(Created page with "=CONTRACT ADMINISTRATION= ==Managing Contracts== The Additional Information tab allows you to maintain additional information on the contract. 1. Navigate to the Contract...")
 
Line 1: Line 1:
 
=CONTRACT ADMINISTRATION=
 
=CONTRACT ADMINISTRATION=
  
==Managing Contracts==
+
==Managing Contracts Information==
  
The Additional Information tab allows you to maintain additional information on the contract.  
+
<p style="color:green"><i>The Additional Information tab allows you to maintain additional information on the contract.  
 +
</i>
 +
</p>
  
1. Navigate to the Contract Administration component.
+
1. Navigate to the '''Contract Administration''' component.
  
 
2. Search for and Select the contract ID that you are assigned.
 
2. Search for and Select the contract ID that you are assigned.
  
3. Click the Additional Information tab.
+
3. Click the '''Additional Information''' tab.
 +
 
 +
 
 +
[[File:Contract Administration Picture1.png|center]]
 +
 
  
 
4. The following fields are available, depending on your role, some maybe updatable:
 
4. The following fields are available, depending on your role, some maybe updatable:
a. Proposal Type - click the drop-down arrow and select the proposal type.
+
 
b. Division/Residency - enter the administrative office level responsible for this contract.
+
<ol style="list-style-type:lower-alpha">
c. Designer - search for and select the person responsible for the contract’s design.
+
<li>'''Proposal Type''' - click the drop-down arrow and select the proposal type.</li>
d. Surety - search for and select the name of the company that insures the proposal vendor.
+
<li>'''Division/Residency''' - enter the administrative office level responsible for this contract.</li>
e. Surety Agent - search for and select the contact person at the surety company.
+
<li>'''Designer''' - search for and select the person responsible for the contract’s design.</li>
f. Stormwater Events Enabled – click checkbox if a Stormwater Event is required.
+
<li>'''Surety''' - search for and select the name of the company that insures the proposal vendor.</li>
g. Contract Work Type - click the drop-down arrow and select the kind of work to be performed.
+
<li>'''Surety Agent''' - search for and select the contact person at the surety company.</li>
h. Progress Schedule Type - click the drop-down arrow and select the method used to track contract progress.
+
<li>'''Stormwater Events Enabled''' – click checkbox if a Stormwater Event is required.</li>
i. Contract Alternate Name 1 - enter an alternate name for the contract, if appropriate.
+
<li>'''Contract Work Type''' - click the drop-down arrow and select the kind of work to be performed.</li>
j. Contract Alternate Name 2 - enter a second alternate name for the contract, if appropriate.
+
<li>'''Progress Schedule Type''' - click the drop-down arrow and select the method used to track contract progress.</li>
k. Total Allowable Maximum Subcontract Percent - enter the maximum percent of contract work that the agency allows to be subcontracted for non-specialty items.
+
<li>'''Contract Alternate Name 1''' - enter an alternate name for the contract, if appropriate.</li>
l. Supplemental Spec Book - enter a specification book associated with the proposal in addition to the primary spec book.
+
<li>'''Contract Alternate Name 2''' - enter a second alternate name for the contract, if appropriate.</li>
m. Incentive Cap Amount - enter the maximum incentive amount that can be paid to contractors for work on the contract.
+
<li>'''Total Allowable Maximum Subcontract Percent''' - enter the maximum percent of contract work that the agency allows to be subcontracted for non-specialty items.</li>
n. Disincentive Cap Amount - enter the maximum total amount of disincentives that can be withheld from payment to contractors for work on the contract.
+
<li>'''Supplemental Spec Book''' - enter a specification book associated with the proposal in addition to the primary spec book.</li>
 +
<li>'''Incentive Cap Amount''' - enter the maximum incentive amount that can be paid to contractors for work on the contract.</li>
 +
<li>'''Disincentive Cap Amount''' - enter the maximum total amount of disincentives that can be withheld from payment to contractors for work on the contract.</li>
 +
</ol>
 +
 
  
 
