==[[#8.2 The Plan Review ProjectWise Process|8.2 The Plan Review ProjectWise Process]]==
 
'''Folder:'''
 
[[File:HeaderFolder PlanReview.png|none|left|650px|frameless]]
 
 
===[[#8.2.1 Package Submittal|8.2.1 Package Submittal]]===
 
 
 
====[[#State: Plan Review - Pending Submittal|State: Plan Review - Pending Submittal]]====
 
'''PPMS Task:'''  3580 - Develop Preliminary Plans
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''Design Team'' – Create PDF of:
 
* Plan Set and name “JN_Road_Prelim.pdf”, “JN_Bridge_Prelim.pdf”
 
* Proposal and name “JN_Proposal_Prelim.pdf”
 
* Supporting Documents and name “JN_SupportingDocuments_Prelim.pdf”
 
 
 
''NOTE: ROW must be included in plan set.''
 
|-
 
| style="text-align:center;" | 2
 
|''Design Team'' – Add PDFs created in step 1 into the ‘3 – Plan Review’ folder.[[File:PlanReviewFolder.png|right|650px|frameless]]
 
 
|-
 
| style="text-align:center;" | 3
 
| ''Design Team'' – Are all Preliminary Plan Review related files in the system? Yes, then:
 
* Highlight all files located in the ‘3 – Plan Review' folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
| style="text-align:center;" | 4
 
| ''Design Team'' – Click on OK in the ‘Change Document to State’ window
 
|-
 
| style="text-align:center;" | 5
 
| ''Design Team'' – Add the Project Manger’s email address into the system generated email.
 
 
Add Route and JN to Subject line of email.
 
 
[[File:Email_ThePlanReview_PendingSubmittal.jpg|right|650px|frameless]]
 
 
 
''NOTE: Leave MDOT-eProposal address in email. Also, you only need to send one email (close out of the other ones).''
 
|}
 
 
{{top}}
 
 
====[[#State: Plan Review - Review|State: Plan Review - Review]]====
 
'''PPMS Task:'''  3580 - Develop Preliminary Plans
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''Project Manager'' – Upon receipt of email, review proposal, plans and supporting document packages.
 
|-
 
| style="text-align:center;" | 2
 
| ''Project Manager'' – If files are ready for review, create a Digital Pen Set.
 
|-
 
|}
 
 
{{top}}
 
 
===[[#8.2.2 Review|8.2.2 Review]]===
 
'''Folder:'''
 
[[File:HeaderFolder_PlanReview_Review.png|none|left|650px|frameless]]
 
 
====[[#State: Plan Review - Pending|State: Plan Review - Pending]]====
 
'''PPMS Task:'''  3580 - Develop Preliminary Plans
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''Project Manager'' – Update and Save the ‘JN_0303_DPS.pdf file, located in ‘- Supporting Documents’ folder.
 
 
 
''NOTE: This is a “living” form. The Project Manager will update this form at each milestone.''
 
|-
 
| style="text-align:center;" | 2
 
| ''Project Manager'' – Print ‘JN_0303_DPS.pdf’ to PDF and apply the naming convention of ‘JN_0303_DPS _Prelim.pdf’.
 
|-
 
| style="text-align:center;" | 3
 
| ''Project Manager'' – Add file created in step 2 into the ‘Design Submittal Form and Minutes’ Folder.
 
 
[[File:Img_PlanReview_RequestForMeeting.jpg|right|875px|frameless]]
 
 
 
''NOTE: This file will be used to trigger the rest of the The Plan Review workflow process.''
 
|-
 
| style="text-align:center;" | 4
 
| ''Project Manager'' – Ready to coordinate the Plan Review meeting date with QA Review Manager? Yes, then:
 
* Single Left click on the ‘0303_DPS_Prelim.pdf’ located in the ‘Design Submittal Form and Minutes’ folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
| style="text-align:center;" | 5
 
| ''Project Manager'' – Click on OK in the ‘Change Document to State’ window
 
|-
 
| style="text-align:center;" | 6
 
| ''Project Manager'' – This email is to coordinate with QA on a date for the meeting. Enter Route and JN in subject. Enter dates available into the body of the system generated email.
 
 
Add Route and JN to Subject line of email.
 
 
[[File:Email_PlanReview_RequestForMeeting.jpg|right|650px|frameless]]
 
 
 
''NOTE: The Project Manager is NOW responsible for scheduling The Plan Review Meeting. This email is only to coordinate dates with QA Reviewer, NOT for them to schedule it.''
 
