
2. Negotiated unit prices based upon force account type records
 
 
 
When the negotiated unit price method is not available or the unit price cannot be determined prior to completion of the work, and it is shown that the cost is less than the amount if computed using actual force account records, unit prices can be supported using force account type records.  Documentation for this method is to include labor, equipment and material usage, and cost totals.  Convert to a unit price before adding on administrative costs, profit and other costs.  When using this method to document the cost of extra work, include documentation with the contract modification for extras totaling $25,000.00.  For extra work less than $25,000.00, keep the documentation in the project files and cross reference the file location on the contract modification. 
 
 
 
 
 
 
 
3. Force account procedures
 
 
 
When unit prices cannot be agreed upon in advance and the force account type record method is not available, use force account procedures to determine the cost of the extra work.  Subsection 109.07 of the 2003 Standard Specifications for Construction contains force account procedures. Subsection ??109.05.D.?? of the 2012 Standard Specifications for Construction contain force account procedures. 
 
 
 
 
 
 
 
Documenting Impacts to Contract Time
 
 
 
Staff need to address the impacts on contract time from extra work, quantity changes, and adjustments to the contract.  The contractor completes an analysis of the time impact for extra work and submits it to the engineer as part of the Work Plan under ??109.07.A?? of the 2012 Standard Specifications for Construction. Include extensions of time in the contract modification, when warranted, and if it can be determined at that point.  If the duration of the extension of time cannot be determined when the contract modification is prepared, document whether an extension of time is warranted on the contract modification.  Any extension of time will be determined upon completion of the extra, additional, or adjusted work.  In all cases, use Section 108 of the 2012 Standard Specifications for Construction to determine the extension of time to be granted.
 
 
 
 
 
 
 
Form 1120 Submittal to the FHWA
 
 
 
Construction staff are to submit Form 1120, Final Inspection/Acceptance and Certification Report, to the FHWA in a timely manner.  Per the FHWA requirement, MDOT must submit a Final Inspection/Acceptance and Certification Report if the project is a FHWA oversight project on an NHS route.
 
 
 
 
 
 
 
:# Daily Work Report
 
:# Measurement and Payment
 
 
 
 
 
 
 
'''Section 001.04        '''Post Construction Considerations'''
 
 
 
# Acceptance of Materials
 
 
 
 
 
 
 
As Built Construction Plans Process
 
 
 
As built construction plans are also known as As Constructed Final Plans or Marked Final Plans.  As Built Plans are original awarded project plan sheets that have been updated to show changes, corrections, and comments made during construction.
 
 
 
:# Convert the 11x17 paper plans to a PDF file.
 
:# Drop the PDF file into ProjectWise folder 7 – As Builts by Region/TSC staff
 
:# MDOT Form 0250, As Constructed Final Plans, is now available in ProjectWise to fill out and "send" within ProjectWise.
 
 
 
 
 
 
 
Instructions an be found at the following websites:
 
 
 
[http://www.michigan.gov/documents/mdot/As_Built_Plans_Mark-Up_Standards_295498_7.pdf http://www.michigan.gov/documents/mdot/As_Built_Plans_Mark-Up_Standards_295498_7.pdf]
 
 
 
and
 
 
 
[http://www.michigan.gov/documents/mdot/As_Built_Plans_ProjectWise_Submittal_Procedures_for_Jobs_Let_by_E-Proposal_295500_7.pdf http://www.michigan.gov/documents/mdot/As_Built_Plans_ProjectWise_Submittal_Procedures_for_Jobs_Let_by_E-Proposal_295500_7.pdf]
 
 
 
 
 
 
 
# Audit Requirements
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
 
 
 
 
'''
 
 
 
Section 101    '''Terms, Format, and Definitions'''
 
 
 
 
 
 
 
'''Section 101.01        '''General'''
 
 
 
    Brief Description
 
 
 
 
 
 
 
'''Section 101.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 101.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 101.04        '''Post Construction Considerations'''
 
 
 
A.    Acceptance of Materials
 
 
 
# Audit Requirements
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
 
 
 
 
''''''Section 102    Bid Submission, Award, and Execution of Contract'''
 
 
 
 
 
 
 
'''Section 102.01        '''General'''
 
 
 
    Brief Description
 
 
 
 
 
 
 
'''Section 102.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 102.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 102.04        '''Post Construction Considerations'''
 
 
 
# Acceptance of Materials
 
# Audit Requirements
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
 
 
 
 
''''''Section 103    '''Scope of the Work'''
 
 
 
 
 
 
 
'''Section 103.01        '''General'''
 
 
 
    Brief Description
 
 
 
 
 
 
 
'''Section 103.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 103.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 103.04        '''Post Construction Considerations'''
 
 
 
A.    Acceptance of Materials
 
 
 
# Audit Requirements
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
'''
 
 
 
Section 104    '''Control of the Work'''
 
 
 
 
 
 
 
'''Section 104.01        '''General'''
 
 
 
    Brief Description
 
 
 
 
 
 
 
'''Section 104.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 104.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 104.04        '''Post Construction Considerations'''
 
 
 
# Acceptance of Materials
 
# Audit Requirements
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
'''
 
 
 
Section 105    '''Control of Materials'''
 
 
 
 
 
 
 
'''Section 105.01        '''General'''
 
 
 
    Brief Description
 
 
 
 
 
 
 
'''Section 105.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 105.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
 
 
 
 
 
 
Independent Assurance Testing (IAT)
 
 
 
IAT requirements are outlined in Section 5 of the Materials Quality Assurance Procedures Manual.  The independent assurance testing program is an integral part of the construction materials sampling and testing program that has been mandated for state Department of Transportations by the Federal Highway Administration (FHWA). Per 23 CFR 637, independent assurance program is defined as “activities that are an unbiased and independent evaluation of all the sampling and testing procedures used in the acceptance program”.
 
 
 
 
 
 
 
The following items have been identified as needing special attention:
 
 
 
# It is essential that ALL qualified (refer to Section E.1.3 of Reference for explanation of the term “qualified”) sampling and testing personnel should be a part of the independent assurance (IA) tests. Likewise, equipment involved in acceptance sampling and testing should be used for IA tests. The department is required routinely to verify to both federal and state authorities that these requirements are being met as part of our obligations for federal transportation funding.
 
# All Region IAT Coordinators should ensure that the IAT database is continually updated. Copies of IAT reports are distributed to appropriate areas.
 
# Refer to Section E.5 “IAT Technician” of Reference, which states that “The IAT coordinator will assign qualified personnel to conduct IATs. IATs should be performed by technicians not normally involved in the acceptance testing for the project. At the discretion of the IAT coordinator exceptions may be made due to circumstances such as remoteness of the project or staffing limitations. This should be the exception rather than the rule.”
 
# Region materials personnel should remain vigilant regarding potential conflict of interest issues with consultant personnel on IATs. A consultant firm cannot be participating in IAT oversight of tester/s working for the same firm.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Construction and Technology Indirect Testing Credit
 
 
 
Materials testing and investigation is an essential component to the overall operations of MDOT. There are a number of reasons for materials testing, including verification and qualification of material products of potential vendors, inspections of labs and facilities in promulgation of testing and acceptance of products, and field testing to ensure compliance with standard material specifications. The indirect testing template program detail reads:
 
 
 
 
 
 
 
<nowiki>The [C&T Indirect Testing Credit] funds are used for MDOT personnel or authorized agents for testing performed in materials testing labs throughout the state that are not project specific, such as certification and verification of materials used in MDOT projects, stockpile testing, testing materials of pre-qualified material producers, soil testing, salt testing, and host of other non-project specific testing that is required to maintain the integrity of the materials used in the Trunkline maintenance and construction.</nowiki>
 
 
 
 
 
 
 
The purpose of the Construction & Technology indirect testing credit is to cover performance, material, and acquisition expenditures that relate to either multiple projects, capital program administrative testing, or to perform testing related work for an un-programmed project wherein the activity is not scoping in nature (please refer to the MDOT Project Scoping Manual.
 
 
 
 
 
 
 
Eligibility and Use
 
 
 
Following are examples of types of expenditures that would be appropriate to code to the Construction and Technology indirect testing credit project number. It is noteworthy to state this is not an all-inclusive list, as operational needs are consistently in a state of change and require adaptation.
 
 
 
* Prequalification of interested vendors (salary and travel).
 
* Certification/verification of samples taken at a vendor’s lab/facility (salary and travel).
 
* Certification/verification of samples taken in the field if a project number is not available (salary and travel).
 
* Construction season closing process, including preparation of forms, documentation, manual updates, etc. (salary and travel).
 
* Lab preparation for a future construction season (salary).
 