5. The following fields will self-populate:
 
5. The following fields will self-populate:
a. Stormwater Earth Moving - indicates whether the SECIR report for this contract includes an earth moving inspection.
+
 
b. Original Reference Vendor ID - shows the identification number for the original contractor on the contract.
+
<ol style="list-style-type:lower-alpha">
c. Original Reference Vendor Name - lists the name of the original contractor.
+
<li>'''Stormwater Earth Moving''' - indicates whether the SECIR report for this contract includes an earth moving inspection.</li>
d. Original Material Generated User ID - indicates a unique identifier regarding each person for materials.
+
<li>'''Original Reference Vendor ID''' - shows the identification number for the original contractor on the contract.</li>
e. DWR Agency View Reference Item Associations Imported - indicates whether the contract imported associations between DWR agency views and reference items.
+
<li>'''Original Reference Vendor Name''' - lists the name of the original contractor.</li>
f. Override Global Payment Estimate Exceptions - indicates whether the contract includes overrides to the agency- wide default settings for contractor payment estimate exceptions.
+
<li>'''Original Material Generated User ID''' - indicates a unique identifier regarding each person for materials.</li>
g. Override Global Contract Payment Approval Levels - indicates whether the contract includes overrides to the agency- wide default settings for contractor payment approval levels.
+
<li>'''DWR Agency View Reference Item Associations Imported''' - indicates whether the contract imported associations between DWR agency views and reference items.</li>
 +
<li>'''Override Global Payment Estimate Exceptions''' - indicates whether the contract includes overrides to the agency- wide default settings for contractor payment estimate exceptions.</li>
 +
<li>'''Override Global Contract Payment Approval Levels''' - indicates whether the contract includes overrides to the agency- wide default settings for contractor payment approval levels.</li>
 +
</ol>
 +
 
  
 
6. The following fields can be completed in the Phase Financial Closeout group box:
 
6. The following fields can be completed in the Phase Financial Closeout group box:
a. Project Review Date - enter the date that the project was reviewed.
 
b. Primary Reason for Delay - enter the proper reason for delay.
 
c. Construction Comments - enter any information about the associated work.
 
d. Engineer Certification Expiration Date - enter the date that the engineer certification will expire.
 
e. Final Estimate Projected Date - enter the projected final estimate completion date.
 
  
7. Click the Save button.
+
<ol style="list-style-type:lower-alpha">
 +
<li>'''Project Review Date''' - enter the date that the project was reviewed.</li>
 +
<li>'''Primary Reason for Delay''' - enter the proper reason for delay.</li>
 +
<li>'''Construction Comments''' - enter any information about the associated work.</li>
 +
<li>'''Engineer Certification Expiration Date''' - enter the date that the engineer certification will expire.</li>
 +
<li>'''Final Estimate Projected Date''' - enter the projected final estimate completion date.</li>
 +
</ol>
 +
 
 +
 
 +
7. Click the '''Save''' button.
 +
 
 +
 
 +
 
 +
 
 +
<!-- *********************************************************************************
 +
*********************************************************************************-->
 +
 
 +
 
  
  
 
==Maintaining Administrative Offices on the Contract==
 
==Maintaining Administrative Offices on the Contract==
  
The Administrative Offices tab enables you to associate one or more administrative offices with the contract. Staff assigned to the administrative offices selected will be able to see contracts with their roles that are assigned to that office.
+
<p style="color:green"><i>The Administrative Offices tab enables you to associate one or more administrative offices with the contract. Staff assigned to the administrative offices selected will be able to see contracts with their roles that are assigned to that office.
 +
</i>
 +
</p>
  
1. To add an administrative office, Click the Administrative Offices tab.
+
1. To add an administrative office, Click the '''Administrative Offices''' tab.
  
2. Enter the search criteria for an administrative office in the Quick Find search box. Or, click the Select Administrative Office button.
+
2. Enter the search criteria for an administrative office in the '''Quick Find''' search box. Or, click the '''Select Administrative''' Office button.
  
 
3. Click the row for the office to add to the contract.
 
3. Click the row for the office to add to the contract.
  
4. Click the Add to Contract button.
+
4. Click the '''Add to Contract''' button.
 +
 
 +
 
 +
[[File:Contract Administration Picture2.png|center]]
 +
 
  
 
5. Click the expand arrow for the new office row.
 
5. Click the expand arrow for the new office row.
  
+
 
 +
[[File:Contract Administration Picture3.png|center]]
 +
 
  
 
6. The following fields are available:
 
6. The following fields are available:
a. Effective Date - enter the date the office becomes effective.
 
b. Expiration Date - enter the date that approval or effectiveness ends for the office, if appropriate. This does not need to be populated.
 
c. Status - click the drop-down arrow and select the status of the office.
 
d. Active - should be defaulted to Active and indicates whether the record is active or not, based on the effective and expiration dates and the status field.
 