 
''NOTE: Leave all addresses in email. ''
 
|-
 
|}
 
 
{{top}}
 
 
====[[#State: Plan Review - Request for Meeting|State: Plan Review - Request for Meeting]]====
 
'''PPMS Task:''' 
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''QA Review Manager'' – Upon receipt of email, review Proposal, Plans and Supporting Documents packages.
 
|-
 
| style="text-align:center;" | 2
 
| ''QA Review Manager'' – If ready to assign a reviewer, then:
 
* Single Left click on the ‘0303_DPS_Prelim.pdf’ located in the ‘Meeting Request and Minutes’ folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
| style="text-align:center;" | 3
 
| ''QA Review Manager'' – Click on OK in the ‘Change Document to State’ window
 
|-
 
| style="text-align:center;" | 4
 
| ''QA Review Manager'' – Add the Reviewer’s email address into the system generated email.
 
 
Add Route and JN to Subject line of email.
 
 
[[file:Email_PlanReview_AssignedToReviewer.jpg|right|650px|frameless]]
 
 
 
''NOTE: Do not forget to switch this email to HTML format and include the File’s URN.''
 
|-
 
|}
 
{{top}}
 
 
====[[#State: Plan Review - Assigned to Reviewer|State: Plan Review - Assigned to Reviewer]]====
 
'''PPMS Task:''' 
 
 
{| class="wikitable" width = 80%
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95% | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''QA Reviewer'' – Upon receipt of email, proceed with coordinating meeting date and time with Project Manager.
 
|-
 
| style="text-align:center;" | 2
 
| ''QA Reviewer'' – Once there is an agreed upon date:
 
* Single Left click on the ‘0303_DPS_Prelim.pdf’ located in the ‘Meeting Request and Minutes’ folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
| style="text-align:center;" | 3
 
| ''QA Reviewer'' – Click on OK in the ‘Change Document to State’ window
 
|-
 
| style="text-align:center;" | 4
 
| ''QA Reviewer'' – Add the Project Manager’s email address into the system generated email.
 
 
[[file:Email_PlanReview_SchedAndNotify.jpg|right|650px|frameless]]
 
 
 
''NOTE: Add Route and JN to Subject line.''
 
|-
 
|}
 
{{top}}
 
 
====[[#State: Plan Review - Scheduling and Distribution|State: Plan Review - Scheduling and Distribution]]====
 
'''PPMS Task:''' 
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''Project Manager'' – Upon receipt of email, proceed with scheduling meeting date and time with reviewers.
 
|-
 
| style="text-align:center;" | 2
 
| ''Project Manager'' – Once you ready to initiate the meeting appointment:
 
* Single Left click on the ‘0303_DPS_Prelim.pdf’ located in the ‘Meeting Request and Minutes’ folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
| style="text-align:center;" | 3
 
| ''Project Manager'' – Click on OK in the ‘Change Document to State’ window
 
|-
 
| style="text-align:center;" | 4
 
| ''Project Manager'' – Please do the following to the system generated email:
 
 
* File > Save (this will save the email into your Drafts Outlook cabinet)
 
* Close the system generated email
 
* Go into your Outlook Drafts cabinet
 
* Highlight ‘The Plan Review Meeting for (CS - JN)’ email
 
* On the ‘Home’ tab click on the ‘Meeting’ icon
 
* The ProjectWise generated email will open into a Meeting Appointment
 
:* Update Date and Time for appointment
 
:* Add internal and external meeting attendees
 
::* Use the Review meeting contacts list.xlsx located in the ‘-Supporting Documents’ Reference Set. This list includes all Region and Central Office reviewers as well as [mailto:MDOT-RIDSupport@michigan.gov| MDOT RID Support].
 
 
[[File:Base_Meeting_Invite.png|650px|center|frameless]]
 
 
::''NOTE: Have ROW? Remember to invite ROW staff.''
 
 
:* Review body of email and update all meeting specific information (see highlighted text below)
 
 
 
:THE PLAN REVIEW MEETING ON: "<span style="background-color: #FFFF00">ENTER ROUTE</span>" CS: "<span style="background-color: #FFFF00">ENTER CN</span>" JNs: "<span style="background-color: #FFFF00">ENTER JNs HERE</span>"; "<span style="background-color: #FFFF00">ENTER LOCATION DESCRIPTION HERE</span>".
 
 
:Work entails: "<span style="background-color: #FFFF00">ENTER INFORMATION HERE</span>"
 
 
:The Plan Review Meeting on this project has been scheduled for "<span style="background-color: #FFFF00">ENTER DATE HERE</span>". "<span style="background-color: #FFFF00">ENTER QA REVIEWER</span>” will oversee this meeting and meet interested personnel at MDOT’s "<span style="background-color: #FFFF00">ENTER LOCATION AND STREET ADDRESS HERE</span>" at "<span style="background-color: #FFFF00">ENTER TIME HERE</span>".
 
 
:This project will be using the pilot digital pen process for reviewing the plans. Please make sure files are printed from the Digital Pen Plan Set folder (Digital Pen Plan Set) in ProjectWise and that all plan comments are done using a digital pen or PDF commenting. See the attached file for additional instructions.
 