* Lab supplies and materials required for testing (other operating expense).
 
* Lab equipment required for testing (other operating expense).
 
* Lab supplies and materials required for research (other operating expense).
 
* Calibration related expenses for testing and research equipment (salary, travel, and other operating expenses).
 
* Vehicle and equipment usage (other operating expenses).
 
* Lab qualification activities, such as proficiency testing.
 
* Lab accreditation activities.
 
* Sample collections and transport.
 
 
 
 
 
 
 
Inappropriate Use
 
 
 
It is not appropriate to use the Construction and Technology indirect testing credit to substitute or supplement administrative costs, as a substitute for small increments of activity that occurred on multiple programmed projects, or avoidance of multiple lines of coding.
 
 
 
 
 
 
 
The following are examples of administrative costs (PCA 79900) and direct project costs that are not appropriate to code to the indirect testing credit project number.
 
 
 
 
 
 
 
Salary:
 
 
 
* Leave (annual, sick, other)
 
* Training
 
* Project Scoping eligible activities (please refer to the MDOT Project Scoping Manual).
 
* Project specific activities
 
* Administrative or project activities that are not directly related to materials and testing processes, as previously identified
 
 
 
 
 
 
 
Travel:
 
 
 
* Training
 
* Project Scoping eligible activities (please refer to the MDOT Project Scoping Manual)
 
* Project specific activities
 
* Administrative or project activities that are not directly related to materials and testing processes, as previously identified
 
 
 
 
 
 
 
Other:
 
 
 
* Telephone (Mobile or Desk) and Telegraph
 
* Utilities
 
* Rentals and Leases (Land and Building, Office Equipment)
 
* Consultant Fees and Compensation (Except those directly related to materials and testing.)
 
* Subscriptions
 
* Membership Dues
 
* Postage and UPS
 
* Fuel (Vehicle, Equipment, Facility Heating)
 
* Computer Equipment
 
* Office Supplies
 
* Conferences, Seminars, Training (Internal/External)
 
* Lease Payments
 
 
 
 
 
 
 
Buy America Provision
 
 
 
The Buy America regulations require the use of domestic steel and iron in all federally funded highway construction (including local agency and transportation enhancement projects) where the material is permanently incorporated into the project.  Buy America covers all foreign steel and iron materials and products, regardless of the percentage they comprise in a manufactured product or the form they may take.  This also applies to steel and metal material used as a minor component with other manufactured products, e.g. reinforced concrete pipe.
 
 
 
 
 
 
 
Material Criteria
 
 
 
The engineer should use the Documentation Guide (Minimum Acceptance Requirements for Materials Approvals and Documentation) to assist in item cross-referencing the requirements for the Buy America contract provision.  The guide is available on the Web at:
 
 
 
[http://www.michigan.gov/documents/mdot/MDOT_DocumentationGuide_328761_7.pdf http://www.michigan.gov/documents/mdot/MDOT_DocumentationGuide_328761_7.pdf]
 
 
 
 
 
 
 
Waivers
 
 
 
The contractor may request a waiver on certain materials for contract items of work. The engineer should use the criteria described in Subsection C-104 of the FHWA Michigan Operations Manual, to determine whether the request is valid to warrant further consultation with the FHWA Area Engineer.  The engineer should be aware that waivers are sometimes granted; however, it is on a project case-by-case basis.  The consideration of a cost savings approach for the differential between domestic and foreign products is not typically supported by FHWA as grounds for a waiver.
 
 
 
 
 
 
 
Approval Authority
 
 
 
The engineer will coordinate the waiver review with their chain of custody, including their FHWA area engineer, on whether an item should be subsequently processed through the FHWA Michigan Division.  It is important to note: The engineer does not have the approval authority to waive any of the Buy America requirements delegated to the department for any federal-aid funded contract.  All approvals must be obtained from the FHWA Michigan Division Office.
 
 
 
 
 
 
 
Compliance
 
 
 
The practice of making otherwise federal-aid eligible items non-participating (state or local agency funded) to circumvent the Buy America requirements is unacceptable and should not be approved in federal-aid projects.  The engineer must make every effort to be in full compliance.  The engineer must secure the necessary manufacture certification paperwork from the contractor to meet the contract requirements for the Buy America provisions prior to making payment for the items of work
 
 
 
 
 
 
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 105.04        '''Post Construction Considerations'''
 
 
 
A.    Acceptance of Materials
 
 
 
# Audit Requirements
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
 
 
 
 
''''''Section 106    '''Quality Assurance Acceptance Program'''
 
 
 
 
 
 
 
'''Section 106.01        '''General'''
 
 
 
    Brief Description
 
 
 
 
 
 
 
'''Section 106.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 106.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 106.04        '''Post Construction Considerations'''
 
 
 
# Acceptance of Materials
 
# Audit Requirements
 
# Protection of the Work
 
 
 
 
 
 
 
Section Checklist
 
 
 
 
 
 
 
'''
 
 
 
Section 107    '''Legal Relations and Responsibilities to the Public'''
 
 
 
 
 
 
 
'''Section 107.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 107.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
 
 
 
 
 
 
The Federal Highway Administration (FHWA) requires contractors to prominently display posters in areas available to employees and applicants for employment during the life of the project.  Complete form 1967, Jobsite Poster Inspection Checklist, during the start of the construction project.  This form is an aid to make sure that the contractor is following the proper procedure, as required by specification.  The completed form must be in the project files.
 
 
 
 
 
 
 
Staff should always check MDOT’s Prevailing Wage Web site for the latest revised poster information at:
 
 
 
[http://www.michigan.gov/mdot/0,1607,7-151-9622_11044_11367-222170--,00.html www.michigan.gov/mdot/0,1607,7-151-9622_11044_11367-222170--,00.html]
 
 
 
 
 
 
 
You may also go to [http://www.michigan.gov/mdot www.michigan.gov/mdot].  Click on Maps & Publications, then Manuals, Guides, Advisories, and Memos, and finally Prevailing Wage Compliance.
 
 
 
 
 
 
 
Construction engineers should discuss this requirement at the preconstruction meeting, and make sure the contractors are complying.
 
 
 
 
 
 
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 107.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
 
 
 
 
 
 
Staging and Storage Areas
 
 
 
Contractors are not permitted under any circumstances to use any public recreation area as a staging area, marshalling yard, storage facility, or any other construction support unless approved by the Michigan Department of Transportation (MDOT) and the Federal Highway Administration (FHWA) prior to project letting.  Public recreation areas include: parks, trails, recreation areas, game areas, wildlife and waterfowl refuges, playgrounds, golf courses, ball fields, etc.; which are publicly owned (local, state or federal).  These areas are protected by Section 4(f) of the United States Department of Transportation Act of 1966. Federal law requires there be no use of these areas unless: 1) There is no prudent and feasible alternative; and, 2) All possible measures are taken to minimize harm to the area if there is a use. Compliance with federal law requires these criteria be met and their documentation be approved by the FHWA prior to the project letting.
 
 
 
 
 
 
 
Any and all negotiated agreements between the contractor and the owner of the public recreation area are not to be considered valid by MDOT. MDOT’s Environmental Section manager is to be immediately notified if project staff are informed of any negotiations or receive a copy of an agreement. Furthermore, the contractor is to be immediately notified that these discussions and/or agreements are not valid, will not be honored by MDOT, and non-compliance can result in penalties up to and including termination of the construction contract as well as immediate restoration of the public recreation area at the contractor’s cost.
 
 
 
 
 
 
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 107.04        '''Post Construction Considerations'''
 
 
 
::# Acceptance of Materials
 
::# Audit Requirements
 
::# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
'''
 
 
 
Section 108    '''Prosecution and Progress'''
 
 
 
 
 
 
 
'''Section 108.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 108.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 108.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 108.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
'''
 
 
 
Section 109    '''Measurement and Payment'''
 
 
 
 
 
 
 
'''Section 109.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 109.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 109.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 109.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
'''
 
 
 
Section 150    '''Mobilization'''
 
 
 
 
 
 
 
'''Section 150.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 150.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 150.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 150.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
'''
 
 
 
Section 201    '''Clearing'''
 
 
 
 
 
 
 
'''Section 201.01    '''General'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
This work consists of clearing, selectively thinning, clearing for fence, and applying growth preventive material if required.
 
 
 
 
 
 
 
'''Section 201.02    '''Preconstruction Considerations'''
 
 
 
 
 
 
 
# Preconstruction Meeting
 
 
 
 
 
 
 
All applicable supplemental specifications, Michigan Department of Environmental Quality (MDEQ) permits, and project special provisions should be discussed at the pre-construction meeting.
 