  
7. Click the Save button.
+
<ol style="list-style-type:lower-alpha">
 +
<li>'''Effective Date''' - enter the date the office becomes effective.</li>
 +
<li>'''Expiration Date''' - enter the date that approval or effectiveness ends for the office, if appropriate. This does not need to be populated.</li>
 +
<li>'''Status''' - click the drop-down arrow and select the status of the office.</li>
 +
<li>'''Active''' - should be defaulted to Active and indicates whether the record is active or not, based on the effective and expiration dates and the status field.</li>
 +
</ol>
 +
 
 +
 
 +
7. Click the '''Save''' button.
  
 
8. Once saved, depending on which level of contract administrative office is selected, you may need to use range fill to fill in the Effective Date and Status of the higher contract administrative offices.
 
8. Once saved, depending on which level of contract administrative office is selected, you may need to use range fill to fill in the Effective Date and Status of the higher contract administrative offices.
  
a. Click the arrow next to the Effective Date label on the contract administrative office that you selected and select All x rows (where x is the number of contract administrative offices).
+
<ol style="list-style-type:lower-alpha">
b. Click the arrow next to the Status label on the contract administrative office that you selected and select All x rows (where x is the number of contract administrative offices).
+
<li>Click the arrow next to the Effective Date label on the contract administrative office that you selected and select All x rows (where x is the number of contract administrative offices).</li>
 +
<li>Click the arrow next to the Status label on the contract administrative office that you selected and select All x rows (where x is the number of contract administrative offices).</li>
 +
</ol>
 +
 
 +
 
 +
9. Click the '''Save''' button.
 +
 
 +
 
 +
 
 +
 
 +
<!-- *********************************************************************************
 +
*********************************************************************************-->
 +
 
  
9. Click the Save button.
 
  
  
 
==Maintaining Contract Specific Contract Authority==
 
==Maintaining Contract Specific Contract Authority==
  
 +
<p style="color:green"><i>Contract Specific Contract Authority works in conjunction with other security features to give individual users the authority to access and change contract information. The Contract Authority tab contains all the contract authority information that has been recorded for this contract.
 +
</i>
 +
</p>
 +
  
Contract Specific Contract Authority works in conjunction with other security features to give individual users the authority to access and change contract information. The Contract Authority tab contains all the contract authority information that has been recorded for this contract.
+
<div style="overflow:auto">
 +
{| class="wikitable" style="margin-left:auto; margin-right:auto; border:none; background:lightyellow; color:Red"
 +
! '''NOTE'''
 +
|-
 +
|When using InfoTech Mobile Inspector, users must be assigned contract-specific contract authority in order to access contract data and enter DWR information in Mobile Inspector. Assigning All Contract Access or inheriting office-wide contract authority does not provide the user with contract access in Mobile Inspector.  
 +
|-
 +
|}
 +
</div>
  
  Note: When using InfoTech Mobile Inspector, users must be assigned contract-specific contract authority in order to access contract data and enter DWR information in Mobile Inspector. Assigning All Contract Access or inheriting office-wide contract authority does not provide the user with contract access in Mobile Inspector.
 
  
1. To add contract authority information, Click the Contract Authority tab.
+
1. To add contract authority information, Click the '''Contract Authority''' tab.
 +
 
 +
2. In the '''Contract Specific Contract Authority''' section, Click the '''New''' button.
 +
 
 +
 
 +
[[File:Contract Administration Picture4.png|center]]
  
2. In the Contract Specific Contract Authority section, Click the New button.
 
  
 
3. The following fields are available:
 
3. The following fields are available:
a. Person - enter the ID of the person for whom you are assigning contract authority.
 
b. Role - enter the role of the person for whom you are assigning contract authority.
 
c. Effective Date - enter the date the contract authority becomes effective for the person.
 
d. Expiration Date - enter the date the contract authority ends for the person.
 
e. Status - click the drop-down arrow and select the status for the record.
 
