Deletion log
Jump to navigation
Jump to search
Below is a list of the most recent deletions.
(newest | oldest) View (newer 100 | older 100) (20 | 50 | 100 | 250 | 500)- 15:49, 21 May 2014 Greenes2 talk contribs deleted page 103.11 - Submitting Contract Revisions (Author request: content was: "103 - Post Award Administration '''103.11 - SUBMITTING CONTRACT MODIFICATIONS''' '''103.11.1 Post Final -''' When a contract modification is processed after the project has been finaled, generally the result of a ...)
- 15:49, 21 May 2014 Greenes2 talk contribs deleted page 103.10 - Failure to Sign (Author request: content was: "103 - Post Award Administration '''103.10 - FAILURE TO SIGN''' When a Contractor fails to sign a change contract modification, the contract modification should be submitted unsigned after 21 calendar days. If a Cont...)
- 15:49, 21 May 2014 Greenes2 talk contribs deleted page 103.09 - Balancing Quantities (Author request: content was: "103 - Post Award Administration '''103.09 - BALANCING QUANTITIES''' Balancing Contract Modifications should be prepared as soon as contract items are completed. Do not delay submitting Contract Modifications until t...)
- 15:49, 21 May 2014 Greenes2 talk contribs deleted page 103.08 - FHWA Approval (Author request: content was: "103 - Post Award Administration '''103.08 - FHWA APPROVAL''' Federally funded projects are considered in two categories, EXEMPT or NONEXEMPT. An EXEMPT project does not require FHWA review and oversight. A NONEXEMP...)
- 15:49, 21 May 2014 Greenes2 talk contribs deleted page 103.07 - Basis of Payment for Extra Work (Author request: content was: "103 - Post Award Administration '''103.07 - BASIS OF PAYMENT FOR EXTRA WORK''' Documenting the basis of payment on the contract modification for extra work is necessary. Payment can be based on negotiated unit price...)
- 15:49, 21 May 2014 Greenes2 talk contribs deleted page 103.06 - Distribution (Author request: content was: "103 - Post Award Administration '''103.06 - DISTRIBUTION''' For ''FieldManager'' Version 3.0 and above the Contract Modification is approved and authorized at the Region level. If the Contract Modification does not ...)
- 15:49, 21 May 2014 Greenes2 talk contribs deleted page 103.01 - Work Order (Author request: content was: "103 - Post Award Administration '''103.01 - WORK ORDER''' The Work Order, Form 1137, is a written order signed by the Engineer and requiring performance by the Contractor. Signed work orders have contractual status....)
- 15:44, 21 May 2014 Greenes2 talk contribs deleted page 103.05 - Preparing COntract Revisions (Author request: content was: "103 - Post Award Administration '''103.05 - PREPARING CONTRACT MODIFICATIONS''' Contract modifications are usually prepared by the Engineer. If possible, contract modifications should be approved before the work is ...)
- 15:44, 21 May 2014 Greenes2 talk contribs deleted page 103.04 - Decimal Values (Author request: content was: "103 - Post Award Administration '''103.04 - DECIMAL VALUES''' Quantities for Contract Modifications should be computed to the same decimal values shown in the summary of quantities in the contract or proposal, or tot...)
- 15:44, 21 May 2014 Greenes2 talk contribs deleted page 103.03 - Types of Contract Revisions (Author request: content was: "103 - Post Award Administration '''103.03 - TYPES OF CONTRACT MODIFICATIONS''' '''103.03.1 Changes in Contract''' A change in the contract alters the quantity of existing contract items. This includes items bid ...)
- 15:44, 21 May 2014 Greenes2 talk contribs deleted page 103.02 - Contract Revisions (Author request: content was: "103 - Post Award Administration '''103.02 - CONTRACT MODIFICATIONS''' The Standard Specifications for Construction define a contract modification as the regulation form prepared as a recommendation for changes in, ad...)
- 15:44, 21 May 2014 Greenes2 talk contribs deleted page 102.04 - PreConstruction Meeting (Author request: content was: "102 - PreConstruction Administration '''102.04 - PRECONSTRUCTION MEETING''' A preconstruction meeting will be initiated by the Engineer when authorized or once the confirmed low bidder is announced. Representatives ...)