 
:non-MDOT invitees: This project will be using Adobe commenting to review the plans which are located in MDOT’s ProjectWise. For access into MDOT’s ProjectWise system, please notify the Project Manager.
 
 
:All digital pen comments need to be placed in ProjectWise by 4:00 pm, "<span style="background-color: #FFFF00">ADD DATE HERE</span>" for the "<span style="background-color: #FFFF00">ENTER PROJECT MANAGER</span>" to do comment cleanup and redistribute a commented set of prints to all meeting attendees by "<span style="background-color: #FFFF00">ADD DATE HERE</span>" meeting.
 
 
:Electronic plan and proposal documents can be viewed in MDOT’s ProjectWise at the following location:
 
 
::Document Link: "<span style="background-color: #FFFF00">ADD DIGITAL PEN PLAN SET LINK HERE</span>"
 
 
::Project Manager: "<span style="background-color: #FFFF00">ENTER NAME AND PHONE NUMBER HERE</span>"
 
 
:If you have further comments or questions that require discussion, please contact me.
 
 
 
''NOTE: Please allow 20 work days for Preliminary Plan Review.''
 
|-
 
|}
 
 
[[File:DontForget.jpg|75px|left]]
 
 
 
 
 
''REMINDER: Update RID Checklist then move it into [[Chapter_8_-_ProjectWise_Pre-Bid_Processes#8.2.3_Preliminary_RID_Review|RID_Preliminary]] folder along with other RID files for review.  Make sure [mailto:MDOT-RIDSupport@michigan.gov MDOT RID Support] is included in meeting invite.''
 
 
 
 
 
 
{{top}}
 
 
====[[#State: Plan Review - Ready for Review|State: Plan Review - Ready for Review]]====
 
'''PPMS Task:'''  3590 - Preliminary Plan Review (NOTE: 20 work days for review)
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''The Plan Reviewers'' – Print dot matrix set, or applicable portions, and comment using the Digital Pen process or Adobe commenting.
 
 
 
''NOTE: Reviewers in the same office can share the same dot matrix set and pen. Also, it is recommended that comments are not removed from the pens until after the review meeting.''
 
|-
 
| style="text-align:center;" | 2
 
| ''The Plan Reviewers'' – Upload Digital Pen comments into ProjectWise.
 
|-
 
| style="text-align:center;" | 3
 
| ''Project Manager'' – After the 20-work-day review period:
 
* Single Left click on the ‘0303_DPS_Prelim.pdf’ located in the ‘Design Submittal Form’ folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
| style="text-align:center;" | 4
 
| ''Project Manager'' – Click on OK in the ‘Change Document to State’ window.
 
 
 
''NOTE: No email will be generated.''
 
|-
 
|}
 
{{top}}
 
 
====[[#State: Plan Review - PM Review in Progress|State: Plan Review - PM Review in Progress]]====
 
'''PPMS Task:'''  3600 - Project Manager Preliminary Plan Review (5 work days for review)
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''Project Manager'' – Copy ALL digital pen comment files to the ‘Pre-Construction > Record Plan Set Review Comments’ folder prior to reviewing the files.
 
|-
 
| style="text-align:center;" | 2
 
| ''Project Manager'' – Review and compile comments on ALL digital pen comment files located under the JN’s ‘3 - Plan Review’ folder.
 
|-
 
| style="text-align:center;" | 3
 
| ''Project Manager'' – Once all comments have reviewed and compiled:
 
* Single Left click on the ‘0303_DPS_Prelim.pdf’ located in the ‘Design Submittal Form’ folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
| style="text-align:center;" | 4
 
| ''Project Manager'' – Click on OK in the ‘Change Document to State’ window.
 
|-
 
| style="text-align:center;" | 5
 
| ''Project Manager'' - Add all Reviewers’ email addresses into the system generated email.
 
 
[[File:Email_PlanReview_ReadyForMeeting.jpg|650px|right|frameless]]
 
 
 
''NOTE: Do not forgot to switch this email to HTML format and include the File’s URN.''
 
|-
 
|}
 
{{top}}
 
 
====[[#State: Plan Review - Ready for  Meeting|State: Plan Review - Ready for  Meeting]]====
 
'''PPMS Task:'''  Design Team (5 work days for review)
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''Reviewers'' – Review compiled comments. Reminder: contact Project Manager with any comments prior to the the Plan Review Meeting.
 
|-
 
| style="text-align:center;" | 2
 
| ''QA Review'' – Once the meeting has ocucred:
 
* Prepare Draft Meeting Notes
 
* Add file into the ‘Meeting Request and Minutes’ folder.
 
|-
 
| style="text-align:center;" | 3
 
| ''QA Review'' – Prepare to send out notification requesting review of draft report:
 
* Highlight all files located in the ‘Meeting Request and Minutes’ folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
| style="text-align:center;" | 4
 
| ''QA Review'' – Click on OK in the ‘Change Document to State’ window.
 
|-
 
| style="text-align:center;" | 5
 
| ''QA Review'' - Add all applicable email addresses into the system generated email.
 