 
 
 
 
 
 
If the project, or any part of the project, is within lands owned by the USDA Forest Service or MDEQ, representatives of those agencies should be contacted to attend the pre-construction meeting and contacted before the actual start of construction operations.  Regulations other than those set forth by MDOT may apply to these areas.
 
 
 
 
 
 
 
# Acceptance of Materials
 
 
 
 
 
 
 
There is no acceptance of materials for clearing.
 
 
 
 
 
 
 
# Preparatory Work and Contractor Work Plans
 
 
 
 
 
 
 
Before beginning any construction operation, refer to subsection 107.15, Compliance with Laws; Environmental Protection, and Section 208, Soil Erosion and Sedimentation Control, of the Standard Specifications for Construction, and any applicable supplemental specifications, MDEQ permits and special provisions.  Further guidance is also provided and depicted in the Soil Erosion and Sedimentation Control Manual.
 
 
 
 
 
 
 
The inspector should become familiar with the various locations and controls for clearing areas established by the staking operations.  The clearing areas can then be checked against plan quantities.  Computations may be available from the project design staff.  Changes from plan quantity should be checked and recorded.  The plans, proposal and right-of-way (ROW) agreements should also be checked for any special provisions or agreements.
 
 
 
 
 
 
 
 
 
 
 
Before the start of work, the Engineer, inspector and Contractor's on-the-job supervisor should field check the project together to agree as to the stake-out controls, interpretation of any special provisions and, most important of all, the actual pay limits.  At this time, the Contractor's planned operations should be discussed, with instructions that the work be controlled to the extent that any plant life so designated will be saved. 
 
 
 
 
 
 
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
All project permits should be reviewed for applicability and conflict with clearing operations.
 
 
 
 
 
 
 
'''Section 201.03        '''Inspection Guidelines during Construction '''
 
 
 
 
 
 
 
# Acceptance of Materials
 
 
 
 
 
 
 
# Equipment and Methods
 
 
 
 
 
 
 
# Construction Operations
 
 
 
 
 
 
 
The Engineer should be informed when possible when any changes from plan quantities or standard specifications have been determined as necessary to complete the work.
 
 
 
 
 
 
 
# Safety and Environmental Considerations
 
 
 
 
 
 
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 201.04        '''Post Construction Considerations'''
 
 
 
 
 
 
 
# Acceptance of Materials
 
 
 
 
 
 
 
# Audit Requirements
 
 
 
 
 
 
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
''''''Section 202    '''Removing Trees, Stumps, and Corduroy'''
 
 
 
 
 
 
 
'''Section 202.01        '''General'''
 
 
 
''Insert weblink to Section 202 in the 2012 Standard Specifications for Construction  ''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 202.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 202.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 202.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 203    '''Removing Drainage Structures, Culverts, and Sewers'''
 
 
 
 
 
 
 
'''Section 203.01        '''General'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 203.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 203.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 203.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 204    '''Removing Miscellaneous Structures, and Materials'''
 
 
 
 
 
 
 
'''Section 204.01        '''General'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 204.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 204.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 204.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 205    '''Roadway Earthwork'''
 
 
 
 
 
 
 
'''Section 205.01        '''General'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 205.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 205.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 205.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 206    '''Excavation and Backfill for Structures'''
 
 
 
 
 
 
 
'''Section 206.01        '''General'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 206.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 206.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 206.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 207    '''Obliterating Roadway'''
 
 
 
 
 
 
 
'''Section 207.01        '''General'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 207.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 207.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 207.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 208    '''Soil Erosion and Sedimentation Control'''
 
 
 
 
 
 
 
'''Section 208.01        '''General'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 208.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 208.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
 
 
 
 
 
 
Filter Bags
 
 
 
Filter bag requirements are specified in subsections 208.03.D.3 and 208.03.C.3 in the 2003 and 2012 Standard Specifications for Construction, respectively. Filter bags should be placed in a well-vegetated, relatively flat upland area, away from any watercourse. For those projects with limited right-of-way where the discharged water may not be adequately clarified before it enters the waterway, one or more gravel filter berms should be installed between the filter bag and the watercourse to provide additional filtration. The contractor must furnish and install filter bags per the specifications and maintain proper filtration prior to discharge to any watercourse.
 
 
 
 
 
 
 
The following items should be considered when utilizing filter bags:
 
 
 
• Filter bags with holes or tears are not acceptable
 
 
 
• Place filter bags in an upland area
 
 
 
• Pumps should be sized based on filter bag capacity
 
 
 
• Use multiple filter bags as necessary to accommodate water volume
 
 
 
• Filter bags should be adequately connected to the discharge hose
 
 
 
• Install gravel filter berms as necessary to provide adequate filtration
 
 
 
• Replace filter bags when full of sediment
 
 
 
 
 
 
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 208.04        '''Post Construction Considerations'''
 
 
 
::# Acceptance of Materials
 
::# Audit Requirements
 
::# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 209    '''Project Cleanup'''
 
 
 
 
 
 
 
'''Section 209.01        '''General'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 209.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 209.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 209.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 301    '''Subbase'''
 
 
 
 
 
 
 
'''Section 301.01        '''General'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 301.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 301.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 301.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 302    '''Aggregate Base Course'''
 
 
 
 
 
 
 
'''Section 302.01        '''General'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 302.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 302.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 302.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 303    '''Open-Graded Drainage Courses'''
 
 
 
 
 
 
 
'''Section 303.01        '''General'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 303.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 303.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 303.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 304    Rubblizing Portland Cement Concrete Pavement'''
 
 
 
 
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 304.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 304.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 304.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 304.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 305    '''HMA Base Crushing and Shaping'''
 
 
 
 
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 305.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 305.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 305.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 305.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 306    '''Aggregate Surface Course'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 306.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 306.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 306.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 306.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 307    '''Aggregate Shoulders and Approaches'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 307.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 307.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 307.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 307.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 308    '''Geotextile for Base'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 308.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 308.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 308.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 308.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 401    '''Pipe Culverts'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 401.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 401.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
 
 
 
 
 
 
Mandrel Testing of Corrugated Polyethylene Pipe (CPE)
 
 
 
During the preconstruction meeting it should be pointed out if CPE pipe is installed, at least 50 percent of each size must be mandrel tested.  The engineer should select those runs of pipe that may have been problematic during installation or in areas subjected to a high volume of construction traffic.  The mandrel testing should be conducted 5 to 10 work days prior to paving.  Prior to testing, the contractor must provide an approved mandrel which is appropriate for testing CPE pipe (mandrel size for PVC is smaller). The mandrel must have at least nine points and be 95 percent of the nominal diameter of the pipe. Per AASHTO M 294 Corrugated Polyethylene Pipe, nominal pipe diameter is defined as 12”, 15”, 18”, etc. Mandrels can be a fixed size or a variable size and are commercially available for most pipe sizes up to 48”. The diameter of the mandrel, whether it is fixed or variable size, must be verified with a proving ring. As a rule of thumb, the length of the mandrel should be equal to or greater than the diameter.
 
 
 
 
 
 
 
The pipe should be cleaned thoroughly before testing. Even the smallest amount of debris can hinder the passage of the mandrel. During the test, the mandrel must be pulled through the pipe by hand. The use of a winch, come-along or other mechanical means is prohibited. If the mandrel can not be pulled through the pipe, the test fails and corrective action is required.  Prior to any corrective action, the contractor may opt to video the pipe to determine the cause of the mandrel not passing through or attempt to clean the pipe again and re-run the mandrel test. If the test still fails, the CPE pipe may be removed and reinstalled providing it has been inspected for damage and approved for re-use. The other option is to remove and replace the damaged pipe with new CPE or other acceptable pipe type. If CPE pipe is used it must be mandrel tested after installation. The use of a pipe “re-rounder” is not an acceptable method for corrective action. Video taping of CPE pipe for acceptance should be conducted only after passing mandrel tests have been achieved.
 
 
 
 
 
 
 
Two forms have been created to document CPE pipe installation and mandrel testing results for sewers and culverts, form numbers 1974 and 1975, respectively. All CPE pipe installed on a project must be recorded on these forms along with mandrel test results. This information must also be documented on the IDR. Upon completion of the form(s), the original version must be placed in the project files (file folder # 304 Drainage Items Testing) and a copy sent to the Grading and Drainage Engineer at C&T for inclusion in the mandated annual report to the legislature.
 
 
 
 
 
 
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 401.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 401.04        '''Post Construction Considerations'''
 
 
 
# Acceptance of Materials
 
# Audit Requirements
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 402    '''Storm Sewers'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 402.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 402.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 402.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 402.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 403    '''Drainage Structures'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 403.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 403.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 403.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
 
 
 
 
 
 
Drainage Structure Covers
 
 
 
Field staff should ensure the covers are visually inspected and accepted before placement and note this inspection on an Inspector’s Daily Report (IDR).  A letter is also required from the contractor stating that the BUY AMERICA provisions have been met for the steel.
 