- 15:44, 21 May 2014 Greenes2 talk contribs deleted page Kari test page (Author request: content was: "<center>For copies of this manual contact the MDOT Publications Office</center> <center>Telephone: (517) 322-1676 Fax: (517) 322-1395</center> <center></..." (and the only contributor was "[[Special:Contributions/Obri...)
- 15:44, 21 May 2014 Greenes2 talk contribs deleted page 102.02 - Plans, Proposals, Input, Review, and Evaluation (Author request: content was: "102 - PreConstruction Administration '''102.02. - PLANS, PROPOSAL, INPUT, REVIEW AND EVALUATION''' With the advent of Plan Review Reengineering, the Engineer assigned to the construction of the project is now involve...)
- 15:44, 21 May 2014 Greenes2 talk contribs deleted page 102.01 - Contractor Evaluations and Prequalification (Author request: content was: "102 - PreConstruction Administration '''102.01 - CONTRACTOR EVALUATIONS AND PREQUALIFICATION''' At a minimum, Contractor evaluations for the last two construction seasons are reviewed when the Contractor applies for ...)
- 15:44, 21 May 2014 Greenes2 talk contribs deleted page 101.10 - Controlling Consultant Costs (Author request: content was: "101 - General Project Administration '''101.10. - CONTROLLING CONSULTANT COSTS''' The Regions are charged with knowing their costs and controlling their construction engineering costs. As several consultant construc...)
- 15:37, 21 May 2014 Greenes2 talk contribs deleted page 101.05 - Certified Payrolls (Author request: content was: "101 - General Project Administration '''101.05 - CERTIFIED PAYROLLS''' '''101.05.1 State Funded Projects ''' Certified weekly payrolls covering the Contractor’s and the Subcontractors’ work forces will not be...)
- 15:37, 21 May 2014 Greenes2 talk contribs deleted page 101.03 - Field Manager (Author request: content was: "101 - General Project Administration '''101.03 - FIELDMANAGER''' [http://michigan.gov/mdot/0,1607,7-151-9625_47921---,00.html FieldManager] is a construction management system employed by over 1000 users to manage an...)
- 15:37, 21 May 2014 Greenes2 talk contribs deleted page 101.02 - Project Records (Author request: content was: "101 - General Project Administration '''101.02 - PROJECT RECORDS''' To ensure uniform record keeping of project documents, a standard filing system is followed in each project office. These procedures will be follow...)
- 15:37, 21 May 2014 Greenes2 talk contribs deleted page 101.09 - Disadvantaged Business Enterprises (DBE's) (Author request: content was: "101 - General Project Administration '''101.09 - DISADVANTAGED BUSINESS ENTERPRISES (DBE’s)''' DBE’s are defined as those prime and subcontractors, truckers, materials suppliers and other service providers who ar...)
- 15:37, 21 May 2014 Greenes2 talk contribs deleted page 101.08 - On the Job Training (Author request: content was: "101 - General Project Administration '''101.08 - ON-THE-JOB TRAINING''' As of January 1, 2001, MDOT has implemented a new OJT Pilot Program designed to provide training in the skilled construction trade classifica...)
- 15:37, 21 May 2014 Greenes2 talk contribs deleted page 101.07 - Equal Employment Opportunity (Author request: content was: "101 - General Project Administration '''101.07 - EQUAL EMPLOYMENT OPPORTUNITY''' For these regulations, minorities are defined as Black, Asian or Pacific Islanders, Native American and Hispanic. Compliance with the ...)
- 15:37, 21 May 2014 Greenes2 talk contribs deleted page 101.06 - Davis-Bacon Provisions (Author request: content was: "101 - General Project Administration '''101.06 - DAVIS-BACON PROVISIONS''' '''101.06.1 Truck Drivers - Owner/Operators''' These individuals are not subject to the wage rates prescribed by the Department of Labor....)
- 15:37, 21 May 2014 Greenes2 talk contribs deleted page 101.04 - Inspector's Daily Reports (Author request: content was: "101 - General Project Administration '''101.04 - INSPECTOR’S DAILY REPORT (IDR)''' Perhaps the single most important type of project documentation is the Inspector’s Daily Report (IDR) and its variations. Becaus...)
- 15:37, 21 May 2014 Greenes2 talk contribs deleted page 101.01 - Project Authority (Author request: content was: "101 - General Project Administration '''101.01 - PROJECT AUTHORITY''' It is important that users of the manual understand their role in ensuring that specifications are adhered to in completing the project. Each per...)
