Difference between revisions of "1.1 Base Plan Review ProjectWise Process"
Line 67: | Line 67: | ||
|- | |- | ||
| style="text-align:center;" | 1 | | style="text-align:center;" | 1 | ||
− | | ''Project Manager'' – | + | | ''Project Manager'' – Upon receipt of email, please review plans and supporting documents |
− | + | |- | |
+ | | style="text-align:center;" | 2 | ||
+ | | ''Project Manager'' – Copy the ‘JN_0303_DPS.pdf’ file, located in '-Supporting Documents' folder in the 'Milestone Forms' Document Set into the 'Supporting Documents' folder. | ||
''NOTE: This is a “living†form. The Project Manager will update this form at each milestone.'' | ''NOTE: This is a “living†form. The Project Manager will update this form at each milestone.'' | ||
|- | |- | ||
− | |||
− | |||
|- | |- | ||
| style="text-align:center;" | 3 | | style="text-align:center;" | 3 | ||
− | | ''Project Manager'' – Add file created in step | + | | ''Project Manager'' – Print 'JN_0303_DPS.pdf' to PDF and apply the naming convention of 'JN_0303_DPS_Base.pdf' |
+ | |- | ||
+ | | style="text-align:center;" | 4 | ||
+ | | ''Project Manager'' – Add file created in step 3 into the ‘Design Submittal Form’ Folder. | ||
[[File:Base Design Submittal Folder.png|650px|frameless|right|Base Design Submittal Form Folder]] | [[File:Base Design Submittal Folder.png|650px|frameless|right|Base Design Submittal Form Folder]] | ||
Line 82: | Line 85: | ||
''NOTE: This file will be used to trigger the rest of the Base Plan Review workflow process.'' | ''NOTE: This file will be used to trigger the rest of the Base Plan Review workflow process.'' | ||
|- | |- | ||
− | | style="text-align:center;" | | + | | style="text-align:center;" | 5 |
| ''Project Manager'' – Ready for Base Plans to be reviewed? Yes, then: | | ''Project Manager'' – Ready for Base Plans to be reviewed? Yes, then: | ||
+ | * Create a Bluebeam Studio Session. For information on how to use Bluebeam Software, see [[Collaborative Milestone Review Process]] | ||
* Single Left click on the ‘0303_DPS_Base.pdf’ located in the ‘Design Submittal Form’ folder. | * Single Left click on the ‘0303_DPS_Base.pdf’ located in the ‘Design Submittal Form’ folder. | ||
* Then right click and select Change State. | * Then right click and select Change State. | ||
* Select Next. | * Select Next. | ||
|- | |- | ||
− | | style="text-align:center;" | | + | | style="text-align:center;" | 6 |
| ''Project Manager'' – Click on OK in the ‘Change Document to State’ window | | ''Project Manager'' – Click on OK in the ‘Change Document to State’ window | ||
|- | |- | ||
− | | style="text-align:center;" | | + | | style="text-align:center;" | 7 |
| ''Project Manager'' – Please do the following to the system generated email: | | ''Project Manager'' – Please do the following to the system generated email: | ||
* File > Save (this will save the email into your Drafts Outlook cabinet) | * File > Save (this will save the email into your Drafts Outlook cabinet) | ||
Line 97: | Line 101: | ||
* Go into your Outlook Drafts cabinet | * Go into your Outlook Drafts cabinet | ||
* Highlight ‘Base Plans ready for review’ email | * Highlight ‘Base Plans ready for review’ email | ||
− | * | + | * On the 'Home' tab click on the 'Meeting' icon |
+ | * The ProjectWise generated email will open into a Meeting Appointment | ||
+ | ** Update Date and Time for appointment | ||
** Add internal and external Base Plan meeting attendees | ** Add internal and external Base Plan meeting attendees | ||
− | *** Use the | + | *** Use the 'Review meeting contacts list.xlsx' located in the ‘-Supporting Documents’ Reference Set. This list includes all Region and Central Office reviewers. |
− | **:''NOTE: Have ROW? Remember to invite ROW staff.'' | + | **:'''''NOTE: Have ROW? Remember to invite ROW staff.''''' |
**Review body of email and update all meeting specific information (see highlighted text below) | **Review body of email and update all meeting specific information (see highlighted text below) | ||
Line 110: | Line 116: | ||
− | : | + | :The Base Plan Review Meeting '''ON:''' Route '''CS:''' # '''JNs:''' #, Description |
− | |||
− | |||
− | |||
− | |||
− | : | + | :Work entails: <span style="background-color: #FFFF00">''ENTER INFORMATION HERE''</span> |
− | : | + | :The Base Plan Meeting on this project has been scheduled for <span style="background-color: #FFFF00">''ENTER DATE HER''E</span>. <span style="background-color: #FFFF00">''ENTER PROJECT MANAGER''</span> will oversee this meeting and meet interested personnel at MDOT’s <span style="background-color: #FFFF00">''ENTER LOCATION AND STREET ADDRESS HERE''</span> at <span style="background-color: #FFFF00">''ENTER TIME HERE''</span>. |