 
 
 
 
 
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 403.04        '''Post Construction Considerations'''
 
 
 
# Acceptance of Materials
 
# Audit Requirements
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 404    '''Underdrains'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 404.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 404.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 404.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 404.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 405    '''Pump Station Construction'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 405.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 405.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 405.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 405.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 406    '''Precast Three-Sided, Arch, AND Box Culverts'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 406.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 406.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 406.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 406.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 501    '''Plant Produced Hot Mix Asphalt'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 501.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 501.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 501.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 501.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 502    '''HMA Crack Treatment'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 502.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 502.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 502.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
 
 
 
 
 
 
HMA Material Transfer System
 
 
 
The following information discusses an acceptable paver hopper insert, as required by any special provision, or other material transfer device specifications requiring a paver hopper insert.  A paver hopper insert with a minimum capacity of 15 tons must be provided and installed in the paver for the system and must be kept at least 1/3 full at all times.  Current specification does not allow the paver hopper to be modified to meet the tonnage capacity required of the hopper insert.  Hopper inserts are designed in such a manner that they provide mass flow of the HMA to the flow-gates of the paver.  Mass flow of HMA should eliminate any dead zones where material accumulates and cools, and eventually may slough off into the flow-gates of the paver creating chunks in the paving operation.  Simple modifications to a paver hopper insert to increase the capacity do not allow for mass flow; however, simple modifications can create dead zones and allow sloughing of cold material into the flow-gates.
 
 
 
 
 
 
 
The paver hopper insert must be constructed of a material that is stiff enough to maintain its shape when self supported.  Section 502.03 of the 2003 Standard Specifications for Construction state in part the following, “Provide safe and environmentally acceptable equipment that can produce a specification pavement”.  The contractor will supply the engineer with the details of the hopper, including material type, dimensions and capacity prior to being used on the project in accordance with Section 104.01 of the 2003 Standard Specifications for Construction.  The engineer will approve the use of any proposed paver hopper insert prior to use on the project.  These requirements must be enforced to maintain statewide consistency of specifications.
 
 
 
 
 
 
 
Hot Mix Asphalt (HMA) Paving – Seasonal Limitations
 
 
 
Adherence to seasonal limitations must be followed according to the applicable standard specifications and contract documents, unless a contract authorization is issued to allow the contractor to pave.  A contract modification is required when there is a change in contract conditions.  The modification must document and state under what conditions the contractor may pave, and the contractor must meet these conditions each day of paving.  All other specification requirements, including weather, temperature and compaction, remain in place.  These requirements can be found in Section 502.03.J and Table 502-1 of the standard specifications.
 
 
 
 
 
 
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 502.04        '''Post Construction Considerations'''
 
 
 
::# Acceptance of Materials
 
::# Audit Requirements
 
::# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 503    '''Paver Placed Surface Seal'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 503.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 503.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 503.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 503.04        '''Post Construction Considerations'''
 
 
 
# Acceptance of Materials
 
# Audit Requirements
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 504    '''Micro-Surfacing'''
 
 
 
''Insert weblink to Section 201 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 504.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 504.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 504.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 504.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 505    '''Chip Seals'''
 
 
 
''Insert weblink to Section 505 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 505.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 505.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 505.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 505.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 506    '''Slurry Seal'''
 
 
 
''Insert weblink to Section 506 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 506.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 506.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 506.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 506.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 601    Portland Cement Concrete for Pavements'''
 
 
 
''Insert weblink to Section 601 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 601.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 601.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 601.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 601.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 602    '''Concrete Pavement Construction'''
 
 
 
''Insert weblink to Section 602 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 602.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 602.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 602.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
 
 
 
 
 
 
Shipping Tie Wires on Transverse Joint Assemblies
 
 
 
Field investigations conducted by the department in the 1980’s concluded that there were cases where early-age transverse cracking of the pavement had occurred as a result of excessive stresses being built up at the joint assembly when the shipping tie wires were not removed prior to paving. However, a recently conducted national study documented that the additional stresses resulting from not removing the shipping tie wires would be of insufficient magnitude to impact early-age transverse cracking of the pavement. The study further concluded that by cutting the shipping tie wires, there is much more likelihood that the transverse joint assembly will be distorted under the loading imposed by the plastic concrete during paving, which could result in misalignment of the dowel bars and, ultimately, potential lockup of the in-service pavement joints.
 
 
 
 
 
 
 
Contractors are not to cut and remove shipping tie wires after the assemblies are staked onto the grade.  Further, as noted in Standard Plans Series R-40 and this FUSP, the entire joint assembly is to be rejected if the nominal diameter of the shipping tie wires exceed 0.177 inch (approx. 3/16 inch). Since cutting shipping tie wires may result in distortion of the assembly under loading (as described above), transverse joint assemblies that arrive at the project site with oversize shipping tie wires should be rejected. In other words, cutting of oversized shipping tie wires (in lieu of rejection) should not be permitted.
 
 
 
 
 
 
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 602.04        '''Post Construction Considerations'''
 
 
 
# Acceptance of Materials
 
# Audit Requirements
 
# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 603    '''Concrete Pavement Restoration'''
 
 
 
''Insert weblink to Section 603 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 603.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 603.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 603.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 603.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 604    '''Contractor Quality Control for Concrete'''
 
 
 
''Insert weblink to Section 604 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 604.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 604.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 604.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 604.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 605    '''Quality Assurance (Acceptance) for Concrete'''
 
 
 
''Insert weblink to Section 605 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 605.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 605.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 605.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 605.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 701    Portland Cement Concrete for Structures'''
 
 
 
''Insert weblink to Section 701 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 701.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 701.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 701.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 701.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 702    '''Mortar and Grout'''
 
 
 
''Insert weblink to Section 702 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 702.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 702.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 702.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 702.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 703    '''Mortar and Concrete Patching, Repair, and Resurfacing Mixtures'''
 
 
 
''Insert weblink to Section 703 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 703.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 703.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 703.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 703.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 704    '''Steel Sheet Piling and Cofferdams'''
 
 
 
''Insert weblink to Section 704 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 704.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 704.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 704.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
 
 
Construction Operations
 
 
 
 
 
 
 
Dewatering and Filter Bags
 
 
 
It is often necessary to dewater from within a cofferdam to obtain a dry work area. Subsection 704.03.C of the 2003 and 2012 Standard Specifications for Construction describe the requirements for using a geotextile filter bag (filter bag) during dewatering operations. When the work requires pumping of water that may contain silt and sediment, it must be properly treated as described below and per specification. The engineer should inspect the water prior to allowing discharge directly into a watercourse and monitor during the course of pumping to ensure it remains silt and sediment free. If the water is silt and sediment free, it may be discharged directly to a watercourse. If the water is not silt and sediment free it must be pumped into a filter bag.
 
 
 
 
 
 
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 704.04        '''Post Construction Considerations'''
 
 
 
::# Acceptance of Materials
 
::# Audit Requirements
 
::# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 705    '''Foundation Piling'''
 
 
 
''Insert weblink to Section 705 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 705.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 705.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 705.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 705.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 706    '''Structural Concrete Construction'''
 
 
 
''Insert weblink to Section 706 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 706.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 706.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 706.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 706.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 707    '''Structural Steel Construction'''
 
 
 
''Insert weblink to Section 707 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 707.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 707.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
 
 
 
 
 
 
Welding of Pile Splices
 
 
 
Construction staff should review the plans and the proposal for welding pile splices. Field observations have noted that pile splices are not being constructed as shown on the plans or as noted in 707.03.D.8.b, c, and d of the Standard Specifications for Construction. 
 
 
 
 
 
 
 
Welding issues noted in the field have included welders and contractors without welder certifications available at the job site, or welders working out of position from their certification, which conflicts with 707.03.D.8.d. of the standard specifications
 
 
 
There were also issues with welds not meeting the welding requirements per 707.03.D.8.b. This includes welders not removing the slag from their welds, improper grinding, piles that had a poor fit up, and misalignment of the pile sections. There were a considerable number of welds that did not meet American Welding Society (AWS) Code for visual inspection such as arc strikes, cold lap, undercut, and underfill.
 
 
 
 
 
 
 
Some welders were not aware of the weld requirements such as weld lengths, locations, weld size, weld type, and root preparation including back gouging of the welds.
 