- 15:36, 21 May 2014 Greenes2 talk contribs deleted page 210.06 - Dust Control (Author request: content was: "210 - Environmental '''210.06 - DUST CONTROL''' Dust control is very important, especially during the earthwork phase of construction. Adequate dust control measures will be maintained by the Contractor so as not to...)
- 15:35, 21 May 2014 Greenes2 talk contribs deleted page 210.05 - Contractor Yards (Author request: content was: "210 - Environmental '''210.05 - CONTRACTOR YARDS''' As mentioned in Section 205 of this manual, under Borrow/Use of Excess Property, the Contractor is not allowed to use sta...)
- 15:35, 21 May 2014 Greenes2 talk contribs deleted page 210.04 - Discovery of Bones, Archeological, and Historical Findings (Author request: content was: "210 - Environmental '''210.04 - DISCOVERY OF BONES, ARCHAEOLOGICAL AND HISTORICAL FINDINGS''' Subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/107%20Legal%20Rel,%20Resp%20to%20Public.pdf 107.09] of th...)
- 15:35, 21 May 2014 Greenes2 talk contribs deleted page 210.03 - Hazardous Waste Site Identification Numbers (MIK Numbers) (Author request: content was: "210 - Environmental '''210.03 - HAZARDOUS WASTE SITE IDENTIFICATION NUMBERS (MIK NUMBERS)''' In the past, when waste site identification numbers, formerly MIK numbers, were needed, they were obtained from the Environ...)
- 15:35, 21 May 2014 Greenes2 talk contribs deleted page 210.02 - Removal of Underground Storage Tanks (Author request: content was: "210 - Environmental '''210.02 - REMOVAL OF UNDERGROUND STORAGE TANKS''' MDOT has the responsibility to remove any underground storage tanks (USTs) found within the ROW, even if not in direct conflict with the propose...)
- 15:35, 21 May 2014 Greenes2 talk contribs deleted page 210.01 - General (Author request: content was: "210 - Environmental '''210.01 - GENERAL''' This section of the manual is not intended to be an all-inclusive environmental guidance document, but addresses those environmental issues that are commonly associated with...)
- 15:35, 21 May 2014 Greenes2 talk contribs deleted page 209.01 - General (Author request: content was: "209 - Project Cleanup '''209.01 - GENERAL''' This work consists of cleaning up the project, including roadsides, prior to final acceptance. Cleanup applies to the area within the ROW not in excess of 50 feet (15 met...)
- 15:35, 21 May 2014 Greenes2 talk contribs deleted page 208.05 - Non-Compliance Progressive Steps (Author request: content was: "208 - Soil Erosion and Sedimentation Control (NPDES) '''208.05 - NON-COMPLIANCE PROGRESSIVE STEPS''' '''208.05.01''' The following are suggested progressive steps to take if a Contractor fails to comply with eithe...)
- 15:35, 21 May 2014 Greenes2 talk contribs deleted page 208.02 - Soil Erosion and Sedimentation Control Guidelines (Author request: content was: "208 - Soil Erosion and Sedimentation Control (NPDES) '''208.02 - SOIL EROSION AND SEDIMENTATION CONTROL GUIDELINES''' '''208.02.01''' Notification: While individual permits are not necessary, the Engineer is requi...)
- 15:34, 21 May 2014 Greenes2 talk contribs deleted page 208.04 - Winter Shutdown (Author request: content was: "208 - Soil Erosion and Sedimentation Control (NPDES) '''208.04 - WINTER SHUTDOWN''' '''208.04.01''' MDOT is able to suspend NPDES inspections during the winter on those projects that satisfy all of the following c...)
- 15:34, 21 May 2014 Greenes2 talk contribs deleted page 208.03 - National Pollutuion Discharge Eliminaton System (NPDES) Guidelines (Author request: content was: "208 - Soil Erosion and Sedimentation Control (NPDES) '''208.03 - NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM GUIDELINES''' '''208.03.01''' The proposal for projects subject to NPDES regulations, earth disturba...)
- 15:34, 21 May 2014 Greenes2 talk contribs deleted page 208.01 - General (Author request: content was: "208 - Soil Erosion and Sedimentation Control (NPDES) '''208.01 - GENERAL''' '''208.01.01''' MDOT is responsible to provide transportation services in an environmentally sensitive manner. To that end, the followi...)
