- 11:45, 19 January 2022 diff hist -162 m 709 - Timber Sturctures Removed 2012 Spec Book tagline link
- 11:45, 19 January 2022 diff hist -167 m 708 - Prestressed Concrete Removed 2012 Spec Book tagline link current
- 11:45, 19 January 2022 diff hist -169 m 707 - Structural Steel Removed 2012 Spec Book tagline link
- 11:44, 19 January 2022 diff hist -168 m 706 - Structural Concrete Removed 2012 Spec Book tagline link
- 11:44, 19 January 2022 diff hist -162 m 705 - Foundation Piling Removed 2012 Spec Book tagline link
- 11:44, 19 January 2022 diff hist -171 m 704 - Steel Sheet Piling and Cofferdams Removed 2012 Spec Book tagline link
- 11:43, 19 January 2022 diff hist -172 m 703 - Mortar and Concrete Patching Repair and Resurfacing Mixes Removed 2012 Spec Book tagline link current
- 11:43, 19 January 2022 diff hist -163 m 702 - Mortar and Grout Removed 2012 Spec Book tagline link current
- 11:43, 19 January 2022 diff hist -165 m 701 - Portland Cement Concrete for Structures Removed 2012 Spec Book tagline link current
- 11:41, 19 January 2022 diff hist -168 m 603 - Concrete Pavement Restoration Removed 2012 Spec Book tagline link
- 11:41, 19 January 2022 diff hist -180 m 602 - Concrete Pavement Construction Removed 2012 Spec Book tagline link
- 10:46, 18 January 2022 diff hist +369 Main Page →Recent Minor Changes: Added 102.02 change for lead times of Delineator and 3# U-Channel Posts
- 10:41, 18 January 2022 diff hist 0 102.02 Contents of Proposal - Progress Clause →Progress Clause: Updated Typical Long-Lead Items for Delineator and 3# U-Channel Posts
- 12:41, 13 January 2022 diff hist -50 501 - Plant Produced Hot Mix Asphalt →Utilizing Reclaimed Asphalt Pavement (RAP) Millings from the Same Project When Using a Portable Hot Mix Asphalt (HMA) Plant: Removed section cat
- 12:39, 13 January 2022 diff hist +25 501 - Plant Produced Hot Mix Asphalt →Utilizing Reclaimed Asphalt Pavement (RAP) Millings from the Same Project When Using a Portable Hot Mix Asphalt (HMA) Plant: Updated cat section
- 17:48, 12 January 2022 diff hist -171 m 406 - Precast Three-Sided, Arch, and Box Culverts Removed 2012 Spec Book tagline link current
- 17:47, 12 January 2022 diff hist -167 m 405 - Pump Station Construction Removed 2012 Spec Book tagline link current
- 17:47, 12 January 2022 diff hist -155 m 404 - Underdrain Removed 2012 Spec Book tagline link current
- 17:47, 12 January 2022 diff hist -165 m 403 - Drainage Structures Removed 2012 Spec Book tagline link current
- 17:47, 12 January 2022 diff hist -158 m 402 - Storm Sewers Removed 2012 Spec Book tagline link current
- 17:46, 12 January 2022 diff hist -159 m 401 - Culverts Removed 2012 Spec Book tagline link
- 17:46, 12 January 2022 diff hist -161 m 209 - Project Cleanup Removed 2012 Spec Book tagline link
- 17:46, 12 January 2022 diff hist -166 m 207 - Obliterating Roadway Removed 2012 Spec Book tagline link
- 17:45, 12 January 2022 diff hist -171 m 206 - Excavation and Backfill for Structures Removed 2012 Spec Book tagline link
- 17:45, 12 January 2022 diff hist -163 m 205 - Roadway Earthwork Removed 2012 Spec Book tagline link
- 17:45, 12 January 2022 diff hist -169 m 204 - Removing Miscellaneous Structures and Materials Removed 2012 Spec Book tagline link
- 17:44, 12 January 2022 diff hist -176 m 203 - Removing Drainage Structures, Culverts, and Sewers Removed 2012 Spec Book tagline link
- 17:44, 12 January 2022 diff hist -169 m 202 - Removing Trees, Stumps, and Corduroy Removed 2012 Spec Book tagline link
- 17:43, 12 January 2022 diff hist -151 m 201 - Clearing Removed 2012 Spec Book tagline link
- 17:42, 12 January 2022 diff hist -155 m 150 - Mobilization Removed 2012 Spec Book tagline link current
- 17:40, 12 January 2022 diff hist -171 m 108.10 Liquidated Damages Removed 2012 Spec Book tagline link
- 17:39, 12 January 2022 diff hist -171 m 108.07 Extension of Time on Work Day Contracts Removed 2012 Spec Book tagline link
- 17:38, 12 January 2022 diff hist -171 m 108.01 Subcontracting of Contract Work Removed 2012 Spec Book tagline link current
- 17:36, 12 January 2022 diff hist -176 m 107.15 Compliance with Laws; Environmental Protection Removed 2012 Spec Book tagline link current