− | : | + | :'''This project will be using a Bluebeam Studio Session for reviewing the documents. Instructional videos on how to install Bluebeam Revu, create an account, install MDOT specific toolsets, and additional resources for utilizing the software can be found at the following link:''' [[Collaborative Milestone Review Process]] |
− | : | + | :<span style="background-color: #FFFF00">''PASTE BLUEBEAM STUDIO SESSION HERE''</span> |
− | : | + | :All comments need to be completed by 4:00 pm, <span style="background-color: #FFFF00">''ENTER DATE HERE''</span> for the ''PROJECT MANAGER'' <span style="background-color: #FFFF00">''ENTER PROJECT MANAGER'' </span> to review comments. |
− | : | + | :Electronic plan and proposal documents can be viewed in MDOT’s ProjectWise Base Plan folder at the following location: |
− | |||
− | :Project Manager: | + | :''Project Manager:'' <span style="background-color: #FFFF00">''ENTER NAME HERE AND PHONE NUMBER''</span> |
− | :If you have further comments or questions that require discussion, please contact me. | + | :::::''If you have further comments or questions that require discussion, please contact me.'' |
''NOTE: Please allow 20 work days for Base Plan Review.'' | ''NOTE: Please allow 20 work days for Base Plan Review.'' |
Revision as of 15:47, 13 November 2018
By Chapter
Folder:
1.1.1 Base Plan - Package Submittal
State: Base Plan - Pending Submittal
PPMS Task: 3360 - Prepare Base Plans
Step | Action |
---|---|
1 | Design Team – Create PDF of:
NOTE: ROW must be included in Base Plan set. |
2 | Design Team – Add PDFs created in step 1 into the ‘2 – Base Plans’ folder. |
3 | Design Team – Are all Base Plan related files in the system? Yes, then:
|
4 | Design Team – Click on OK in the ‘Change Document to State’ window |
5 | Design Team – Add the Project Manger’s email address into the system generated email
|
State: Base Plan - Review
PPMS Task: 3360 - Prepare Base Plans
Step | Action |
---|---|
1 | Project Manager – Upon receipt of email; review proposal, plans and supporting document packages. If ready, proceed to the next step of initiating the Plan Review. |
1.1.2 Base Plan - Review
Folder:
State: Base Plan Review - Pending
PPMS Task: 3360 - Prepare Base Plans
Step | Action |
---|---|
1 | Project Manager – Upon receipt of email, please review plans and supporting documents |
2 | Project Manager – Copy the ‘JN_0303_DPS.pdf’ file, located in '-Supporting Documents' folder in the 'Milestone Forms' Document Set into the 'Supporting Documents' folder.
NOTE: This is a “living†form. The Project Manager will update this form at each milestone. |
3 | Project Manager – Print 'JN_0303_DPS.pdf' to PDF and apply the naming convention of 'JN_0303_DPS_Base.pdf' |
4 | Project Manager – Add file created in step 3 into the ‘Design Submittal Form’ Folder.
NOTE: This file will be used to trigger the rest of the Base Plan Review workflow process. |
5 | Project Manager – Ready for Base Plans to be reviewed? Yes, then:
|
6 | Project Manager – Click on OK in the ‘Change Document to State’ window |
7 | Project Manager – Please do the following to the system generated email:
NOTE: Please allow 20 work days for Base Plan Review. |
State: Base Plan Review - Ready for Review
PPMS Task: 3380 - Review Base Plans (20 work days for review)
Step | Action |
---|---|
1 | Base Plan Reviewers – Print dot matrix set and comment using the Digital Pen process or Adobe commenting.
|
2 | Base Plan Reviewers – Upload Digital Pen comments into ProjectWise.
|
3 | Project Manager – After the 20 work day review period,
|
4 | Project Manager – Click on OK in the ‘Change Document to State’ window.
NOTE: No email will be generated. |
State: Base Plan Review - PM Review in Progress
PPMS Task: 3395 - Project Manager Base Plan Review (5 work days for review)
Step | Action |
---|---|
1 | Project Manager – Copy ALL digital pen comment files to the ‘Pre-Construction > Record Plan Set Review Comments’ folder prior to reviewing the files. |
2 | Project Manager – Review and Compile comments on ALL digital pen comment files located under the JN’s ‘2 - Base Plan’ folder. |
3 | Project Manager – Once all comments have reviewed and compiled:
|
4 | Project Manager – Click on OK in the ‘Change Document to State’ window. |
5 | Project Manager - Add all Reviewers’ email addresses into the system generated email. |
State: Base Plan Review - Design Team Response
PPMS Task: Design Team (5 work days for review)
Step | Action |
---|---|
1 | Design Team/Reviewers – Review compiled comments. Reminder: contact Project Manager with any comments prior to the Base Plan Meeting. |
2 | Project Manager – Once the meeting has ocucred:
|
3 | Project Manager – Click on OK in the ‘Change Document to State’ window. |
4 | Base Plan Review workflow process is now complete. |