  
4. Click the Save button.
+
<ol style="list-style-type:lower-alpha">
 +
<li>'''Person''' - enter the ID of the person for whom you are assigning contract authority.</li>
 +
<li>'''Role''' - enter the role of the person for whom you are assigning contract authority.</li>
 +
<li>'''Effective Date''' - enter the date the contract authority becomes effective for the person.</li>
 +
<li>'''Expiration Date''' - enter the date the contract authority ends for the person.</li>
 +
<li>'''Status''' - click the drop-down arrow and select the status for the record.</li>
 +
</ol>
 +
 
 +
 
 +
4. Click the '''Save''' button.
 +
 
 +
 
 +
 
 +
 
 +
<!-- *********************************************************************************
 +
*********************************************************************************-->
 +
 
 +
 
  
  
 
==Viewing Office-Wide Contract Authority==
 
==Viewing Office-Wide Contract Authority==
  
This section contains a list of all the office-wide contract authorities in the system that would include this contract, listed by person. The information in this list is view only and cannot be changed.
+
<p style="color:green"><i>This section contains a list of all the office-wide contract authorities in the system that would include this contract, listed by person. The information in this list is view only and cannot be changed.
 +
</i>
 +
</p>
 +
 
  
 
1. To view information on the contract authorities, Click the Contract Authority tab.
 
1. To view information on the contract authorities, Click the Contract Authority tab.
  
2. In the Office-Wide Contract Authority section, click in a row to expand it.
+
2. In the '''Office-Wide Contract Authority''' section, click in a row to expand it.
 +
 
 +
 
 +
[[File:Contract Administration Picture5.png|center]]
 +
 
  
 
3. View the information.
 
3. View the information.
Line 114: Line 196:
 
The Contract Items component provides information about all the items associated with the contract.
 
The Contract Items component provides information about all the items associated with the contract.
  
 +
 +
 +
 +
<!-- *********************************************************************************
 +
*********************************************************************************-->
  
  
Line 120: Line 207:
 
==Viewing Contract Items==
 
==Viewing Contract Items==
  
The General tab contains an accordion list of all of the awarded vendor's bid prices for the contract items and any items that were added or modified by change orders.
+
<p style="color:green"><i>The General tab contains an accordion list of all of the awarded vendor's bid prices for the contract items and any items that were added or modified by change orders.
 +
</i>
 +
</p>
  
1. To view contract items on the General tab, Navigate to the Contract Administration component, and select the appropriate contract.
+
1. To view contract items on the General tab, Navigate to the '''Contract Administration''' component, and select the appropriate contract.
  
2. Click the Items quick link.
+
2. Click the '''Items''' quick link.
  
 
3. Click the expand arrow for a row to view information about the item.
 
3. Click the expand arrow for a row to view information about the item.
  
 
The other tabs, Contract Project Items tab, and Contractor Items tab show the contract item information sorted by project and contractor respectively.  
 
The other tabs, Contract Project Items tab, and Contractor Items tab show the contract item information sorted by project and contractor respectively.  
 +
 +
 +
 +
 +
<!-- *********************************************************************************
 +
*********************************************************************************-->
 +
 +
  
  
 
==Adding an Unattached Item to the Contract==
 
==Adding an Unattached Item to the Contract==
  
An unattached item is an item added to the contract after the contract has been executed. Unattached items are included in contract categories and can be tracked on daily work reports but are not recognized as contract items by the system and cannot be included in a contract payment until they are added to the contract through a change order and the change order is approved.
+
<p style="color:green"><i>An unattached item is an item added to the contract after the contract has been executed. Unattached items are included in contract categories and can be tracked on daily work reports but are not recognized as contract items by the system and cannot be included in a contract payment until they are added to the contract through a change order and the change order is approved.
 +
</i>
 +
</p>
 +
 
  
Navigation: Construction > Contract Administration > Contract Administration Overview > Select Contract > Contract Administration Summary > Items quick link > General tab
+
1. To add unattached items to a contract Click the '''General''' tab.
  
1. To add unattached items to a contract Click the General tab.
+
2. Click the '''Select Unattached Items''' button.
  
2. Click the Select Unattached Items button.
+
3. In the '''Item ID''' field, search for and select the Item you want to designate as unattached in the contract.
  