 
[[File:Email_PlanReview_DraftMtgReport.jpg|650px|right|frameless]]
 
 
 
''NOTE: Do not forget to switch this email to HTML format and include the File’s URN. Add Route and JN to Subject line.''
 
 
''NOTE: Send only one email.''
 
|-
 
|}
 
{{top}}
 
 
====[[#State: Plan Review - Draft Meeting Report Pending|State: Plan Review - Draft Meeting Report Pending]]====
 
'''PPMS Task:''' 
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''Reviewers'' – Upon receipt of email, review Draft Meeting Report. Reminder: contact QA Reviewer with any comments prior to the due date.
 
|-
 
| style="text-align:center;" | 2
 
| ''QA Review'' – Once the due date has ocucred:
 
* Prepare Final Meeting Notes
 
* Print to PDF and add file into the ‘Meeting Request and Minutes’ folder.
 
|-
 
| style="text-align:center;" | 2
 
| ''QA Review'' – Prepare to send out request to have Final Meeting Report distributed:
 
* Highlight all files located in the ‘Meeting Request and Minutes’ folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
| style="text-align:center;" | 3
 
| ''QA Review'' – Click on OK in the ‘Change Document to State’ window.
 
|-
 
| style="text-align:center;" | 4
 
| ''QA Review'' – Add Route and JN
 
 
[[File:Email_PlanReview_FinalDist.jpg|650px|right|frameless]]
 
 
 
''NOTE: Do not forgot to switch this email to HTML format and include the File’s URN.''
 
 
''NOTE: Send only one email.''
 
|-
 
|}
 
{{top}}
 
 
====[[#State: Plan Review - Final Report Distribution|State: Plan Review - Final Report Distribution]]====
 
'''PPMS Task:''' 
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''QA Admin Assistant'' – Prepare Final Meeting Report for distribution.
 
|-
 
| style="text-align:center;" | 2
 
| ''QA Admin Assistant'' – Prepare to send out Final Meeting Report notification:
 
* Highlight Final Meeting report located in the ‘Meeting Request and Minutes’ folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
| style="text-align:center;" | 3
 
| ''QA Admin Assistant'' – Click on OK in the ‘Change Document to State’ window.
 
|-
 
| style="text-align:center;" | 4
 
| ''QA Admin Assistant'' - Add all applicable email addresses into the system generated email.
 
 
[[File:Email_ThePlanReview_Review_FinalReportDist.jpg|650px|right|frameless]]
 
|}
 
 
{{top}}
 
 
====[[#State: Plan Review - Final Meeting Report|State: Plan Review - Final Meeting Report]]====
 
'''PPMS Task:''' 
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''Preliminary Plan Review workflow process is now complete.''
 
|-
 
|}
 
 
{{top}}
 
 
===[[#8.2.3 Preliminary RID Review|8.2.3 Preliminary RID Review]]===
 
 
 
====[[#State: Preliminary RID Review - Pending|State: Preliminary RID Review - Pending]]====
 
'''PPMS Task:'''  3580 - Develop Preliminary Plans
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
 
|-
 
|style="text-align:center;" | 1
 
| ''Design Team'' – Create RID Submittal during [[Chapter_8_-_ProjectWise_Pre-Bid_Processes#8.2.1_Package_Submittal | State: Plan Review - Pending Submittal]]:
 
* Place RID files in the ‘RID-Preliminary’ folder per [[Chapter_5_-_RID_Process | Chapter 5 - RID Process]]
 
* Copy the latest version of the [[media:RID_Review_Checklist.xlsm | RID Review Checklist.xlsm]] into the ‘- Supporting Documents’ folder.
 
* Complete the preliminary column of the [[media:RID_Review_Checklist.xlsm | RID Review Checklist.xlsm]]. If files or categories that are identified with an “R” in the [[media:Project_Data_Requirements_Table.pdf | Project Data Requirements Table.pdf]] are not included please document the reason in the Preliminary Comments Column of the [[media:RID_Review_Checklist.xlsm | RID Review Checklist.xlsm]].
 
|-
 
|style="text-align:center;" | 2
 
| ''Project Manager'' – Move the [[media:RID_Review_Checklist.xlsm | RID Review Checklist.xlsm]] file, located in ‘- Supporting Documents’ folder to ‘RID_Preliminary’ folder.
 