- 15:34, 21 May 2014 Greenes2 talk contribs deleted page 207.01 - General (Author request: content was: "207 - Obliterating Roadway '''207.01 - GENERAL''' Obliterating roadway applies only on those portions of the existing or temporary roadway outside the limits of the new roadway. The ditches will be filled and roadwa...)
- 15:34, 21 May 2014 Greenes2 talk contribs deleted page 206.04 - Suitability of Foundation Material (Author request: content was: "206 - Excavation and Backfill for Structures '''206.04 - SUITABILITY OF FOUNDATION MATERIAL''' Final excavation for the foundation to grade will not be made until just before the concrete is to be placed. Concrete w...)
- 15:34, 21 May 2014 Greenes2 talk contribs deleted page 206.03 - Excavation for Structures (Author request: content was: "206 - Excavation and Backfill for Structures '''206.03 - EXCAVATION FOR STRUCTURES''' Foundation excavation is set up for the excavation of all materials, except rock, encountered within the foundation excavation lim...)
- 15:34, 21 May 2014 Greenes2 talk contribs deleted page 206.02 - Backfill for Structures (Author request: content was: "206 - Excavation and Backfill for Structures '''206.02 - BACKFILL FOR STRUCTURES''' Backfill for structures that are bridges, grade separations, pump houses and retaining walls shall be Granular Material Class II, un...)
- 15:32, 21 May 2014 Greenes2 talk contribs deleted page 206.01 - Preparing Abutment Areas (Author request: content was: "206 - Excavation and Backfill for Structures '''206.01 - PREPARING ABUTMENT AREA''' The importance of the proper construction of bridge abutment embankments cannot be overemphasized. The abutments are rigid structur...)
- 15:32, 21 May 2014 Greenes2 talk contribs deleted page 205.15 - Measurement of Earthwork (Author request: content was: "205 - Roadway Earthwork '''205.15 - MEASUREMENT OF EARTHWORK''' If no changes occur during construction and there are no known design errors, final quantities for earth excavation, embankment CIP and top 3 feet (1 m)...)
- 15:32, 21 May 2014 Greenes2 talk contribs deleted page 205.14 - Machine Grading (Author request: content was: "205 - Roadway Earthwork '''205.14 - MACHINE GRADING''' Machine grading is used only when light grading, such as may be accomplished with a blade grader, is required to develop the desired section. This item includes...)
- 15:32, 21 May 2014 Greenes2 talk contribs deleted page 205.13 - Wetland Construction (Author request: content was: "205 - Roadway Earthwork '''205.13 - WETLAND CONSTRUCTION''' If a wetland is to be constructed in association with a project for mitigation purposes, there will generally be plan sheets detailing the construction requ...)
- 15:32, 21 May 2014 Greenes2 talk contribs deleted page 205.12 - Borrow/Use of Excess Property (Author request: content was: "205 - Roadway Earthwork '''205.12 - BORROW/USE OF EXCESS PROPERTY''' Earth material found outside the grading limits is considered borrow material. This can include material either inside or outside the ROW. Unless...)
- 15:32, 21 May 2014 Greenes2 talk contribs deleted page 205.11 - Trimming and Finishing Earth Grade (Author request: content was: "205 - Roadway Earthwork '''205.11 - TRIMMING AND FINISHING EARTH GRADE''' After the earth grade has been constructed to the required grade, all stones and rocks more than 3 inches (80 mm) in diameter appearing on the...)
- 15:31, 21 May 2014 Greenes2 talk contribs deleted page 205.10 - Test Rolling (Author request: content was: "205 - Roadway Earthwork '''205.10 - TEST-ROLLING''' Test-rolling the grade is a very important procedure for determining uniform stability of the subgrade. Perhaps the most important subgrade quality to attain is st...)
- 15:31, 21 May 2014 Greenes2 talk contribs deleted page 205.09 - Swamp Treatment (Author request: content was: "205 - Roadway Earthwork '''205.09 - SWAMP TREATMENT''' All swamp areas should be shown on plans with a specific method of treatment indicated. All low, poorly drained areas not shown as peat or muck should neverthel...)