 
 
 
 
 
 
There were also issues with improper storage of low hydrogen (E-7018) welding rods according to 707.03.D.8.b of the standard specifications, such as leaving weld rods out for more than two hours, open partially used cans of welding rod on site, hot boxes with the tops left open, welding in the rain, welding on wet steel, welding rods sitting on the ground, hot boxes not plugged in overnight, hot boxes not plugged in during work or generators not running.
 
 
 
 
 
 
 
Include documentation of poor welds and the welder who performed the welds on Form 1122B, Inspector’s Daily Report (IDR). Attach photos as necessary. Most welds can be accepted or rejected based on visual inspection conducted during and after welding. If there is question as to the acceptability of a finished weld, non-destructive testing can be performed to verify.
 
 
 
 
 
 
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 707.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 707.04        '''Post Construction Considerations'''
 
 
 
::# Acceptance of Materials
 
::# Audit Requirements
 
::# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
'''
 
 
 
Section 708    '''Prestressed Concrete'''
 
 
 
''Insert weblink to Section 708 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 708.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 708.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 708.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 708.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 709    '''Timber Structures'''
 
 
 
''Insert weblink to Section 709 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 709.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 709.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 709.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 709.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 710    '''Waterproofing and Protective Covers'''
 
 
 
''Insert weblink to Section 710 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 710.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 710.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 710.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 710.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 711    '''Bridge Railings'''
 
 
 
''Insert weblink to Section 711 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 711.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 711.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 711.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 711.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 712    Bridge Rehabilitation - Concrete'''
 
 
 
''Insert weblink to Section 712 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 712.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 712.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 712.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 712.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 713    Bridge Rehabilitation - Steel'''
 
 
 
''Insert weblink to Section 713 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 713.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 713.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 713.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 713.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 714    '''Temporary Structures and Approaches'''
 
 
 
''Insert weblink to Section 714 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 714.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 714.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 714.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 714.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 715    '''Cleaning and Coating Existing Structural Steel'''
 
 
 
''Insert weblink to Section 715 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 715.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 715.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 715.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 715.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 716    '''Shop Cleaning and Coating Structural Steel'''
 
 
 
''Insert weblink to Section 716 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 716.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 716.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 716.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 716.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 717    '''Downspouts and Drains'''
 
 
 
''Insert weblink to Section 717 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 717.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 717.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 717.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 717.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 718    '''Drilled Shafts'''
 
 
 
''Insert weblink to Section 718 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 718.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 718.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 718.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 718.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 801    '''Concrete Driveways'''
 
 
 
''Insert weblink to Section 801 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 801.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 801.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 801.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 801.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 802    '''Concrete Curb, Gutter, and Dividers'''
 
 
 
''Insert weblink to Section 802 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 802.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 802.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 802.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 802.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 803    '''Concrete Sidewalks, Sidewalk Ramps, and Steps'''
 
 
 
''Insert weblink to Section 803 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 803.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 803.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 803.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 803.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 804    Concrete Barriers, Glare Screens, and Foundations for Light Standards and Sign Supports'''
 
 
 
''Insert weblink to Section 804 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 804.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 804.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 804.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 804.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 805    '''Hot Mix Asphalt Curb'''
 
 
 
''Insert weblink to Section 805 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 805.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 805.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 805.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 805.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 806    '''Shared Use Paths'''
 
 
 
''Insert weblink to Section 806 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 806.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 806.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 806.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 806.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 807    '''Guardrail, Guardrail Terminals, and Miscellaneous Posts '''
 
 
 
''Insert weblink to Section 807 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 807.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 807.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 807.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 807.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 808    '''Fencing'''
 
 
 
''Insert weblink to Section 808 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 808.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 808.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 808.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 808.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 809    '''Field Office'''
 
 
 
''Insert weblink to Section 809 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 809.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 809.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 809.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 809.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 810    '''Permanent Traffic Signs and Supports'''
 
 
 
''Insert weblink to Section 810 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 810.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 810.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 810.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 810.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 811    '''Permanent Pavement Markings'''
 
 
 
''Insert weblink to Section 811 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 811.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 811.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 811.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
 
 
 
 
 
 
Material and Verification Application Guidelines
 
 
 
These guidelines were developed to clarify acceptable procedures for inspecting pavement markings.  The complete guideline can be found at:
 
 
 
 
 
 
 
[http://mdotwas1.mdot.state.mi.us/public/tands/Details_Web/mdot_pm_material_verification_guideline.pdf http://mdotwas1.mdot.state.mi.us/public/tands/Details_Web/mdot_pm_material_verification_guideline.pdf]
 
 
 
 
 
 
 
Material and Application Verification Guidelines explain documentation requirements, how to use Form 1585, contractor yard visits, and plate sampling.  By following this guideline, pavement marking verification practices will be performed consistently statewide.
 
 
 
 
 
 
 
Pavement Marking Materials Reporting Requirements
 
 
 
Subsection 105.01 of the 2003 Standard Specifications for Construction requires the contractor to provide a material source list for all materials incorporated into the project.  This information should be provided at the preconstruction meeting.  The contractor must include the product name as shown on the Qualified Products List (QPL) as well as the product manufacturer.
 
 
 
 
 
 
 
Section F of the Materials Quality Assurance Procedures Manual requires the placement of a label or copy of the label, tag, etc. in the project file.  A notation on an Inspector’s Daily Report (IDR) may be completed in lieu of a label.  Include the product and manufacturer on the IDR, and note that the labeling of the material was checked and verified.
 
 
 
 
 
 
 
Do not accept the material if any of the following apply:
 
 
 
* The product name is not on the product label
 
* It is not listed on the QPL
 
* It is not the same as the product listed on the testing order.
 
 
 
 
 
 
 
The contractor may submit a revised testing order to request usage of a different product.  The engineer must approve the revised testing order before the material may be used on the project.
 
 
 
 
 
 
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
Regular Dry Price Adjustment – End of Season
 
 
 
Field staff should process a uniform price adjustment when regular dry or low temperature waterborne paint is substituted for waterborne paint due to seasonal limitations.
 
 
 
 
 
 
 
Use the Special Provision for Early/Late Season Striping for Permanent Pavement Markings in all projects calling for a combined total of 30,000 ft or more of Pavt Mrkg, Waterborne,_inch, (color).  Pay as noted under d. Measurement and Payment in the special provision, which is available at: [http://mdotwas1.mdot.state.mi.us/public/dessssp/spss_source/03SP811L.pdf http://mdotwas1.mdot.state.mi.us/public/dessssp/spss_source/03SP811L.pdf]
 
 
 
 
 
 
 
The negotiated price adjustments for changing from the following pay items to the new pay items will be published each fall by the Division of Field Operations.  The pay item changes should be as follows:
 
 
 
:* “Pavt Mrkg, Waterborne, _in (white) . . . ft” to “Pavt Mrkg, Regular Dry, _in (white) . . . ft”
 
:* “Pavt Mrkg, Waterborne, _in (yellow) . . . ft” to “Pavt Mrkg, Regular Dry, _in (yellow) . . . ft”
 
 
 
 
 
 
 
 
 
 
 
'''Section 811.04        '''Post Construction Considerations'''
 
 
 
::# Acceptance of Materials
 
::# Audit Requirements
 
::# Protection of the Work
 
 
 
 
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 812    '''Temporary Traffic Control for Construction Zone Operations'''
 
 
 
''Insert weblink to Section 812 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 812.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 812.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 812.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 812.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 813    '''Slope Protection'''
 
 
 
''Insert weblink to Section 813 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 813.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 813.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 813.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 813.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 814    '''Paved Ditches'''
 
 
 
''Insert weblink to Section 814 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 814.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 814.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 814.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 814.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 815    '''Landscaping'''
 
 
 
''Insert weblink to Section 815 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 815.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 815.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 815.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 815.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 816    '''Turf Establishment'''
 
 
 
''Insert weblink to Section 816 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 816.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 816.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 816.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 816.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 817    '''Landscape Mowing'''
 
 
 
''Insert weblink to Section 817 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 817.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 817.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 817.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 817.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 818    '''Dune Grass Planting'''
 
 
 
''Insert weblink to Section 818 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 818.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 818.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 818.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 818.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 819    '''Electrical and Lighting'''
 
 
 
''Insert weblink to Section 819 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 819.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 819.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 819.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 819.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 820    '''Traffic Signals'''
 
 
 
''Insert weblink to Section 820 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 820.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 820.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 820.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
 
 
 
 
 
 
Traffic Signal Installation, Steel Strain Pole Band Clamps
 
 
 
Steel band clamps are used for traffic signal span wire installation on steel strain poles.
 
 
 
 
 
 
 
Clamps must meet the material requirements in Special Detail SIG-010-A “Span Wire T.S. on Steel and Wood Poles”, Detail B, Pole Band Clamps on Steel Pole”, which specifies ASTM A36 steel bands using ASTM A325 galvanized steel bolts.
 
