Difference between revisions of "1.4 Letting Plan Review ProjectWise Process"
Campbellw2 (talk | contribs) |
|||
Line 128: | Line 128: | ||
| ''Design Team'' – Create RID Submittal during the [[1.4 Letting Plan Review ProjectWise Process#State:_E-Proposal_Complete | State: E-Proposal Complete]]: | | ''Design Team'' – Create RID Submittal during the [[1.4 Letting Plan Review ProjectWise Process#State:_E-Proposal_Complete | State: E-Proposal Complete]]: | ||
* Place RID files in the ‘RID’ folder per [[Chapter_5_-_RID_Process | Chapter 5 - RID Process]] | * Place RID files in the ‘RID’ folder per [[Chapter_5_-_RID_Process | Chapter 5 - RID Process]] | ||
− | * Respond to comments in the [http://mdotjboss.state.mi.us/SpecProv/getDocumentById.htm?docGuid=71536ffa-6a51-4e45-b38b-da310526378b&fileName= RID Review Checklist.xlsm] located in the ‘- Supporting Documents’ folder. | + | * Respond to comments in the [http://mdotjboss.state.mi.us/SpecProv/getDocumentById.htm?docGuid=71536ffa-6a51-4e45-b38b-da310526378b&fileName=%22RID%20Review%20Checklist.xlsm%22 RID Review Checklist.xlsm] located in the ‘- Supporting Documents’ folder. |
− | * Complete the RID column of the [http://mdotjboss.state.mi.us/SpecProv/getDocumentById.htm?docGuid=71536ffa-6a51-4e45-b38b-da310526378b&fileName= RID Review Checklist.xlsm]. | + | * Complete the RID column of the [http://mdotjboss.state.mi.us/SpecProv/getDocumentById.htm?docGuid=71536ffa-6a51-4e45-b38b-da310526378b&fileName=%22RID%20Review%20Checklist.xlsm%22 RID Review Checklist.xlsm]. |
|- | |- | ||
| style="text-align:center;" | 2 | | style="text-align:center;" | 2 | ||
Line 150: | Line 150: | ||
|- | |- | ||
| style="text-align:center;" | 1 | | style="text-align:center;" | 1 | ||
− | | ''MDOT-RIDSupport Reviewers'' – Perform review of the RID files and document comments in the [http://mdotjboss.state.mi.us/SpecProv/getDocumentById.htm?docGuid=71536ffa-6a51-4e45-b38b-da310526378b&fileName= RID Review Checklist.xlsm]. Reference saved views in the RID Comments column. | + | | ''MDOT-RIDSupport Reviewers'' – Perform review of the RID files and document comments in the [http://mdotjboss.state.mi.us/SpecProv/getDocumentById.htm?docGuid=71536ffa-6a51-4e45-b38b-da310526378b&fileName=%22RID%20Review%20Checklist.xlsm%22 RID Review Checklist.xlsm]. Reference saved views in the RID Comments column. |
''NOTE: During this state the ‘RID’ folder will remain accessible for easy corrections of RID files during the MDOT-RIDSupport review.'' | ''NOTE: During this state the ‘RID’ folder will remain accessible for easy corrections of RID files during the MDOT-RIDSupport review.'' |
Revision as of 09:28, 17 October 2016
By Chapter
-Reserved-
1.4.1 Letting - Package Submittal
-Reserved-
State: E-Proposal Pending
PPMS Task: -Reserved-
State: E-Proposal Complete
PPMS Task: -Reserved-
State: E-Prop Initiate Final Project Review
PPMS Task: -Reserved-
State: E-Prop Workflow Assign
PPMS Task: -Reserved-
1.4.2 Letting - Review
-Reserved-
State: QA Tech - Pending
PPMS Task: -Reserved-
State: QA Tech - Complete
PPMS Task: -Reserved-
State: QA Tech - Assign to Reviewer
PPMS Task: -Reserved-
State: QA SE - Pending
PPMS Task: -Reserved-
State: QA SE - Complete
PPMS Task: -Reserved-
State: QA SE - Assign to Estimator
PPMS Task: -Reserved-
State: QA Est - Pending
PPMS Task: -Reserved-
State: QA Est - Complete
PPMS Task: -Reserved-
State: QA Final - Pending
PPMS Task: -Reserved-
State: QA Final - Complete
PPMS Task: -Reserved-
State: QA Final - Ready for Finance
PPMS Task: -Reserved-
State: Finance PQ - Pending
PPMS Task: -Reserved-
State: Finance BLU - Pending
PPMS Task: -Reserved-
State: Final
PPMS Task: -Reserved-
1.4.3 Letting - RID Review
State: E-Proposal RID Pending
PPMS Task:
Step | Action |
---|---|
1 | Design Team – Create RID Submittal during the State: E-Proposal Complete:
|
2 | Project Manager – Make sure the RID files are ready for review prior to completing the State: E-Prop Initiate Final Project Review. |
3 | Project Manager – Include MDOT RID Support on the email generated during the State: E-Prop Initiate Final Project Review. |
State: E-Proposal RID Complete
PPMS Task:
Step | Action |
---|---|
1 | MDOT-RIDSupport Reviewers – Perform review of the RID files and document comments in the RID Review Checklist.xlsm. Reference saved views in the RID Comments column.
NOTE: During this state the ‘RID’ folder will remain accessible for easy corrections of RID files during the MDOT-RIDSupport review. |
2 | MDOT-RIDSupport Reviewers – Prior to the State: QA Final – Ready for Finance:
|
3 | MDOT-RIDSupport Reviewers – Click on OK in the ‘Change Document to State’ window. |
State: E-Proposal RID Publish
PPMS Task:
Step | Action |
---|---|
1 | Finance – During the Final State:
Note: The RID must be in the State: E-Proposal Complete before they can be changed to the State: E-Proposal RID Publish. If the RID is not in the State: E-Proposal Complete at the time of Publishing please contact MDOT RID Support |
2 | If RID files are added after advertisement:
|