- 15:31, 21 May 2014 Greenes2 talk contribs deleted page 205.08 - Constructing Embankments (Author request: content was: "205 - Roadway Earthwork '''205.08 - CONSTRUCTING EMBANKMENTS''' Embankments are generally constructed by three methods. (The last method will be discussed under Swamp Treatment. * Controlled density method. * 12 i...)
- 15:31, 21 May 2014 Greenes2 talk contribs deleted page 205.07 - Disposing of Surplus and Unsuitable Material (Author request: content was: "205 - Roadway Earthwork '''205.07 - DISPOSING OF SURPLUS AND UNSUITABLE MATERIAL''' The Contractor will be responsible for disposal of all surplus and unsuitable material. If it is disposed of in a storage area, spe...)
- 15:30, 21 May 2014 Greenes2 talk contribs deleted page 205.06 - Constructing Ditches (Author request: content was: "205 - Roadway Earthwork '''205.06 - CONSTRUCTING DITCHES''' Removal of material from ditches is generally classed as earth excavation as ditches are normally excavated along with general road cut using typical earth ...)
- 15:30, 21 May 2014 Greenes2 talk contribs deleted page 205.05 - Subgrade Undercutting (Author request: content was: "205 - Roadway Earthwork '''205.05 - SUBGRADE UNDERCUTTING''' There are three types of subgrade undercutting, all of which include backfilling and compaction. * Type I will be backfilled with selected clay or other s...)
- 15:30, 21 May 2014 Greenes2 talk contribs deleted page 205.04 - Blasting (Author request: content was: "205 - Roadway Earthwork '''205.04 - BLASTING''' Before using explosives on a project, the Contractor is to furnish the Engineer with a copy of the "rider" or clause in the insurance policy as evidence that there is a...)
- 15:30, 21 May 2014 Greenes2 talk contribs deleted page 205.03 - Rock Excavation (Author request: content was: "205 - Roadway Earthwork '''205.03 - ROCK EXCAVATION''' This work consists of the removal of solid rock or cemented soils that do not soften when wet or cannot be excavated without continuous drilling, blasting or con...)
- 15:30, 21 May 2014 Greenes2 talk contribs deleted page 205.02 - Preparing Roadway Foundation (Author request: content was: "205 - Roadway Earthwork '''205.02 - PREPARING ROADWAY FOUNDATION''' The roadway foundation must be properly prepared to provide uniform support and a stable structure. During embankment construction, the following o...)
- 15:30, 21 May 2014 Greenes2 talk contribs deleted page 205.01 - Earth Excavation (Author request: content was: "205 - Roadway Earthwork '''205.01 - EARTH EXCAVATION''' Section [http://mdotcf.state.mi.us/public/specbook/files/2012/205%20Roadway%20Earthwork.pdf 205] of the Standard Specifications for Construction details constru...)
- 15:30, 21 May 2014 Greenes2 talk contribs deleted page 204.03 - Hot Mix Asphalt (HMA) Pavements and Driveways (Author request: content was: "204 - Removing Miscellaneous Structures and Materials '''204.03 - HOT MIX ASPHALT (HMA) PAVEMENTS AND DRIVEWAYS''' For removal of HMA pavements and driveways: If the HMA surface removed is 5 inches (130 mm) or less ...)
- 15:30, 21 May 2014 Greenes2 talk contribs deleted page 204.02 - Structures (Author request: content was: "204 - Removing Miscellaneous Structures and Materials '''204.02 - STRUCTURES''' All structures and attached parts and connections shown on the plans to be removed will be entirely removed. Structures requiring remov...)
- 15:30, 21 May 2014 Greenes2 talk contribs deleted page 204.01 - Documentation (Author request: content was: "204 - Removing Miscellaneous Structures and Materials '''204.01 - DOCUMENTATION''' Identifying, measuring and recording removal items on an IDR (or on Form 1122A) are very important. If the Contractor chooses to dis...)
- 15:30, 21 May 2014 Greenes2 talk contribs deleted page 203.02 - Culvert of Sewer (Author request: content was: "203 - Removing Drainage Structures, Culverts, and Sewers '''203.02 - CULVERT OR SEWER''' When a culvert pipe and/or sewer pipe is to be removed, the culvert pipe and/or sewer pipe (and end treatments) are to be compl...)