 
 
[[File:RID Prelim Checklist Folder.png|800px|right|frameless]]
 
 
''NOTE: This is a “living” form. The Project Manager will update this form at each milestone.''
 
|-
 
|style="text-align:center;" | 3
 
| ''Project Manager'' – Make sure the RID files are ready for review prior to completing the [[Chapter_8_-_ProjectWise_Pre-Bid_Processes#State:_Plan_Review_-_Pending | State: Plan Review - Pending]].
 
|-
 
|style="text-align:center;" | 4
 
| ''Project Manager'' – Once you are ready to initiate the meeting appointment during the [[Chapter_8_-_ProjectWise_Pre-Bid_Processes#State:_Plan_Review_-_Scheduling_and_Distribution | State: Plan Review – Scheduling and Distribution]]:
 
* Single Left click on the files in located in the ‘RID-Preliminary’ folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
|style="text-align:center;" | 5
 
| ''Project Manager'' – Click on OK in the ‘Change Document to State’ window
 
|-
 
|style="text-align:center;" | 6
 
| ''Project Manager'' – Include [mailto:MDOT-RIDSupport@michigan.gov MDOT RID Support] on the email generated during the [[Chapter_8_-_ProjectWise_Pre-Bid_Processes#State:_Plan_Review_-_Scheduling_and_Distribution | State: Plan Review – Scheduling and Distribution]].
 
|-
 
|} 
 
 
{{top}}
 
 
====[[#State: Preliminary RID Review - Review in Progress|State: Preliminary RID Review - Review in Progress]]====
 
'''PPMS Task:'''  3590 - The Plan Review ''(20 work days for review)''
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| ''MDOT-RIDSupport Reviewers'' – Perform review of the RID files and document comments in the [[media:RID_Review_Checklist.xlsm | RID Review Checklist.xlsm]]. Reference saved views in the Preliminary Comments column.
 
 
''NOTE: During this state the ‘RID-Preliminary’ folder will be locked for MDOT-RIDSupport review.''
 
|-
 
| style="text-align:center;" | 2
 
| ''MDOT-RIDSupport Reviewers'' – Move the [[media:RID_Review_Checklist.xlsm | RID Review Checklist.xlsm]] file, located in ‘RID_Preliminary’ folder to ‘RID_OEC’ folder. Leave a copy in the ‘RID_Preliminary’ folder and add the date to end of the [[media:RID_Review_Checklist.xlsm | RID Review Checklist.xlsm]] in the ‘RID_Preliminary’ folder.
 
|-
 
| style="text-align:center;" | 3
 
| ''MDOT-RIDSupport Reviewers'' – After the 20 work day review period:
 
* Single Left click on the files in located in the ‘RID-Preliminary’ folder.
 
* Then right click and select Change State.
 
* Select Next.
 
|-
 
| style="text-align:center;" | 4
 
| ''MDOT-RIDSupport Reviewers'' – Click on OK in the ‘Change Document to State’ window.
 
 
''NOTE: No email will be generated.''
 
|-
 
|}
 
{{top}}
 
 
====[[#State: Preliminary RID Review - Complete|State: Preliminary RID Review - Complete]]====
 
'''PPMS Task:''' 
 
 
{| class="wikitable" width = "80%"
 
|-
 
! style="text-align:center; width: 5%" | Step
 
! style="text-align:center; width: 95%" | Action
 
|-
 
| style="text-align:center;" | 1
 
| The files in the ‘RID-Preliminary’ folder will be locked as a time stamp of the submittal and review.  Responses from the Design Team or Project Manager should be placed in the OEC Comments column of the [[media:RID_Review_Checklist.xlsm | RID Review Checklist.xlsm]] which is now in the ‘RID_OEC’ folder.  The RID files can be copied from the ‘RID-Preliminary’ folder if necessary for discussion.
 
|-
 
| style="text-align:center;" | 2
 
| The files can be viewed by the Project Manager and Design Team during the [[Chapter_8_-_ProjectWise_Pre-Bid_Processes#State:_Plan_Review_-_PM_Review_in_Progress|State: Plan Review - PM Review in Progress]] and the [[Chapter_8_-_ProjectWise_Pre-Bid_Processes#State:_Plan_Review_-_Ready_for_Meeting|State: Plan Review - Ready for Meeting]].
 
|-
 
|}
 
{{top}}
 
  
 
==[[#8.3 OEC Plan Review ProjectWise Process|8.3 OEC Plan Review ProjectWise Process]]==
 
==[[#8.3 OEC Plan Review ProjectWise Process|8.3 OEC Plan Review ProjectWise Process]]==

Revision as of 16:25, 8 October 2015

ProjectWise Pre-Bid Processes

8.3 OEC Plan Review ProjectWise Process

Folder:

HeaderFolder OEC.png

8.3.1 Package Submittal

State: OEC - Pending Submittal

PPMS Task:

Step Action
1 Design Team – Create PDF of:
  • Plan Set and name “JN_Road_OEC.pdf” or “JN_Bridge_OEC.pdf”
  • Proposal and name “JN_Proposal_OEC.pdf”
  • Supporting Documents and name “JN_SupportingDocuments_OEC.pdf”


NOTE: ROW must be included in plan set.