 
 
 
 
 
 
Pole band clamps must be stamped with identification that is traceable back to the manufacturer, which can be used to determine the month and year of clamp manufacture. The stamping method must be a low stress stamping method. The stamp cannot be located near the bolted flange, must be located near the center of the backside clamp from traffic on the outside face, and be visible after galvanizing.
 
 
 
 
 
 
 
The minimum inside bend radius for cold formed members must be at least 1.5 times the material thickness (or 3/8 inches).
 
 
 
 
 
 
 
The contractor must submit a Certificate of Compliance to the engineer stating that the pole band clamp meets the requirements in Special Detail SIG-010-A. The contractor must provide one clamp assembly per lot per size to the engineer for testing as a basis of acceptance prior to use on the project. Material not meeting these requirements will be returned to the contractor at no cost to the department.
 
 
 
 
 
 
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
Payment of Cased Steel Strain Pole Foundations
 
 
 
The quantity (Ft) for “Strain Pole Fdn, Cased” includes the entire depth of concrete foundation for payment.  Construction methods typically install the casing from 3.5 ft below surface to the bottom of the foundation.
 
 
 
 
 
 
 
'''Section 820.04        '''Post Construction Considerations'''
 
 
 
::# Acceptance of Materials
 
::# Audit Requirements
 
::# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 821    '''Preservation of ''''''Land'''''' ''''''Monuments'''''', Control Points, and Property '''
 
 
 
'''Corners '''
 
 
 
''Insert weblink to Section 821 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 821.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 821.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 821.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 821.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 822    '''Ground or Cut Shoulder Corrugations'''
 
 
 
''Insert weblink to Section 822 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 822.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 822.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 822.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 822.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 823    '''Water Mains'''
 
 
 
''Insert weblink to Section 823 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 823.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 823.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 823.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 823.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 824    '''Contractor Staking'''
 
 
 
''Insert weblink to Section 824 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 824.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 824.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 824.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 824.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 901    '''Cement and Lime'''
 
 
 
''Insert weblink to Section 901 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 901.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 901.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 901.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 901.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 902    '''Aggregates'''
 
 
 
''Insert weblink to Section 902 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 902.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 902.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 902.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
 
 
 
 
 
 
Materials Testing Documentation Requirements for Pre-Qualified Aggregates
 
 
 
All aggregates supplied to MDOT projects from pre-qualified sources must have quality assurance (QA) testing conducted by MDOT personnel at frequencies established in the MDOT Materials Quality Assurance Procedures Manual, Section C6, part 7, and in the Materials Acceptance Requirements Table in the Materials Source Guide. Region materials personnel will monitor and conduct quality assurance testing for pre-qualified aggregate sources within their jurisdiction.
 
 
 
 
 
 
 
As part of the materials testing documentation, the delivery/project engineer must verify and document that the QA testing has been completed for the material received from pre-qualified aggregate sources. The delivery/project engineer will need to contact the region’s material supervisor for verification. The materials supervisor will confirm that QA testing has been properly completed and provide the delivery/project engineer with written documentation for the project files to be placed in file folder 306. The documentation can include one or more of the following:
 
 
 
• A copy of the QA test report;
 
 
 
• A written statement verifying completion of the QA testing;
 
 
 
• A telephone record memo verifying completion of the QA testing;
 
 
 
• Other written documentation that QA testing has been completed.
 
 
 
 
 
 
 
Additional documentation required for pre-qualified aggregates include properly completed delivery tickets. The tickets must include the following:
 
 
 
• MDOT aggregate source number;
 
 
 
• Date of shipment;
 
 
 
• Control section and job number;
 
 
 
• Concrete plant number (if applicable);
 
 
 
• Michigan series number and class letter of aggregate;
 
 
 
• Weight or volume shipped;
 
 
 
• Suppliers name, telephone number and location.
 
 
 
In addition, the following statement shall be printed or stamped on each ticket: “I attest that aggregate as delivered from this pre-qualified source meets specification requirements for the listed Michigan series and class for quantity stated. Date________ Signature____________.” This statement must be signed by an authorized company representative. This statement does not signify acceptance by MDOT of the aggregate.
 
 
 
 
 
 
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 902.04        '''Post Construction Considerations'''
 
 
 
::# Acceptance of Materials
 
::# Audit Requirements
 
::# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 903    '''Admixtures and Curing Materials for Concrete'''
 
 
 
''Insert weblink to Section 903 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 903.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 903.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 903.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 903.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 904    '''Asphaltic Materials'''
 
 
 
''Insert weblink to Section 904 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 904.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 904.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 904.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 904.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 905    '''Steel Reinforcement'''
 
 
 
''Insert weblink to Section 905 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 905.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 905.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 905.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 905.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
 
 
 
 
'''
 
 
 
Section 906    '''Structural Steel'''
 
 
 
''Insert weblink to Section 906 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 906.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 906.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 906.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 906.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 907    '''Fencing Materials'''
 
 
 
''Insert weblink to Section 907 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 907.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 907.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 907.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 907.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 908    '''Miscellaneous Metal Products'''
 
 
 
''Insert weblink to Section 908 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 908.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 908.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 908.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
 
 
 
 
 
 
Bridge Mounted Light Standard Anchor Bolt Assemblies
 
 
 
All light standard anchor bolt assemblies, whether supplied and installed by the contractor or by another agency, must meet MDOT specifications when installed on department bridges.  Although bridge mounted light standards may be inspected during scheduled bridge inspections, they do not receive scheduled inspections throughout their service life similar to tower lights or cantilever sign supports.  The foundation anchor bolts are critical to ensuring the structural capacity of the light standard throughout the design life.  The following specifications must be adhered to:
 
 
 
 
 
 
 
MDOT Standard Plan B-103-E contains specifications for anchor bolt diameter, length, embedment and couplers.  Anchor bolts and associated hardware must conform to section 908.15 of the standard specifications, and must be sampled in accordance with section 908.15 of the Materials Acceptance Requirements Table in the Materials Source Guide, at a frequency of one per heat per diameter per project.  Any anchor bolt assemblies containing deviations from the standard plans should be called to the attention of the Bridge Field Services Section in Lansing.  Samples from non-standard anchor bolt assemblies should be accompanied by shop drawings and all samples should be accompanied by test data certifications.
 
 
 
 
 
 
 
Anchor bolt installation and tightening using the “turn of nut” procedure must be conducted in accordance with Section 810.03.N of the standard specifications.
 
 
 
 
 
 
 
Construction staff is to utilize the utilities section of the Bridge Inspection Report form to note any deficiencies of the light standard base or anchor bolts when conducting bridge inspections.
 
 
 
 
 
 
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 908.04        '''Post Construction Considerations'''
 
 
 
::# Acceptance of Materials
 
::# Audit Requirements
 
::# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 909    '''Drainage Products'''
 
 
 
''Insert weblink to Section 909 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 909.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 909.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 909.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 909.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 910    '''Geosynthetics'''
 
 
 
''Insert weblink to Section 910 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 910.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 910.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 910.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 910.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 911    '''Water'''
 
 
 
''Insert weblink to Section 911 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 911.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 911.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 911.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 911.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 912    '''Timber and Lumber'''
 
 
 
''Insert weblink to Section 912 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 912.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 912.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 912.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 912.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 913    '''Masonry Units'''
 
 
 
''Insert weblink to Section 913 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 913.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 913.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 913.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 913.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 914    '''Joint and Waterproofing Materials'''
 
 
 
''Insert weblink to Section 914 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 914.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 914.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 914.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 914.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 915    '''Bridge Coating Systems'''
 
 
 
''Insert weblink to Section 915 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 915.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 915.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 915.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 915.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 916    '''Erosion and Sedimentation Control Materials'''
 
 
 
''Insert weblink to Section 916 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 916.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 916.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 916.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 916.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 917    '''Turf and Landscaping Materials'''
 
 
 
''Insert weblink to Section 917 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 917.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 917.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 917.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 917.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 918    '''Electrical and Lighting Materials'''
 
 
 
''Insert weblink to Section 918 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 918.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 918.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 918.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 918.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 919    '''Permanent Traffic Sign and Support Materials'''
 
 
 
''Insert weblink to Section 919 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 919.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 919.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 919.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 919.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 920    '''Permanent Pavement Marking Materials'''
 
 
 
''Insert weblink to Section 920 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 920.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 920.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 920.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 920.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 921    '''Permanent Traffic Signal Materials'''
 
 
 
''Insert weblink to Section 921 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 921.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 921.02        '''Preconstruction Considerations'''
 
 
 