- 15:29, 21 May 2014 Greenes2 talk contribs deleted page 203.01 - Drainage Structures (Author request: content was: "203 - Removing Drainage Structures, Culverts, and Sewers '''203.01 - DRAINAGE STRUCTURES''' When removing or abandoning a drainage structure, any live sewers connected to them will be rebuilt and properly connected t...)
- 15:29, 21 May 2014 Greenes2 talk contribs deleted page 202.02 - Instructions for Removing Corduroy (Author request: content was: "202 - Removing Trees, Stumps, and Corduroy '''202.02 - INSTRUCTIONS FOR REMOVING CORDUROY''' When corduroy is found within 4 feet (1.2 m) below plan grade, its removal will be by the foot (meter) measured along the r...)
- 15:29, 21 May 2014 Greenes2 talk contribs deleted page 202.01 - Instructions for Removing Trees and Stumps (Author request: content was: "202 - Removing Trees, Stumps, and Corduroy '''202.01 - INSTRUCTIONS FOR REMOVING TREES AND STUMPS''' These items will apply to locations outside the areas to be paid as '''Clearing'''. Work in progress and work comp...)
- 15:29, 21 May 2014 Greenes2 talk contribs deleted page 201.01 - General (Author request: content was: "201 - Clearing '''201.01 - GENERAL''' Before beginning any construction operation, refer to subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/107%20Legal%20Rel,%20Resp%20to%20Public.pdf 107.15], Compli...)
- 15:29, 21 May 2014 Greenes2 talk contribs deleted page 307.04 - Weighing Materials (Author request: content was: "307 - Aggregate Shoulders and Approaches '''307.04 - WEIGHING MATERIALS''' Materials paid for by weight are required to be weighed on an approved scale system. There are permanent and portable scale systems. '''307...)
- 15:29, 21 May 2014 Greenes2 talk contribs deleted page 307.03 - Measurement and Payment (Author request: content was: "307 - Aggregate Shoulders and Approaches '''307.03 - MEASUREMENT AND PAYMENT''' Where trenching is required on both sides of the road, each side will be measured separately along the road centerline. When shoulders ...)
- 15:29, 21 May 2014 Greenes2 talk contribs deleted page 307.02 - Construction (Author request: content was: "307 - Aggregate Shoulders and Approaches '''307.02 - CONSTRUCTION''' '''307.02.1 Trenching''' When trenching is proposed, the operations will not be performed beyond the distance that will be backfilled and comp...)
- 15:29, 21 May 2014 Greenes2 talk contribs deleted page 301.03 - Measurement and Payment (Author request: content was: "301 - Subbase '''301.03 - MEASUREMENT AND PAYMENT''' Plan quantity plus or minus any known changes, if agreed to by the Engineer and Contractor, as a basis for final quantity for subbase, is encouraged whenever possi...)
- 15:24, 21 May 2014 Greenes2 talk contribs deleted page 305.01 - General (Author request: content was: "305 - HMA Base Crushing and Shaping '''305.01 - GENERAL''' '''305.01.1 Equipment''' The age of the equipment being used by the Contractor will have an effect on the amount of additional crushed material through ...)
- 15:24, 21 May 2014 Greenes2 talk contribs deleted page 307.01 - General (Author request: content was: "307 - Aggregate Shoulders and Approaches '''307.01 - GENERAL''' For all trenching, shoulder and approach operations that cannot be completed at the end of the day, the Contractor will place and maintain traffic contr...)
- 15:23, 21 May 2014 Greenes2 talk contribs deleted page 306.01 - General (Author request: content was: "306 - Aggregate Surface Course '''306.01 - GENERAL''' Compliance with density requirements for aggregate surface course construction is just as important as for aggregate base construction. Poor compactive efforts a...)
- 15:23, 21 May 2014 Greenes2 talk contribs deleted page 304.04 - Inspection (Author request: content was: "304 - Rubbilizing Existing PCC Pavement '''304.04 - INSPECTION''' The inspector should study the staging details very carefully. In situations where the road must be reopened for traffic, the rubblizing Contractor a...)
- 15:23, 21 May 2014 Greenes2 talk contribs deleted page 304.03 - Materials (Author request: content was: "304 - Rubbilizing Existing PCC Pavement '''304.03 - MATERIALS''' Filler aggregate will meet the Open-graded Aggregate 3G Specification, Section [http://mdotcf.state.mi.us/public/specbook/files/2012/902%20Aggregate.pd...)