- 17:35, 12 January 2022 diff hist -176 m 107.12 Contractor's Responsibility for Utility Property and Services Removed 2012 Spec Book tagline link
- 17:34, 12 January 2022 diff hist -168 m 106 - Quality Assurance Acceptance Program Removed 2012 Spec Book tagline link current
- 17:33, 12 January 2022 diff hist -179 m 105.10 Buy America Source of Steel and Iron Removed 2012 Spec Book tagline link
- 17:32, 12 January 2022 diff hist -167 m 105.07 Handling and Transporting Materials Removed 2012 Spec Book tagline link current
- 17:31, 12 January 2022 diff hist -167 m 105.01 Quality and Scope of Supply Removed 2012 Spec Book tagline link
- 17:29, 12 January 2022 diff hist -161 m 104.07 Contractor Obligations Removed 2012 Spec Book tagline link
- 17:28, 12 January 2022 diff hist -161 m 104.01 Authority of the Department Removed 2012 Spec Book tagline link current
- 17:28, 12 January 2022 diff hist -159 m 103.02 Contract Revisions Removed 2012 Spec Book tagline link
- 17:23, 12 January 2022 diff hist -168 m 101 - Terms, Format, and Conditions Removed 2012 Spec Book tagline link current
- 16:59, 12 January 2022 diff hist -167 m 308 - Geotextiles for Base Removed 2012 Spec Book tagline link current
- 16:58, 12 January 2022 diff hist -170 m 307 - Aggregate Shoulders and Approaches Removed 2012 Spec Book tagline link
- 16:58, 12 January 2022 diff hist -166 m 306 - Aggregate Surface Course Removed 2012 Spec Book tagline link current
- 16:44, 12 January 2022 diff hist -176 m 305 - HMA Base Crushing and Shaping Removed 2012 Spec Book tagline link current
- 16:43, 12 January 2022 diff hist -168 m 304 - Rubbilizing Existing PCC Pavement Removed 2012 Spec Book tagline link
- 16:43, 12 January 2022 diff hist -147 m 303 - Open Graded Drainage Course Removed 2012 Spec Book tagline current
- 16:07, 12 January 2022 diff hist -168 302 - Aggregate Base Courses Removed 2012 Spec Book tagline
- 12:25, 12 January 2022 diff hist -150 m 301 - Subbase Removed 2012 tagline link
- 16:27, 5 January 2022 diff hist +100 Main Page →Recent Major Changes: Updated Summary fields for 109.07 and 107.09
- 09:00, 5 January 2022 diff hist +352 Main Page →Recent Minor Changes: Added Final Project Review Report update
- 08:57, 5 January 2022 diff hist +1 Final Project Review Report Replaced Final Project Review Report User Guide with September 2020 version current
- 08:55, 5 January 2022 diff hist 0 N File:Final Project Review Report User Guide 9-2020.pdf current
- 15:13, 4 January 2022 diff hist +361 Main Page →Recent Minor Changes: Updated info for 102.02
- 14:53, 4 January 2022 diff hist +25 102.02 Contents of Proposal - Progress Clause →Progress Clause: updated/added to Guardrail - Steel typical long-lead times
- 14:30, 4 January 2022 diff hist +357 Main Page →Recent Major Changes: added 109.07 update
- 14:25, 4 January 2022 diff hist -71 109.07 Final Inspection, Acceptance, and Final Payment →Acceptance of Work: Removed outdated images and added updated image
- 14:21, 4 January 2022 diff hist 0 N File:Form 1120 image.pdf current
- 14:09, 4 January 2022 diff hist 0 File:Form 1120 image.jpg SchaeferS uploaded a new version of File:Form 1120 image.jpg current
- 14:08, 4 January 2022 diff hist 0 N File:Form 1120 image.jpg
- 10:25, 4 January 2022 diff hist +93 107.09 Archeological and Historical Findings →LAP Project Considerations: Added link to LAP definitions
- 10:23, 4 January 2022 diff hist +445 Main Page →Recent Minor Changes: Added Archeological and Historical Findings Resource for LAP
- 10:20, 4 January 2022 diff hist +166 Local Agency Program (LAP) →Construction Manual index/links for ‘LAP Project Considerations’: added Archeological and Historical Findings as a resource
- 10:14, 4 January 2022 diff hist +99 107.09 Archeological and Historical Findings →LAP Project Considerations
- 13:42, 21 December 2021 diff hist -363 109.07 Final Inspection, Acceptance, and Final Payment →Acceptance of Work: Updated section information
- 10:30, 21 December 2021 diff hist +316 Main Page →Recent Major Changes: Added 107.09 Archeological and Historical Findings Update
- 10:28, 21 December 2021 diff hist +9 107.09 Archeological and Historical Findings Added link to top
