Recent changes options Below are the changes since 23 April 2021, 12:46 (up to 250 shown). (Reset date selection)
Show last 50 | 100 | 250 | 500 changes in last 1 | 3 | 7 | 14 | 30 days
Hide registered users | Hide anonymous users | Show my edits | Hide bots | Show minor edits
Show new changes starting from 17:38, 8 May 2021
   
List of abbreviations:
N
This edit created a new page (also see list of new pages)
m
This is a minor edit
b
This edit was performed by a bot
(±123)
The page size changed by this number of bytes

6 May 2021

     17:14  702 - Mortar and Grout diffhist +50 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     17:13  701-Portland Cement Concrete for Structures diffhist +49 SchaeferS talk contribs →‎Opening to Traffic
     17:11  701 - Portland Cement Concrete for Structures diffhist +50 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     17:11  700 - Closure of Unsafe Structures diffhist +50 SchaeferS talk contribs →‎Responsibility to Close Unsafe Structures
     16:31  506 - Slurry Seal diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:31  505 - Chip Seals diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:30  504 - Micro-Surfacing diffhist +49 SchaeferS talk contribs →‎Delayed Acceptance
     16:30  503 - Paver Placed Surface Seal diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:09  502 - HMA Crack Treatment diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:08  501 - Plant Produced Hot Mix Asphalt diffhist +51 SchaeferS talk contribs →‎Utilizing Reclaimed Asphalt Pavement (RAP) Millings from the Same Project When Using a Portable Hot Mix Asphalt (HMA) Plant
     16:06  Mandrel Testing of Plastic Pipe diffhist +37 SchaeferS talk contribs →‎Nine Point Mandrel with Proving Rings
     16:05  406 - Precast Three-Sided, Arch, and Box Culverts diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:05  405 - Pump Station Construction diffhist +48 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:05  404 - Underdrain diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:04  403 - Drainage Structures diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:04  402 - Storm Sewers diffhist +49 SchaeferS talk contribs →‎Video Inspection of Installed Storm Sewers
     16:04  401 - Culverts diffhist +25 SchaeferS talk contribs →‎Video Inspection
     16:03  308 - Geotextiles for Base diffhist +81 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:02  307 - Aggregate Shoulders and Approaches diffhist +49 SchaeferS talk contribs →‎Tare Weights
     16:02  306 - Aggregate Surface Course diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:02  305 - HMA Base Crushing and Shaping diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:01  304 - Rubbilizing Existing PCC Pavement diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:01  303 - Open Graded Drainage Course diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     16:01  302 - Aggregate Base Courses diffhist +49 SchaeferS talk contribs →‎Payment by Weight
     16:00  301 - Subbase diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     15:58  208 - Soil Erosion and Sedimentation Control (NPDES)‎‎ 2 changes history +49 [SchaeferS‎ (2×)]
     
15:58 (cur | prev) 0 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     
15:57 (cur | prev) +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     15:57  209 - Project Cleanup diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     15:57  207 - Obliterating Roadway diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     15:57  206 - Excavation and Backfill for Structures diffhist +49 SchaeferS talk contribs →‎Excavation for Structures
     15:56  205 - Roadway Earthwork diffhist +49 SchaeferS talk contribs →‎Computer Processing of Earthwork
     15:56  204 - Removing Miscellaneous Structures and Materials diffhist +49 SchaeferS talk contribs →‎Site Clearing (Form RE-18)
     15:55  202 - Removing Trees, Stumps, and Corduroy‎‎ 2 changes history +49 [SchaeferS‎ (2×)]
     
15:55 (cur | prev) 0 SchaeferS talk contribs →‎Instructions for Removing Corduroy
     
15:55 (cur | prev) +49 SchaeferS talk contribs →‎Instructions for Removing Corduroy
     15:55  203 - Removing Drainage Structures, Culverts, and Sewers diffhist +49 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     15:54  201 - Clearing diffhist +49 SchaeferS talk contribs →‎Daily Reports On Clearing
     15:51  Project Closeout Escalation of Accountability diffhist +24 SchaeferS talk contribs →‎Potential Closeout Problems with Remedies
     15:49  Local Agency Program (LAP) diffhist +25 SchaeferS talk contribs →‎Other Local Agency Partnerships
     15:48  Letter to File diffhist +24 SchaeferS talk contribs →‎Major Deficiencies
     15:47  Interim File Review diffhist +24 SchaeferS talk contribs →‎LAP Project Considerations
     15:46  FPR Frequently Asked Questions diffhist +2 SchaeferS talk contribs →‎What is the difference between a major and minor deficiency?
     15:45  Final Project Review Report diffhist +13 SchaeferS talk contribs
     15:44  Final Project Review diffhist +13 SchaeferS talk contribs →‎FAQs for Final Project Review
     15:43  FHWA CAP Action Plans diffhist +24 SchaeferS talk contribs →‎2019 CAP Targeted Action Plan
     15:42  E-Signature diffhist +25 SchaeferS talk contribs →‎Guidance for Non-MDOT Users
     15:35  E-Construction diffhist -97 SchaeferS talk contribs →‎Resources
     15:34  Dispute Review Board (DRB) diffhist +23 SchaeferS talk contribs →‎Dispute Review Board Process Flowchart
     15:30  Construction Field Services Indirect Testing Charges diffhist +23 SchaeferS talk contribs →‎Inappropriate Use
     15:29  Certified Office Technician Process diffhist +23 SchaeferS talk contribs →‎Office Technician Certification Requirements
     15:28  Certified Engineer Process diffhist +24 SchaeferS talk contribs →‎LAP Project Considerations
     15:09  150 - Mobilization diffhist +25 SchaeferS talk contribs →‎MEASUREMENT AND PAYMENT
     15:06  109.03 Payments for Increased or Decreased Quantities diffhist +32 SchaeferS talk contribs
     15:06  109.02 Scope of Payment diffhist +32 SchaeferS talk contribs
     15:05  109.01 Measurement of Quantities diffhist +32 SchaeferS talk contribs
     14:53  106 - Quality Assurance Acceptance Program diffhist +24 SchaeferS talk contribs →‎QUALITY ASSURANCE ACCEPTANCE PROGRAM
     14:46  Disadvantaged Business Enterprises (DBE) diffhist +25 SchaeferS talk contribs →‎Questions
     14:42  101 - Terms, Format, and Conditions diffhist +24 SchaeferS talk contribs →‎DEFINITIONS

3 May 2021

     10:17  Division 7 Supplemental Information diffhist +19 Clarkj25 talk contribs →‎MDOT Bridge Deck Overlay Construction Inspection Checklist (attached)

28 April 2021

     13:13  MDOT Construction Manual Content Revision Procedures diffhist -433 Clarkj25 talk contribs
     13:01 Move log Clarkj25 talk contribs moved page Content Revision Procedures to MDOT Construction Manual Content Revision Procedures
     11:26  Local Agency Program (LAP) diffhist +54 SchaeferS talk contribs →‎Local Agency Program Assistance/Resources: added new FieldManager link and email address
     11:16  Main Page diffhist 0 SchaeferS talk contribs →‎Recent Major Changes: Updated the compare here review for the Final Estimates updates
     11:06  109.07 Final Inspection, Acceptance, and Final Payment‎‎ 2 changes history +190 [SchaeferS‎ (2×)]
     
11:06 (cur | prev) +25 SchaeferS talk contribs →‎LAP Project Considerations: Updated info in last paragraph
     
11:04 (cur | prev) +165 SchaeferS talk contribs →‎Final Estimates: Updated Processing Final Estimates Item #2