2 Design Team – Add PDFs created in step 1 into the ‘5 – OEC Plans’ folder.
Img OECPlans Folder.png
3 Design Team – Are all OEC Plan related files in the system? Yes, then:
  • Highlight all files located in the ‘5 – OEC Plans’ folder.
  • Then right click and select Change State.
  • Select Next.
4 Design Team – Click on OK in the ‘Change Document to State’ window
5 Design Team - Add the Project Manager’s email address into the system generated email.


Email OEC PendingSub.png

NOTE: Leave MDOT-Eproposal address in email. Also, you only need to send one email (close out of the other ones).

[top of page]


State: OEC - Review

PPMS Task:

Step Action
1 Project Manager – Upon receipt of email, please review proposal, plans and supporting document packages. If ready, proceed to the next step of initiating the OEC Plan Review.
2 Project Manager – If files are ready for review, create a Digital Pen Set.

[top of page]


8.3.2 Review

Folder:

HeaderFolder OEC PlanReview.png

State: OEC - Pending

PPMS Task:

Step Action
1 Project Manager – Update and Save the ‘JN_0303_DPS.pdf file, located in ‘- Supporting Documents’ folder.


NOTE: This is a “living” form. The Project Manager will update this form for each milestone.

2 Project Manager – Print ‘JN_0303_DPS.pdf’ to PDF and apply the naming convention of ‘JN_0303_DPS _OEC.pdf’.
3 Project Manager – Add file created in step 2 into the ‘Design Submittal Form’ Folder.

NOTE: This file will be used to trigger the rest of the OEC Plan Review workflow process.

PW OEC Review Pending.jpg
4 Project Manager – Ready for OEC Plans to be reviewed by Region System Manager? Yes, then:
  • Single Left click on the ‘0303_DPS_OEC.pdf’ located in the ‘Design Submittal Form’ folder.
  • Then right click and select Change State.
  • Select Next.
5 Project Manager – Click on OK in the ‘Change Document to State’ window
6 Project Manager – Add the System Manager’s email address into the system generated email.


Email OEC Review Pending.jpg

NOTE: Leave MDOT-Eproposal address in email.

[top of page]


State: OEC - Ready for System Manager Approval

PPMS Task: (5 work days for review)

Step Action
1 System Manager – Upon receipt of email, review Proposal, Plans and Supporting Documents packages.
2 System Manager – If approved for OEC review/meeting, then:
  • Single Left click on the ‘0303_DPS_OEC.pdf’ located in the ‘Design Submittal Form’ folder.
  • Then right click and select Change State.
  • Select Next.
3 System Manager – Click on OK in the ‘Change Document to State’ window
4 System Manager – Add the Project Manager’s email address into the system generated email.


Email OEC Review ReadyFor.jpg

NOTE: Leave MDOT-Eproposal address in email.

5 Project Manager – Upon System Manager approval, create a Digital Pen Set. Then proceed with scheduling OEC Meeting.

[top of page]


State: OEC - System Manager Approved for Meeting

PPMS Task: (5 work days for review)

Step Action
1 Project Manager – Once digital pen set has been generated then proceed to initiativing meeting appointment:
  • Single Left click on the ‘0303_DPS_OEC.pdf’ located in the ‘Design Submittal Form’ folder.
  • Then right click and select Change State.
  • Select Next.
2 Project Manager – Click on OK in the ‘Change Document to State’ window
3 Project Manager – Please do the following to the system generated email:
  • File > Save (this will save the email into your Drafts Outlook cabinet)
  • Close the system generated email
  • Go into your Outlook Drafts cabinet
  • Highlight ‘OEC Plans ready for review’ email
  • Copy and Paste body of email into a newly created Meeting email
    • Add internal and external Base Plan meeting attendees
      • Use the Contact List located in the ‘-Supporting Documents’ Reference Set. This list includes all Region and Central Office reviewers as well as MDOT RID Support.
      NOTE: Have ROW? Remember to invite ROW staff.
    • Review body of email and update all meeting specific information (see highlighted text below)


THE OEC MEETING ON: "ENTER ROUTE" CS: "ENTER CN" JNs: "ENTER JNs HERE"; "ENTER LOCATION DESCRIPTION HERE".

Work entails: "ENTER INFORMATION HERE" "*PLEASE NOTE THAT CHANGES OR ADDITIONS TO THE SCOPE OF WORK WILL NOT BE CONSIDERED AT THIS MEETING."

The OEC Meeting on this project has been scheduled for "ENTER DATE HERE". "ENTER PROJECT MANAGER" will oversee this meeting and meet interested personnel at MDOT’s "ENTER LOCATION HERE" at ""ENTER TIME HERE".

MDOT Staff: This project will be using the pilot digital pen process for reviewing the plans. Please make sure plans are printed from the Digital Pen Plan Set folder (Digital Pen Plan Set) in ProjectWise and that all plan comments are done using a digital pen or Adobe commenting. See the attached file for additional instructions.

non-MDOT invitees: This project will be using Adobe commenting to review the plans which are located in MDOT’s ProjectWise. For access into MDOT’s ProjectWise system, please notify the Project Manager.