- 10:27, 21 December 2021 diff hist +412 107.09 Archeological and Historical Findings Updated entire section
- 18:17, 15 December 2021 diff hist -156 506 - Slurry Seal Removed 2012 Spec Book tagline at top of page current
- 18:17, 15 December 2021 diff hist -158 504 - Micro-Surfacing Removed 2012 Spec Book tagline at top of page current
- 18:16, 15 December 2021 diff hist -174 503 - Paver Placed Surface Seal Removed 2012 Spec Book tagline at top of page current
- 18:15, 15 December 2021 diff hist -165 502 - HMA Crack Treatment Removed 2012 Spec Book tagline at top of page current
- 18:14, 15 December 2021 diff hist -155 505 - Chip Seals removed 2012 Spec Book tagline at top of page current
- 18:14, 15 December 2021 diff hist 0 505 - Chip Seals →Longitudinal Construction Joints: Updated 2012 Spec Book reference to 2020
- 10:19, 15 December 2021 diff hist -162 501 - Plant Produced Hot Mix Asphalt removed 2012 Spec Book tagline at top of page
- 15:57, 14 December 2021 diff hist +259 Main Page →Recent Minor Changes: Added Division 5, updating 2012 to 2020 Spec Book reference
- 15:53, 14 December 2021 diff hist 0 501 - Plant Produced Hot Mix Asphalt →Plant Procedures: Updated 2012 to 2020 Spec Book reference
- 11:33, 13 December 2021 diff hist +5 Main Page →Recent Minor Changes
- 11:33, 13 December 2021 diff hist -8 Main Page →Recent Minor Changes
- 11:32, 13 December 2021 diff hist +340 Main Page →Recent Minor Changes: Added December's updated Certified Engineer List 12132021
- 11:30, 13 December 2021 diff hist -3 Certified Engineer Process →Current Certified Engineers: Updated Engineer Certification List 12132021
- 11:29, 13 December 2021 diff hist 0 N File:Engineer certification list 12132021.jpg current
- 11:28, 13 December 2021 diff hist 0 N File:Engineer certification list 12132021.pdf current
- 17:24, 23 November 2021 diff hist +443 Main Page →Recent Major Changes: Added new subsection, "Sediment Discharge into Waters of the State of Michigan," in Section 208.
- 17:20, 23 November 2021 diff hist +1,306 208 - Soil Erosion and Sedimentation Control (NPDES) →Non-Compliance of SESC: Created new section "Sediment Discharge into Waters of the State of Michigan"
- 13:35, 18 November 2021 diff hist -11,388 Main Page →Recent Major Changes: removed items more than a year old
- 17:01, 17 November 2021 diff hist +129 103.02 Contract Revisions →Design Errors: Added Premium Costs for Design Errors and Field Issues link under Design Errors Section
- 11:28, 17 November 2021 diff hist +369 Main Page →Recent Major Changes: Added new section Design Errors and updated Premium Costs for Design Errors and Field Issues to 103.02 Contract Revisions section.
- 10:55, 17 November 2021 diff hist +2,849 103.02 Contract Revisions Added new section "Design Errors" and updated "Premium Costs for Design Errors and Field Issues" section
- 08:50, 17 November 2021 diff hist +358 Main Page →Recent Minor Changes: Added Bi-Annual FieldManager User Account Verification Process update
- 17:27, 16 November 2021 diff hist +606 FieldManager →Bi-Annual FieldManager User Account Verification Process: Updated content in its entirety.
- 09:01, 27 October 2021 diff hist +333 Main Page →Recent Major Changes: updated several sections of 103.02 Construction Contract Modification Process Overview
- 08:55, 27 October 2021 diff hist -104 103.02 Contract Revisions →Tier III - Bureau of Field Services Approval: Updated content for Tier III - Bureau of Field Services Approval
- 08:55, 27 October 2021 diff hist -84 103.02 Contract Revisions →Tier II - Region Approval: Updated content for Tier II - Region Approval
- 08:54, 27 October 2021 diff hist -212 103.02 Contract Revisions →Tier I - TSC Approval: Updated content for Tier I - TSC Approval
- 08:52, 27 October 2021 diff hist +215 103.02 Contract Revisions →Contract Modification Development: New content for Contract Modification Development
- 16:17, 20 October 2021 diff hist +412 Main Page →Recent Minor Changes: Added change for 108.01
- 16:09, 20 October 2021 diff hist -256 108.01 Subcontracting of Contract Work →Construction Subcontract Process: Removed text re: engineer's responsibility to check subcontractors are prequalified prior to start of work.