3. In the Item ID field, search for and select the Item you want to designate as unattached in the contract.
+
4. Search for and select the '''Projects''' and '''Categories''' to which to add the unattached item.
 +
 
 +
5. Click the '''Save''' button.
 +
 
 +
 
 +
 
 +
 
 +
<!-- *********************************************************************************
 +
*********************************************************************************-->
  
4. Search for and select the Projects and Categories to which to add the unattached item.
 
  
5. Click the Save button.
 
  
  
 
==Maintaining Contract Project Items==
 
==Maintaining Contract Project Items==
  
The Contract Project Items tab provides a view of all the items in the contract, listed by project category.
+
<p style="color:green"><i>The Contract Project Items tab provides a view of all the items in the contract, listed by project category.
 +
</i>
 +
</p>
  
Navigation: Construction > Contract Administration Summary > Items Quick Link > Contract Project Items tab
 
  
1. To maintain contract project items, Click the Contract Project Items tab.
+
1. To maintain contract project items, Click the '''Contract Project Items''' tab.
  
 
2. Click the expand arrow for the project, and for each newly added item.
 
2. Click the expand arrow for the project, and for each newly added item.
  
3. In the Contract Project Item Comments field, enter comments.
+
3. In the '''Contract Project Item Comments''' field, enter comments.
 +
 
 +
4. Click the '''Save''' button.
 +
 
 +
 
 +
 
 +
 
 +
<!-- *********************************************************************************
 +
*********************************************************************************-->
  
4. Click the Save button.
 
  
  
Line 166: Line 280:
 
==Viewing Contractor Items==
 
==Viewing Contractor Items==
 
    
 
    
The Contractor Items tab contains an accordion list that includes the prime contractor and all subcontractors associated with the contract, and lists the items assigned to each. For more information, see the Working with Contractor Items section of the AASHTOWare Project Construction & Materials™ User’s Guide for Construction.
+
<p style="color:green"><i>The Contractor Items tab contains an accordion list that includes the prime contractor and all subcontractors associated with the contract, and lists the items assigned to each. For more information, see the Working with Contractor Items section of the AASHTOWare Project Construction & Materials™ User’s Guide for Construction.
 +
</i>
 +
</p>
  
Navigation: Construction > Contract Administration > Contract Administration Overview > Select Contract > Contract Administration Summary > Items quick link > Contractor Items tab
 
  
1. To view contractor items on a contract, Click the Contractor Items tab.
+
1. To view contractor items on a contract, Click the '''Contractor Items''' tab.
  
 
2. Click the expand arrow to view the items for a contractor.
 
2. Click the expand arrow to view the items for a contractor.
 +
 +
 +
 +
 +
<!-- *********************************************************************************
 +
*********************************************************************************-->
  
  
Line 179: Line 300:
 
==Using Attention Flags on Contract Items==
 
==Using Attention Flags on Contract Items==
  
Attention flags allow you to place a temporary reminder or comment on a contract item or DWR item.
+
<p style="color:green"><i>Attention flags allow you to place a temporary reminder or comment on a contract item or DWR item.
 +
</i>
 +
</p>
 +
 
 +
 
 +
1. To add an attention flag, Click the '''Items''' link.
 +
 
 +
2. Click the row '''Actions''' button for the item to which to add an attention flag on the Contract Items > General tab and select the '''Contract Item Attention Flags''' task.
 +
 
 +
3. Click the '''New''' button (unless blank row already there).
 +
 
 +
4. In the '''Comments''' field, enter a comment for the flag.
  
Navigation: Construction > Contract Administration > Contract Administration Overview > Select Contract > Contract Administration Summary > Items quick link
+
5. Click the '''Save''' button.
  
1. To add an attention flag, Click the Items link.
 
  
2. Click the row Actions button for the item to which to add an attention flag on the Contract Items > General tab and select the Contract Item Attention Flags task.
 
  
3. Click the New button (unless blank row already there).
 
  
4. In the Comments field, enter a comment for the flag.
+
<!-- *********************************************************************************
 +
*********************************************************************************-->
  
5. Click the Save button.
 
  
  
Line 197: Line 326:
 
==Closing and Archiving a Contract==
 
==Closing and Archiving a Contract==
  
At the end of a contract, the contract can be closed. A closed contract can be reopened if needed.
+
<p style="color:green"><i>At the end of a contract, the contract can be closed. A closed contract can be reopened if needed.
 +
</i>
 +
</p>
  
The archival functionality does not remove a contract from the system. Instead, the system updates the contract so it has an Archived status and the Roles within the system can be configured to restrict access to the archived contracts.
+
<p style="color:green"><i>The archival functionality does not remove a contract from the system. Instead, the system updates the contract so it has an Archived status and the Roles within the system can be configured to restrict access to the archived contracts.
 +
</i>
 +
</p>
  
Navigation:  Construction > Contract Administration > Contract Administration Overview > Select Contract > Contract Administration Summary > General tab
 
  
 
To archive a contract:
 
To archive a contract:
  
1.  From the Construction component, select the Contract
+
1.  From the '''Construction''' component, select the '''Contract
Administration link.
+
Administration''' link.
  