- 15:23, 21 May 2014 Greenes2 talk contribs deleted page 304.02 - Equipment (Author request: content was: "304 - Rubbilizing Existing PCC Pavement '''304.02 - EQUIPMENT''' Equipment will be as listed in subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/304%20Rubbilizing%20PCC%20Pavt.pdf 304.03] of the Stand...)
- 15:23, 21 May 2014 Greenes2 talk contribs deleted page 304.01 - Description (Author request: content was: "304 - Rubbilizing Existing PCC Pavement '''304.01 - DESCRIPTION''' This work will consist of rubblizing existing concrete pavements to be used as a base course for Hot Mix Asphalt (HMA) pavements.")
- 15:23, 21 May 2014 Greenes2 talk contribs deleted page 303.01 - General (Author request: content was: "303 - Open Graded Drainage Course '''303.01 - GENERAL''' The plans and proposal should be reviewed for notes or special provisions pertaining to open graded drainage course (OGDC). OGDC is intended to provide a stab...)
- 15:23, 21 May 2014 Greenes2 talk contribs deleted page 302.03 - Measurement and Payment (Author request: content was: "302 - Aggregate Base Courses '''302.03 - MEASUREMENT AND PAYMENT''' '''302.03.1 Payment by Square Yard (Square Meter)''' The following criteria should be adhered to with payment by the square yard (square meter)...)
- 15:23, 21 May 2014 Greenes2 talk contribs deleted page 302.02 - Construction (Author request: content was: "302 - Aggregate Base Courses '''302.02 - CONSTRUCTION''' '''302.02.1 Placing and Compacting''' Some cross sections are designed with a “step” in the subbase and a different aggregate depth in the shoulder ar...)
- 15:23, 21 May 2014 Greenes2 talk contribs deleted page 302.01 - Materials (Author request: content was: "302 - Aggregate Base Courses '''302.01 - MATERIALS''' Aggregates from dense graded series 21AA, 21A and 22A will be used for aggregate bases as per subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/902...)
- 15:22, 21 May 2014 Greenes2 talk contribs deleted page 301.02 - Construction (Author request: content was: "301 - Subbase '''301.02 - CONSTRUCTION''' '''301.02.1 Procedure''' The subbase will be placed on an approved subgrade surface that meets density and cross section requirements. Verify that subgrade has been exam...)
- 15:22, 21 May 2014 Greenes2 talk contribs deleted page 301.01 - Materials (Author request: content was: "301 - Subbase '''301.01 - MATERIALS''' Granular Material Class II will be used for constructing subbase.")
- 15:22, 21 May 2014 Greenes2 talk contribs deleted page 405.01 - General (Author request: content was: "405 - Pump Station Construction '''405.01- GENERAL''' Pump station construction is extremely specialized work. For this reason, if a pump station is to be constructed, Section [http://mdotcf.state.mi.us/public/specb...)
- 15:22, 21 May 2014 Greenes2 talk contribs deleted page 404.03 - Measurement (Author request: content was: "404 - Underdrain '''404.03 - MEASUREMENT''' The inspector must measure and record trench dimensions to ensure that specification widths and depths are being obtained. Underdrains, edgedrains and bank drains are meas...)
- 15:22, 21 May 2014 Greenes2 talk contribs deleted page 404.02 - Materials (Author request: content was: "404 - Underdrain '''404.02 - MATERIALS''' Subgrade underdrains are slotted or perforated drains placed near the edge of the traveled way for the purpose of lowering a high groundwater condition or draining a granular...)
- 15:22, 21 May 2014 Greenes2 talk contribs deleted page 404.01 - General (Author request: content was: "404 - Underdrain '''404.01 - GENERAL''' It is very difficult to determine the extent and volume of groundwater infiltration. Experienced Region Soils personnel usually make this determination. The inspector should ...)
- 15:22, 21 May 2014 Greenes2 talk contribs deleted page 403.04 - Adjusting Drainage Sturctures (Author request: content was: "403 - Drainage Structures '''403.04 - ADJUSTING DRAINAGE STRUCTURES''' Refer to subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/403%20Drainage%20Structures.pdf 403.04] of the Standard Specifications ...)
