Difference between revisions of "Chapter 1 - ProjectWise Pre-Bid Processes"

From MediaWiki
Jump to navigation Jump to search
Line 130: Line 130:
  
 
==[[#8.3 OEC Plan Review ProjectWise Process|8.3 OEC Plan Review ProjectWise Process]]==
 
==[[#8.3 OEC Plan Review ProjectWise Process|8.3 OEC Plan Review ProjectWise Process]]==
The '''[OEC Plan Review process instructions.pdf]''' has been temporarily posted while the information is converted to wiki format.
+
The '''[//{{SERVERNAME}}/images_design/3/38/OEC_Plan_Review_process_instructions.pdf OEC Plan Review process instructions.pdf]''' has been temporarily posted while the information is converted to wiki format.
  
 
===[[#8.3.1 Package Submittal|8.3.1 Package Submittal]]===
 
===[[#8.3.1 Package Submittal|8.3.1 Package Submittal]]===

Revision as of 14:59, 10 March 2015

-Reserved-

8.1 Base Plan Review ProjectWise Process

The Base_Plan_Review_process_instructions.pdf has been temporarily posted while the information is converted to wiki format.

8.1.1 Package Submittal

-Reserved-

[top of page]


State: Base Plan - Pending Submittal

PPMS Task: 3360 - Prepare Base Plans

-Reserved-

[top of page]


State: Base Plan - Review

PPMS Task: 3360 - Prepare Base Plans

-Reserved-

[top of page]


8.1.2 Review

-Reserved-

[top of page]


State: Base Plan Review - Pending

PPMS Task: 3360 - Prepare Base Plans

-Reserved-

[top of page]


State: Base Plan Review - Ready for Review

PPMS Task: 3380 – Review Base Plans (NOTE: 20 work days for review)

-Reserved-

[top of page]


State: Base Plan Review - PM Review in Progress

PPMS Task: 3395 – Project Manager Base Plan Review (5 work days for review)

-Reserved-

[top of page]


State: Base Plan Review - Design Team Response

PPMS Task: Design Team (5 work days for review)

-Reserved-

[top of page]


8.2 Preliminary Plan Review ProjectWise Process

The The_Plan_Review_process_instructions.pdf has been temporarily posted while the information is converted to wiki format.

8.2.1 Package Submittal

-Reserved-

[top of page]


State: The Plan Review - Pending Submittal

PPMS Task: 3580 – Develop Preliminary Plans

-Reserved-

[top of page]


State: The Plan Review - Review

PPMS Task: 3580 – Develop Preliminary Plans

-Reserved-

[top of page]


8.2.2 Review

-Reserved-

State: The Plan Review - Pending

PPMS Task: 3580 – Develop Preliminary Plans

-Reserved-

[top of page]


State: The Plan Review - Request for Meeting

PPMS Task:

-Reserved-

[top of page]


State: The Plan Review – Assigned to Reviewer

PPMS Task:

-Reserved-

[top of page]


State: The Plan Review – Scheduling and Distribution

PPMS Task:

-Reserved-

[top of page]


State: The Plan Review - Ready for Review

PPMS Task: 3590 – Preliminary Plan Review (NOTE: 20 work days for review)

-Reserved-

[top of page]


State: The Plan Review – PM Review in Progress

PPMS Task: 3600 – Project Manager Preliminary Plan Review (5 work days for review)

-Reserved-

[top of page]


State: The Plan Review – Ready for Meeting

PPMS Task: Design Team (5 work days for review)

-Reserved-

[top of page]


State: The Plan Review – Draft Meeting Report Pending

PPMS Task:

-Reserved-

[top of page]


State: The Plan Review – Final Report Distribution

PPMS Task:

-Reserved-

[top of page]


State: The Plan Review – Final Meeting Report

PPMS Task:

-Reserved-

[top of page]


8.3 OEC Plan Review ProjectWise Process

The OEC Plan Review process instructions.pdf has been temporarily posted while the information is converted to wiki format.

8.3.1 Package Submittal

-Reserved-

State: OEC Plan - Pending Submittal

PPMS Task:

-Reserved-

[top of page]


State: OEC Plan - Review

PPMS Task:

-Reserved-

[top of page]


8.3.2 Review

-Reserved-

State: OEC Plan Review - Pending

PPMS Task:

-Reserved-

[top of page]


State: OEC Review – Ready for Region Approval

PPMS Task:

-Reserved-

[top of page]


State: OEC Review – Region Approved for Meeting

PPMS Task:

-Reserved-

[top of page]


State: OEC Plan Review – Meeting Scheduled and Ready for Review

PPMS Task: 3870 – OEC Plan Review (NOTE: 15 work days for review)

-Reserved-

[top of page]


State: OEC Plan Review – PM Review in Progress

PPMS Task: 3885 – Project Manager OEC Plan Review (5 work days for review)

-Reserved-

[top of page]


State: OEC Plan Review - Design Team Response

PPMS Task: Design Team (5 work days for review)

-Reserved-

[top of page]


8.4 Letting Plan Review ProjectWise Process

put temporary link to Letting Plan and Proposal Review process instructions.docx

-Reserved-

[top of page]


8.5 Design Exception ProjectWise Process

put temporary link to Design Exception Review process instructions.docx

-Reserved-