 
2.  Search for and select the contract to activate.
 
2.  Search for and select the contract to activate.
  
3.  Click the Contract ID link.
+
3.  Click the '''Contract ID''' link.
  
4.  In the Contract Status field, click the drop-down arrow and select
+
4.  In the '''Contract Status''' field, click the drop-down arrow and select
Archived Contract.
+
'''Archived Contract'''.
  
5.  Click the Save button.
+
5.  Click the '''Save''' button.

Revision as of 17:15, 30 November 2021

CONTRACT ADMINISTRATION

Managing Contracts Information

The Additional Information tab allows you to maintain additional information on the contract.

1. Navigate to the Contract Administration component.

2. Search for and Select the contract ID that you are assigned.

3. Click the Additional Information tab.


Contract Administration Picture1.png


4. The following fields are available, depending on your role, some maybe updatable:

  1. Proposal Type - click the drop-down arrow and select the proposal type.
  2. Division/Residency - enter the administrative office level responsible for this contract.
  3. Designer - search for and select the person responsible for the contract’s design.
  4. Surety - search for and select the name of the company that insures the proposal vendor.
  5. Surety Agent - search for and select the contact person at the surety company.
  6. Stormwater Events Enabled – click checkbox if a Stormwater Event is required.
  7. Contract Work Type - click the drop-down arrow and select the kind of work to be performed.
  8. Progress Schedule Type - click the drop-down arrow and select the method used to track contract progress.
  9. Contract Alternate Name 1 - enter an alternate name for the contract, if appropriate.
  10. Contract Alternate Name 2 - enter a second alternate name for the contract, if appropriate.
  11. Total Allowable Maximum Subcontract Percent - enter the maximum percent of contract work that the agency allows to be subcontracted for non-specialty items.
  12. Supplemental Spec Book - enter a specification book associated with the proposal in addition to the primary spec book.
  13. Incentive Cap Amount - enter the maximum incentive amount that can be paid to contractors for work on the contract.
  14. Disincentive Cap Amount - enter the maximum total amount of disincentives that can be withheld from payment to contractors for work on the contract.


5. The following fields will self-populate:

  1. Stormwater Earth Moving - indicates whether the SECIR report for this contract includes an earth moving inspection.
  2. Original Reference Vendor ID - shows the identification number for the original contractor on the contract.
  3. Original Reference Vendor Name - lists the name of the original contractor.
  4. Original Material Generated User ID - indicates a unique identifier regarding each person for materials.
  5. DWR Agency View Reference Item Associations Imported - indicates whether the contract imported associations between DWR agency views and reference items.
  6. Override Global Payment Estimate Exceptions - indicates whether the contract includes overrides to the agency- wide default settings for contractor payment estimate exceptions.
  7. Override Global Contract Payment Approval Levels - indicates whether the contract includes overrides to the agency- wide default settings for contractor payment approval levels.


6. The following fields can be completed in the Phase Financial Closeout group box:

  1. Project Review Date - enter the date that the project was reviewed.
  2. Primary Reason for Delay - enter the proper reason for delay.
  3. Construction Comments - enter any information about the associated work.
  4. Engineer Certification Expiration Date - enter the date that the engineer certification will expire.
  5. Final Estimate Projected Date - enter the projected final estimate completion date.


7. Click the Save button.





Maintaining Administrative Offices on the Contract

The Administrative Offices tab enables you to associate one or more administrative offices with the contract. Staff assigned to the administrative offices selected will be able to see contracts with their roles that are assigned to that office.

1. To add an administrative office, Click the Administrative Offices tab.

2. Enter the search criteria for an administrative office in the Quick Find search box. Or, click the Select Administrative Office button.

3. Click the row for the office to add to the contract.

4. Click the Add to Contract button.


Contract Administration Picture2.png


5. Click the expand arrow for the new office row.


Contract Administration Picture3.png


6. The following fields are available:

  1. Effective Date - enter the date the office becomes effective.
  2. Expiration Date - enter the date that approval or effectiveness ends for the office, if appropriate. This does not need to be populated.
  3. Status - click the drop-down arrow and select the status of the office.
  4. Active - should be defaulted to Active and indicates whether the record is active or not, based on the effective and expiration dates and the status field.