# Preconstruction Meeting
 
# Acceptance of Materials
 
# Preparatory Work and Contractor Work Plans
 
# Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 921.03        '''Inspection Guidelines during Construction '''
 
 
 
# Acceptance of Materials
 
# Equipment and Methods
 
# Construction Operations
 
# Safety and Environmental Considerations
 
# Documentation
 
## Daily Work Report
 
## Measurement and Payment
 
 
 
 
 
 
 
'''Section 921.04        '''Post Construction Considerations'''
 
 
 
::# Acceptance of Materials
 
::# Audit Requirements
 
::# Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 922    '''Temporary Traffic Control Materials'''
 
 
 
''Insert weblink to Section 922 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 922.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 922.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 922.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 922.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 
 
 
'''
 
 
 
Section 923    '''Water Main Materials'''
 
 
 
''Insert weblink to Section 923 in the 2012 Standard Specifications for Construction  ''
 
 
 
 
 
 
 
'''Section 923.01        '''General'''
 
 
 
Brief Description
 
 
 
 
 
 
 
'''Section 923.02        '''Preconstruction Considerations'''
 
 
 
Preconstruction Meeting
 
 
 
Acceptance of Materials
 
 
 
Preparatory Work and Contractor Work Plans
 
 
 
Safety and Environmental Issues
 
 
 
 
 
 
 
'''Section 923.03        '''Inspection Guidelines during Construction '''
 
 
 
Acceptance of Materials
 
 
 
Equipment and Methods
 
 
 
Construction Operations
 
 
 
Safety and Environmental Considerations
 
 
 
Documentation
 
 
 
Daily Work Report
 
 
 
Measurement and Payment
 
 
 
 
 
 
 
'''Section 923.04        '''Post Construction Considerations'''
 
 
 
Acceptance of Materials
 
 
 
Audit Requirements
 
 
 
Protection of the Work
 
 
 
   
 
 
 
Section Checklist
 

Revision as of 13:48, 8 June 2021

www.michigan.gov/mdot


CONSTRUCTION MANUAL


Logo.jpg


Bureau of Field Services
Construction Field Services Division

Box culvert construction on M-10 in Clare County.

MDOT Mission Statement

Providing the highest quality integrated transportation services for economic benefit and improved quality of life.


Current News

New FieldManager Helpdesk Number

The FieldManager Helpdesk activated its new phone number, 1-844-4MI-MDOT (1-844-464-6368). On the new phone menu, you can reach the FieldManager Helpdesk by selecting option 2 for AASHTOWare and then option 3 for FieldManager. The old number was deactivated on May 1st. The new number is part of the new unified help desk solution, MI MDOT Software Support, used to track and resolve software related issues from customers.

MI MDOT Software Support.png

[top of page]


Recent Major Changes

The table below is a list of Major changes.

Updated Division Section Summary What Changed
6/8/2021
1
107.01
Created Section 107.01 Laws to be Observed View Here
5/11/2021
1 Supplemental
Certified Office Technician Process
Clarification of Prerequisites for Office Tech Certification Compare Here
4/19/2021
1
109.07
Updated Final Estimates information Compare Here
3/15/2021
1
104
Created new Digital Calculations for Payment section under Division 1, Section 104 View Here
2/9/2021
7
712
Added the Site Activation/Deactivation information Compare Here
2/9/2021
7
715
Updated information under Item #6, Site Activation/Deactivation Compare Here
10/19/2020
1 Supplemental
Construction Field Services Indirect Testing Charges
Updated Construction Field Services Indirect Testing codes Compare Here
9/28/2020
7
700
Created new section 700-Closure of Unsafe Structures under Division 7. View Here
9/24/2020
1 Supplemental
FieldManager
Added new item Bi-Annual FieldManager User Account Verification Process View Here
9/21/2020
1 Supplemental
E-Construction General Procedures for Construction Records Retention
Updated Records Retention content and Training Manual Compare Here
8/12/2020
4
Mandrel Testing of Plastic Pipe
A new Mandrel Testing of Plastic Pipe page was created to provide all-inclusive, in-depth descriptions with images. In sections 401 and 402, under Mandrel Testing, there is a link to the new page. View Here
8/4/2020
1 Supplemental
Local Agency Program (LAP)
Updated Local Agency Program (LAP) guidance including an index for program specific project administration instructions labeled as 'LAP Project Considerations' within various sections of the manual Compare Here
8/3/2020
1
109.08
Updated MERS User Guide Compare Here
7/30/2020
1
105
Created new Structural Fabrication Quality Manual page under Section 105 View Here
7/28/2020
8
812
Added new subsection "Overhead Sign Covers" with examples View Here
7/22/2020
1
109.05
Removed Proof of Payment Requirement for Materials in Force Account Compare Here
7/22/2020
1
105
Added 2020 MQAP content View Here
6/30/2020
1 Supplemental
104.07
Updated content for the Project & Worksite Safety subsection Compare Here
6/30/2020
1 Supplemental
FPR Frequently Asked Questions
Created a new FPR Frequently Asked Questions page View Here
6/25/2020
1 Supplemental
FHWA CAP Action Plans
Created a new FHWA CAP Action Plans page to address IDR issues View Here
6/24/2020
1 Supplemental
Final Project Review Report
Created a new Final Project Review Report page View Here
6/9/2020
1 Supplemental
Interim File Review
Created a new Interim File Review page View Here
5/13/2020
1 Supplemental
109.07
Removed the e-File Project Review Procedures from Section 109.07 Compare Here
5/13/2020
1 Supplemental
Letter to File
Created a new Letter to File page View Here
5/13/2020
1 Supplemental
Project Closeout Escalation of Accountability
Created a new Project Closeout Escalation of Accountability page View Here
5/12/2020
1 Supplemental
Final Project Review
Created a new Final Project Review page View Here
4/28/2020
1 Supplemental
Certified Engineer Process
Created new Certified Engineer Process page View Here
4/21/2020
1
109.08
Created new Prompt Payment section with flow chart View Here
2/12/2020
1
102.02
Updated to Boilerplate Progress Clause Template (Revision 2/10/2020) Compare It
01/23/2020
1
104.07
Update to Worker Visibility information and photos Compare It
01/21/2020
1
102
Update to Local Agency Boilerplate Preconstruction Meeting Minutes - January 2020 View Here
01/21/2020
2
208
Update for entire Soil Erosion and Sedimentation Control (NPDES) section Compare It
10/22/2019
1 Supplemental
Construction Field Services Indirect Testing Charges
Update for FY 2020 Indirect Testing Coding Compare It
9/26/2019
1
105
2019 Summary of revisions to the Materials Quality Assurance Procedures Manual Compare It
9/26/2019
8
811
Permanent Pavement Markings Field Inspection and Processing of Progress Payments: Updated new content Compare It
9/18/2019
6
602
Load Transfer Assemblies: Updated new content and included Presentation for Load Transfer Assemblies Inspections Compare It
9/18/2018
8
811
Updated Paint pricing for 2019 View Updated Table Here
8/30/2019
1
102
Update to Trunkline Boilerplate Preconstruction Meeting Minutes - 2019 View Here
8/20/2019
1 Supplemental
FieldManager
New guidance related to the Standard Rounding Convention Compare It
7/31/2019
Main Page
Main Page
July update to the Documentation Guide which includes corrections related to density requirements. It also includes updated language related to the "e-Final Project Review Procedures" View Here

A definition to the types of changes that you might see in the Construction Manual can be found under Content Revision Procedures, Types of Changes.

[top of page]


Recent Minor Changes

The table below is a list of Minor changes.