All digital pen comments need to be placed in ProjectWise by 4:00 pm, "ADD DATE HERE" for the "ENTER OFFICE NAME HERE" to do comment cleanup and redistribute a commented set of prints to all meeting attendees by "ADD DATE HERE" meeting.

Electronic plan and proposal documents can be viewed in MDOT’s ProjectWise at the following location:

Document Link: "ADD DIGITAL PEN PLAN SEET LINK HERE"

Project Manager: "ENTER NAME HERE AND PHONE NUMBER"

If you have further comments or questions that require discussion, please contact me.

NOTE: Please allow 15 work days for OEC Plan Review.


DontForget.jpg



REMINDER: Update RID Checklist in the RID_OEC folder along with other RID files for review. Highlight all files than change state to next to submit to RID Review staff.


[top of page]


State: OEC - Meeting Scheduled and Ready for Review

PPMS Task: 3870 – OEC Plan Review (10 work days for review)

Step Action
1 OEC Plan Reviewers – Print dot matrix set and comment using the Digital Pen process or Adobe commenting.


NOTE: Reviewers in the same office can share the same dot matrix set and pen. Also, it is recommended that comments are not removed from the pens until after the review meeting.

2 OEC Plan Reviewers – Upload Digital Pen comments into ProjectWise.
3 Project Manager – After the 10 work day review period:
  • Single Left click on the ‘0303_DPS_OEC.pdf’ located in the ‘Design Submittal Form’ folder.
  • Then right click and select Change State.
  • Select Next.
4 Project Manager – Click on OK in the ‘Change Document to State’ window.

NOTE: No email will be generated.

[top of page]


State: OEC - PM Review in Progress

PPMS Task: 3885 – Project Manager OEC Plan Review (5 work days for review)

Step Action
1 Project Manager – Copy ALL digital pen comment files to the ‘Pre-Construction > Record Plan Set Review Comments’ folder prior to reviewing the files.
2 Project Manager – Review and Compile comments on ALL digital pen comment files located under the JN’s ‘5 - OEC Plan’ folder.
3 Project Manager – Once all comments have reviewed and compiled:
  • Single Left click on the ‘0303_DPS_OEC.pdf’ located in the ‘Design Submittal Form’ folder.
  • Then right click and select Change State.
  • Select Next.
4 Project Manager – Click on OK in the ‘Change Document to State’ window.
5 Project Manager - Add all Reviewers’ email addresses into the system generated email.


Email OEC Review PMReview.jpg

NOTE: Please leave the three email addresses on the email.

[top of page]


State: OEC - Design Team Response

PPMS Task: Design Team (5 work days for review)

Step Action
1 Design Team/Reviewers – Review compiled comments. Reminder: contact Project Manager with any comments prior to the OEC Plan Meeting.
2 Project Manager – Once the meeting has occured:
  • Single Left click on the ‘0303_DPS_OEC.pdf’ located in the ‘Design Submittal Form’ folder.
  • Then right click and select Change State.
  • Select Next.
3 Project Manager – Click on OK in the ‘Change Document to State’ window.
4 OEC Plan Review workflow process is now complete.

[top of page]


8.3.3 OEC - RID Review

Folder:

HeaderFolder OEC RIDReview.png

State: OEC RID Review - Pending

PPMS Task:

Step Action
1 Design Team – Create RID Submittal during the State: OEC – Pending Submittal:
2 Project Manager – Make sure the RID Review Checklist.xlsm file, located in ‘RID_OEC’ folder is ready for submittal.


RID OEC Checklist Folder.png

NOTE: This is a “living” form. The Project Manager will update this form at each milestone.

3 Project Manager – Make sure the RID files are ready for review prior to completing the State: OEC - Pending.
4 Project Manager – Once you are ready to initiate the meeting appointment during State: OEC – System Manager Approved for Meeting:
  • Single Left click on the files in located in the ‘RID-OEC’ folder.
  • Then right click and select Change State.
  • Select Next.
5 Project Manager – Click on OK in the ‘Change Document to State’ window
6 Project Manager – Include MDOT RID Support on the email generated during the state change from State: OEC – System Manager Approved for Meeting to State: OEC- Meeting Scheduled and Ready for Review.

State: OEC RID Review - Review in Progress

PPMS Task: 3870 - OEC Plan Review (15 work days for review)

Step Action
1 MDOT-RIDSupport Reviewers – Perform review of the RID files and document comments in the RID Review Checklist.xlsm. Reference saved views in the OEC Comments column.


NOTE: During this state the ‘RID-OEC’ folder will be locked for MDOT-RIDSupport review.