- 15:12, 21 May 2014 Greenes2 talk contribs deleted page 403.03 - Backfilling Drainage Sturctures (Author request: content was: "403 - Drainage Structures '''403.03 - BACKFILLING DRAINAGE STRUCTURES''' Backfilling is to be done in accordance with subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/401%20Pipe%20Culverts.pdf 401.03]...)
- 15:12, 21 May 2014 Greenes2 talk contribs deleted page 403.02 - Construction Methods (Author request: content was: "403 - Drainage Structures '''403.02. - CONSTRUCTION METHODS''' Excavation for drainage structures is to be performed in accordance with subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/206%20Exc,%20Ba...)
- 15:12, 21 May 2014 Greenes2 talk contribs deleted page 403.01 - General (Author request: content was: "403 - Drainage Structures '''403.01 - GENERAL''' Drainage structures refer to manholes, catch basins, leaching basins, inlets and drop inlets as detailed on Standard Plan R-1 series or on project plans. A drainage s...)
- 15:12, 21 May 2014 Greenes2 talk contribs deleted page 402.08 - Illicit Connections (Author request: content was: "402 - Storm Sewers '''402.08 - ILLICIT CONNECTIONS''' If unusual or suspicious connections to MDOT’s storm sewer system are found during a construction project (e.g. the presence of a sudsy discharge or oily discha...)
- 15:12, 21 May 2014 Greenes2 talk contribs deleted page 402.07 - Sewer Taps (Author request: content was: "402 - Storm Sewers '''402.07 - SEWER TAPS''' Connections to storm sewers owned by counties, municipalities or drain commissions shall be according to the regulations of the owner and according to the plans and specif...)
- 15:12, 21 May 2014 Greenes2 talk contribs deleted page 402.06 - Sewer Pipe Jacked in Place (Author request: content was: "402 - Storm Sewers '''402.06 - SEWER PIPE JACKED-IN-PLACE''' Follow the requirements of subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/401%20Pipe%20Culverts.pdf 401.03] of the Standard Specification...)
- 15:12, 21 May 2014 Greenes2 talk contribs deleted page 402.05 - Inspection After Installation (Author request: content was: "402 - Storm Sewers '''402.05 - INSPECTION AFTER INSTALLATION''' All of the general inspection points in the previous section on culverts apply to sewer pipes. '''402.05.1 Mandrel Testing''' If smooth lined corr...)
- 15:11, 21 May 2014 Greenes2 talk contribs deleted page 402.04 - Backfilling Sewer Pipe (Author request: content was: "402 - Storm Sewers '''402.04 - BACKFILLING SEWER PIPE''' Backfilling sewer pipe will be as specified in subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/401%20Pipe%20Culverts.pdf 401.03] of the Standa...)
- 15:11, 21 May 2014 Greenes2 talk contribs deleted page 402.03 - Installation (Author request: content was: "402 - Storm Sewers '''402.03 - INSTALLATION''' Construction methods shall be according to the health and safety requirements in subsection [http://mdotcf.state.mi.us/public/specbook/files/2012/104%20Control%20of%20Wo...)
- 15:11, 21 May 2014 Greenes2 talk contribs deleted page 402.02 - Materials Inspection (Author request: content was: "402 - Storm Sewers '''402.02. - MATERIALS INSPECTION''' Some concrete storm sewer pipe does not contain reinforcement and therefore requires careful handling. Any pipe damaged in transit or by handling should be rej...)
- 15:10, 21 May 2014 Greenes2 talk contribs deleted page 401.06 - Pipe Culverts Jacked in Place (Author request: content was: "401 - Culverts '''401.06 - PIPE CULVERTS JACKED-IN-PLACE''' Pipe culverts jacked-in-place are used when it is desired to place a drainage feature without disturbing the roadbed or railroad above the pipe. The excava...)
- 15:10, 21 May 2014 Greenes2 talk contribs deleted page 402.01 - General (Author request: content was: "402 - Storm Sewers '''402.01 - GENERAL''' The inspector’s preliminary investigation should determine if the storm sewer is correctly staked and the storm sewer is the type, size and class called for in the plans, o...)
- 15:10, 21 May 2014 Greenes2 talk contribs deleted page 401.05 - Inspection after Installation (Author request: content was: "401 - Culverts '''401.05 - INSPECTION AFTER INSTALLATION''' Culvert sections showing signs of settlement or poor alignment shall, as directed by the Engineer, be taken up and relaid at the Contractor’s expense. An...)