Updated Division Section Summary What Changed
6/8/2021
1
102.02
Updated Progress Clause Template for LAP Projects (May 2021) document View Here
6/8/2021
1 Supplemental
Current Certified Engineers
Updated certified engineer list to June 2021 View Here
5/24/2021
1 Supplemental
E-Signature
Edited FHWA Electronic Signature information. Compare Here
5/20/2021
1 Supplemental
E-Signature
Added E-Signature Guidance for FHWA staff as non-MDOT users. Compare Here
4/28/2021
1 Supplemental
Local Agency Program
Updated FieldManager contact info (web address and e-mail). Compare Here
3/17/2021
8
811
Updated information on the Permanent Pavement Markings, Material Documentation section. Compare Here
3/3/2021
2
208
Revised to add requirement to notify CFS resource specialist when Form 1568 for Project Staging or Excess Material Location on MDOT ROW is approved Compare Here
2/8/2021
1 Supplemental
Certified Engineer List
Updated the Certified Engineer List as of February 2021. View Here
2/2/2021
1
104.10
Updated the MDOT Claims Procedure with a revised version. Compare Here
1/6/2021
1
102.02
Replace the two current subsections; Determination of Work Days and Critical Path Networks, with single section titled “Contract Time Determination” Compare Here
1/5/2021
1
102.02
Added Controller Cabinet and Detection Equipment to Typical Long-Lead Items Table Compare Here
1/5/2021
4
402
Update related to Illicit Connections Compare Here
11/30/2020
1 Supplemental
Inspector's Daily Report
Updated instructions Compare Here
10/29/2020
E-Construction
Standard Naming Convention for Documents
Updated Naming Convention Table to reflect recent changes. Also included updated PDF and XLSX files (Rev 10-29-20) Compare It
9/24/2020
8
811
Updated Permanent Pavement Markings payment table to include 2020 prices Compare Here
9/24/2020
1
102.02
Added Guardrail-Steel to the Long-Lead item table Compare Here
9/15/2020
Disadvantaged Business Enterprises (DBE)
Disadvantaged Business Enterprises (DBE)
Updated contact information for MDOT's Title VI Coordinator to Orlando Curry 517-241-7462 View Here
8/11/2020
1 Supplemental
Certified Engineer Process
Updated Record Certification List with added Consultants View Here
8/4/2020
1 Supplemental
FieldManager
Added 'LAP Project Considerations' to the section View Here
8/4/2020
1 Supplemental
Plans, Proposal, Input, Review and Evaluation
Added 'LAP Project Considerations' to the section under Design/Construction Package Evaluation View Here
8/4/2020
1 Supplemental
Plans, Proposal, Input, Review and Evaluation
Added 'LAP Project Considerations' to the section under Post-Construction Reviews View Here
8/4/2020
1
102
Added 'LAP Project Considerations' to the section View Here
8/4/2020
1
102.01
Added 'LAP Project Considerations' to the section under Processing of Contractor Performance Evaluations View Here
8/4/2020
1
102.02
Added 'LAP Project Considerations' to the section View Here
8/4/2020
1
103
Added 'LAP Project Considerations' to the section View Here
8/4/2020
1
103.02
Added 'LAP Project Considerations' to the section View Here
8/4/2020
1
103.02
Added 'LAP Project Considerations' to the section View Here
8/4/2020
1
104.10
Added 'LAP Project Considerations' to the section View Here
8/4/2020
1
108.07
Added 'LAP Project Considerations' to the section View Here
8/4/2020
1
108
Added 'LAP Project Considerations' to the section View Here
8/4/2020
1
109.07
Added 'LAP Project Considerations' to the section under Final Inspection, Acceptance, and Final Payment-Acceptance of work View Here
8/4/2020
1
109.07
Added 'LAP Project Considerations' to the section under Final Inspection, Acceptance, and Final Payment-Pay Estimate and Inactive Project Notification View Here
8/4/2020
1
109.07
Added 'LAP Project Considerations' to the section under Final Estimates View Here
8/4/2020
1
109.07
Added 'LAP Project Considerations' to the section View Here
8/4/2020
1
109.07
Added 'LAP Project Considerations' to the section View Here
8/4/2020
1
109.07
Added 'LAP Project Considerations' to the section under Required Signature on Construction Pay Estimates View Here
8/4/2020
1 Supplemental
e-Construction
Added 'LAP Project Considerations' to the section View Here
7/27/2020
1
102.02
Updated MDOT Production Rates link. Old link did not work properly. View Here
7/22/2020
1 Supplemental
FieldManager
Updated Content for Showing Detail Calculations on Inspector’s Daily Report and Added Rounding Convention Example Compare Here
6/30/2020
1 Supplemental
FPR Frequently Asked Questions
Added FPR Report User Guide link to FPR FAQ page Compare Here
6/30/2020
1 Supplemental
Final Project Review
Added FAQs link for Final Project Review to page Compare Here
6/24/2020
1 Supplemental
Project Closeout Escalation of Accountability
Added links to the new Final Project Review Report page Compare Here
6/17/2020
1 Supplemental
Certified Engineer Process
Reformatted the Certified Engineer Renewal Process for clarity Compare Here
6/9/2020
1 Supplemental
Final Project Review
Updated Final Project Review page with Interim File Review link Compare Here
06/01/2020
1 Supplemental
Certification Programs
Updated Engineer Record Certification List View Here
5/1/2020
1 Supplemental
Dispute Review Board (DRB)
Added updated DRB Procedures to include those let on and after 6-5-2020/Removed older links Compare Here
4/30/2020
1 Supplemental
Certified Office Technician Process
Edited page to reflect only Certified Technician Process information Compare Here
4/29/2020
1
109.07
Removed "Review of Prompt Payment Complaints" section as it's now its own page Compare Here
4/27/2020
1
101.04 Inspector Daily Reports
FieldManager
Updated Helpdesk number from 517-322-1556 to 1-844-4MI-MDOT (1-844-464-6368) in these sections along with the Main page Current News area above Compare Here
Compare Here
4/22/2020
1
102.18
Added the newly created Prompt Payment link to Section 102.18 Compare Here
4/15/2020
1
105.01
Changed Density Control Manual to Density Testing and Inspection Manual Compare Here
4/14/2020
1
105.01
Changed Density Control Handbook to Density Control Manual Compare Here
3/30/2020
1
107
Updated Jobsite Poster View Here
3/20/2020
1
105
Deleted information no longer applicable, or is covered in other documents/Renamed section due to changes Compare It
3/18/2020
1
108.01
Updated links to the new 1302-Fed form. Compare Here
2/21/2020
1
103.02
General Contract Modification Information Format Revision Compare It
2/13/2020
E-Construction
Standard Naming Convention for Documents
Updated Naming Convention Table to reflect recent changes. Also included updated PDF and XLSX files (Rev 2-13-20) Compare It
02/13/2020
1 Supplemental
Certified Engineer Process
Updated Engineer Record Certification List View Here
01/22/2020
Prevailing Wage Oversight Procedures
Jobsite Posting
Updated contact information on the Title VI Poster and Coordinator site information Compare It
11/12/2019
2
208
Soil Erosion and Sedimentation Control Notifications: Updated Notice of Coverage (NOC) and Notice of Termination (NOT) charts Compare It
10/29/2019
1 Supplemental
Indirect Testing Charges - Eligibility and Use
Updated first bullet information for clarity and to include examples Compare It
10/28/2019
1 Supplemental
Certified Engineer Process
Updated Engineer Record Certification List View Here
10/3/2019
8
811
Removal of references to outdated paint marking turn arrows Compare It
8/22/2019
1
107.09
Update related to the process for archeological findings Compare It
7/11/2019
2
208
Added 2 flowcharts for Notice of Coverage (NOC) and Notice of Termination (NOT) in section 208 between “Notification” and “Training”. Also updated language to reflect recent name change of the "Michigan Department of Environmental Quality (MDEQ)" to the "Michigan Department of Environment, Great Lakes, and Energy (EGLE)" Compare It

[top of page]


Preamble

This manual provides guidance to administrative, engineering, and technical staff. Engineering practice requires that professionals use a combination of technical skills and judgment in decision making. Engineering judgment is necessary to allow decisions to account for unique site-specific conditions and considerations to provide high quality products, within budget, and to protect the public health, safety, and welfare. This manual provides the general operational guidelines; however, it is understood that adaptation, adjustments, and deviations are sometimes necessary. Innovation is a key foundational element to advance the state of engineering practice and develop more effective and efficient engineering solutions and materials. As such, it is essential that our engineering manuals provide a vehicle to promote, pilot, or implement technologies or practices that provide efficiencies and quality products, while maintaining the safety, health, and welfare of the public. It is expected when making significant or impactful deviations from the technical information from these guidance materials, that reasonable consultations with experts, technical committees, and/or policy setting bodies occur prior to actions within the timeframes allowed. It is also expected that these consultations will eliminate any potential conflicts of interest, perceived or otherwise. MDOT Leadership is committed to a culture of innovation to optimize engineering solutions. The National Society of Professional Engineers Code of Ethics for Engineering is founded on six fundamental canons. Those canons are provided below. Engineers, in the fulfillment of their professional duties, shall:

  1. Hold paramount the safety, health, and welfare of the public.
  2. Perform Services only in areas of their competence.
  3. Issue public statement only in an objective and truthful manner.
  4. Act for each employer or client as faithful agents or trustees.
  5. Avoid deceptive acts.
  6. Conduct themselves honorably, reasonably, ethically and lawfully so as to enhance the honor, reputation, and usefulness of the profession.


This manual has been revised throughout to incorporate changes brought about by the release of the 2012 Standard Specifications for Construction and by progress in equipment, construction practices, and materials. The format has been established to follow the standard specification outline with divisions and sections set up to facilitate revision and addition of new information as needed.