2 MDOT-RIDSupport Reviewers – Move the RID Review Checklist.xlsm file, located in ‘RID_OEC’ folder to ‘- Supporting Documents’ folder. Leave a copy in the "RID_OEC' folder and add the date to end of the RID Review Checklist.xlsm in the ‘RID_OEC’ folder.
3 MDOT-RIDSupport Reviewers – After the 15 work day review period:
  • Single Left click on the files in located in the ‘RID-OEC’ folder.
  • Then right click and select Change State.
  • Select Next.
4 MDOT-RIDSupport Reviewers – Click on OK in the ‘Change Document to State’ window.


NOTE: No email will be generated.

State: OEC RID Review - Complete

PPMS Task:

Step Action
1 The files in the ‘RID-OEC’ folder will be locked as a time stamp of the submittal and review. Responses from the Design Team or Project Manager should be placed in the RID Comments column of the RID Review Checklist.xlsm which is now in the ‘- Supporting Documents’ folder. The RID files can be copied from the ‘RID-OEC’ folder if necessary for discussion.
2 The files can be viewed by the Project Manager and Design Team during the State: OEC – PM Review in Process and the State: OEC – Design Team Response.

[top of page]


8.4 Letting Plan Review ProjectWise Process

put temporary link to Letting Plan and Proposal Review process instructions.docx

-Reserved-

8.4.1 Letting - Package Submittal

-Reserved-

State: E-Proposal Pending

PPMS Task: -Reserved-

[top of page]


State: E-Proposal Complete

PPMS Task: -Reserved-

[top of page]


State: E-Prop Initiate Final Project Review

PPMS Task: -Reserved-

[top of page]


State: E-Prop Workflow Assign

PPMS Task: -Reserved-

[top of page]


8.4.2 Letting - Review

-Reserved-

State: QA Tech - Pending

PPMS Task: -Reserved-

[top of page]


State: QA Tech - Complete

PPMS Task: -Reserved-

[top of page]


State: QA Tech - Assign to Reviewer

PPMS Task: -Reserved-

[top of page]


State: QA SE - Pending

PPMS Task: -Reserved-

[top of page]


State: QA SE - Complete

PPMS Task: -Reserved-

[top of page]


State: QA SE - Assign to Estimator

PPMS Task: -Reserved-

[top of page]


State: QA Est - Pending

PPMS Task: -Reserved-

[top of page]


State: QA Est - Complete

PPMS Task: -Reserved-

[top of page]


State: QA Final - Pending

PPMS Task: -Reserved-

[top of page]


State: QA Final - Complete

PPMS Task: -Reserved-

[top of page]


State: QA Final - Ready for Finance

PPMS Task: -Reserved-

[top of page]


State: Finance PQ - Pending

PPMS Task: -Reserved-

[top of page]


State: Finance BLU - Pending

PPMS Task: -Reserved-

[top of page]


State: Final

PPMS Task: -Reserved-

[top of page]


8.4.3 Letting - RID Review

State: E-Proposal RID Pending

PPMS Task:

Step Action
1 Design Team – Create RID Submittal during the State: E-Proposal Complete:
2 Project Manager – Make sure the RID files are ready for review prior to completing the State: E-Prop Initiate Final Project Review.
3 Project Manager – Include MDOT RID Support on the email generated during the State: E-Prop Initiate Final Project Review.

[top of page]


State: E-Proposal RID Complete

PPMS Task:

Step Action
1 MDOT-RIDSupport Reviewers – Perform review of the RID files and document comments in the RID Review Checklist. Reference saved views in the RID Comments column.

NOTE: During this state the ‘RID’ folder will remain accessible for easy corrections of RID files during the MDOT-RIDSupport review.

2 MDOT-RIDSupport Reviewers – Prior to the State: QA Final – Ready for Finance:
  • Single Left click on the files in located in the ‘RID’ folder.
  • Then right click and select Change State.
  • Select Next.
3 MDOT-RIDSupport Reviewers – Click on OK in the ‘Change Document to State’ window.

[top of page]


State: E-Proposal RID Publish

PPMS Task:

Step Action
1 Finance – During the Final State:
  • Single Left click on the files in located in the ‘RID’ folder.
  • Then right click and select Change State.
  • Select Next.

Note: The RID must be in the State: E-Proposal Complete before they can be changed to the State: E-Proposal RID Publish. If the RID is not in the State: E-Proposal Complete at the time of Publishing please contact MDOT RID Support

2 If RID files are added after advertisement:
  • Project Manager - Email MDOT RID Support and include 'Added RID', 'RID File Name Change', or 'Post Award RID' in the Subject Line. Please also include a link to the Added RID. See RID_Changes for more information.
  • MDOT RID Support - Confirm that added RID is in conformance with Standards, and then Change State twice to Publish.

[top of page]


8.5 Design Exception ProjectWise Process

put temporary link to Design Exception Review process instructions.docx

-Reserved-