1.4 Letting Plan Review ProjectWise Process
By Chapter
1.4.1 Letting - Package Submittal
State: OEC - Pending Submittal
Pre-Construction Task:
Step | Action |
---|---|
1 | Design Team - Create PDF of:
|
2 | Design Team - Add PDFs created in step 1 into the '6 - Letting Plans and Proposal' folder. |
3 | Design Team - Are all Final Plan related files in the system? Yes, then:
|
4 | Design Team - Click on OK in the '˜Change Document to State' window |
5 | Design Team - Send the system generated email.
NOTE: Leave MDOT-Eproposal address in email. Also, you only need to send one email (close out of the other ones). |
REMINDER: Update RID Checklist in the ˜Supporting Documents/ RID Preparation folder and upload the RID files in the ˜6 - Letting Plans and Proposal/RID folder for review.
Highlight all files in the ˜6 - Letting Plans and Proposal/RID folder, then change state to next to submit to RID Review staff.
State: OEC-PM Review in Progress
Pre-Construction Task:
Step | Action |
---|---|
1 | Project Manager - Upon receipt of email, please review proposal and plan packages located in the '˜6-Letting Plans and Proposal' folder and the Supporting Documents located in the '˜Supporting Documents' folder. If ready, proceed to the next step of initiating the CA Sign Off.
|
2 | Project Manager -
|
3 | Project Manager - Once all supporting documents have been changed to the 'Complete Supporting Documents' State, then:
|
4 | Project Manager - Click on OK in the '˜Change Document to State' window |
5 | Project Manager - Add additional CA Form signers email addresses in the 'To' field and send the system generated email.
NOTE: Leave MDOT-Eproposal address in email. Also, you only need to send one email (close out of the other ones). |
State: OEC - CA Sign Off
Pre-Construction Task:
Step | Action |
---|---|
1 | CA Form Signers - Upon receipt of email, review Proposal and Plan packages located in the '˜6- Letting Plans and Proposal' folder and the Supporting Documents located in the '˜Supporting Documents' folder.
|
2 | CA Form Signers - If approved for Final Plan review, then:
|
3 | Project Manager - Once the CA Form is complete:
|
4 | Project Manager - Once the supporting documents have been changed to the '˜Initiate Final Supporting Documents' State, then:
|
5 | Project Manager - Click on OK in the '˜Change Document to State' window |
6 | Project Manager - Send the system generated email.
NOTE: Leave email address in email. Also, you only need to send one email (close out of the other ones). |
State: e-Prop - Initiate Final Project Review
Pre-Construction Task:
Step | Action |
---|---|
1 | Specifiaction & Estimates Engineer -
|
2 | Specifiaction & Estimates Engineer - Click on OK in the 'Change Document to State' window |
3 | Specifiaction & Estimates Engineer -
NOTE: Leave MDOT-Eproposal address in email. Also, you only need to send one email (close out of the other ones). |
State: e-Prop - Workflow Assign
Pre-Construction Task:
Step | Action |
---|---|
1 | Specification & Estimates Engineer -
|
1.4.2 Letting - Review
-Reserved-
State: QA Tech - Pending
PPMS Task: -Reserved-
State: QA Tech - Complete
PPMS Task: -Reserved-
State: QA Tech - Assign to Reviewer
PPMS Task: -Reserved-
State: QA SE - Pending
PPMS Task: -Reserved-
State: QA SE - Complete
PPMS Task: -Reserved-
State: QA SE - Assign to Estimator
PPMS Task: -Reserved-
State: QA Est - Pending
PPMS Task: -Reserved-
State: QA Est - Complete
PPMS Task: -Reserved-
State: QA Final - Pending
PPMS Task: -Reserved-
State: QA Final - Complete
PPMS Task: -Reserved-
State: QA Final - Ready for Finance
PPMS Task: -Reserved-
State: Finance PQ - Pending
PPMS Task: -Reserved-
State: Finance BLU - Pending
PPMS Task: -Reserved-
State: Final
PPMS Task: -Reserved-
1.4.3 Letting - RID Review
State: E-Proposal RID Pending
PPMS Task:
Step | Action |
---|---|
1 | Design Team - Create RID Submittal during the State: E-Proposal Complete:
|
2 | Project Manager - Make sure the RID files are ready for review prior to completing the State: E-Prop Initiate Final Project Review. |
3 | Project Manager - Include MDOT RID Support on the email generated during the State: E-Prop Initiate Final Project Review. |
State: E-Proposal RID Complete
PPMS Task:
Step | Action |
---|---|
1 | MDOT-RIDSupport Reviewers - Perform review of the RID files and document comments in the RID Review Checklist.xlsm. Reference saved views in the RID Comments column.
NOTE: During this state the '˜RID' folder will remain accessible for easy corrections of RID files during the MDOT-RIDSupport review. |
2 | MDOT-RIDSupport Reviewers - Prior to the State: QA Final - Ready for Finance:
|
3 | MDOT-RIDSupport Reviewers - Click on OK in the '˜Change Document to State' window. |
State: E-Proposal RID Publish
PPMS Task:
Step | Action |
---|---|
1 | Finance - During the Final State:
Note: The RID must be in the State: E-Proposal Complete before they can be changed to the State: E-Proposal RID Publish. If the RID is not in the State: E-Proposal Complete at the time of Publishing please contact MDOT RID Support |
2 | If RID files are added after advertisement:
|