7. Click the Save button.

8. Once saved, depending on which level of contract administrative office is selected, you may need to use range fill to fill in the Effective Date and Status of the higher contract administrative offices.

  1. Click the arrow next to the Effective Date label on the contract administrative office that you selected and select All x rows (where x is the number of contract administrative offices).
  2. Click the arrow next to the Status label on the contract administrative office that you selected and select All x rows (where x is the number of contract administrative offices).


9. Click the Save button.





Maintaining Contract Specific Contract Authority

Contract Specific Contract Authority works in conjunction with other security features to give individual users the authority to access and change contract information. The Contract Authority tab contains all the contract authority information that has been recorded for this contract.


NOTE
When using InfoTech Mobile Inspector, users must be assigned contract-specific contract authority in order to access contract data and enter DWR information in Mobile Inspector. Assigning All Contract Access or inheriting office-wide contract authority does not provide the user with contract access in Mobile Inspector.


1. To add contract authority information, Click the Contract Authority tab.

2. In the Contract Specific Contract Authority section, Click the New button.


Contract Administration Picture4.png


3. The following fields are available:

  1. Person - enter the ID of the person for whom you are assigning contract authority.
  2. Role - enter the role of the person for whom you are assigning contract authority.
  3. Effective Date - enter the date the contract authority becomes effective for the person.
  4. Expiration Date - enter the date the contract authority ends for the person.
  5. Status - click the drop-down arrow and select the status for the record.


4. Click the Save button.





Viewing Office-Wide Contract Authority

This section contains a list of all the office-wide contract authorities in the system that would include this contract, listed by person. The information in this list is view only and cannot be changed.


1. To view information on the contract authorities, Click the Contract Authority tab.

2. In the Office-Wide Contract Authority section, click in a row to expand it.


Contract Administration Picture5.png


3. View the information.

Managing Contract Items


The Contract Items component provides information about all the items associated with the contract.





Viewing Contract Items

The General tab contains an accordion list of all of the awarded vendor's bid prices for the contract items and any items that were added or modified by change orders.

1. To view contract items on the General tab, Navigate to the Contract Administration component, and select the appropriate contract.

2. Click the Items quick link.

3. Click the expand arrow for a row to view information about the item.

The other tabs, Contract Project Items tab, and Contractor Items tab show the contract item information sorted by project and contractor respectively.





Adding an Unattached Item to the Contract

An unattached item is an item added to the contract after the contract has been executed. Unattached items are included in contract categories and can be tracked on daily work reports but are not recognized as contract items by the system and cannot be included in a contract payment until they are added to the contract through a change order and the change order is approved.


1. To add unattached items to a contract Click the General tab.

2. Click the Select Unattached Items button.

3. In the Item ID field, search for and select the Item you want to designate as unattached in the contract.

4. Search for and select the Projects and Categories to which to add the unattached item.

5. Click the Save button.





Maintaining Contract Project Items

The Contract Project Items tab provides a view of all the items in the contract, listed by project category.


1. To maintain contract project items, Click the Contract Project Items tab.

2. Click the expand arrow for the project, and for each newly added item.

3. In the Contract Project Item Comments field, enter comments.

4. Click the Save button.





Viewing Contractor Items

The Contractor Items tab contains an accordion list that includes the prime contractor and all subcontractors associated with the contract, and lists the items assigned to each. For more information, see the Working with Contractor Items section of the AASHTOWare Project Construction & Materials™ User’s Guide for Construction.


1. To view contractor items on a contract, Click the Contractor Items tab.

2. Click the expand arrow to view the items for a contractor.





Using Attention Flags on Contract Items

Attention flags allow you to place a temporary reminder or comment on a contract item or DWR item.


1. To add an attention flag, Click the Items link.

2. Click the row Actions button for the item to which to add an attention flag on the Contract Items > General tab and select the Contract Item Attention Flags task.

3. Click the New button (unless blank row already there).

4. In the Comments field, enter a comment for the flag.

5. Click the Save button.





Closing and Archiving a Contract

At the end of a contract, the contract can be closed. A closed contract can be reopened if needed.

The archival functionality does not remove a contract from the system. Instead, the system updates the contract so it has an Archived status and the Roles within the system can be configured to restrict access to the archived contracts.


To archive a contract:

1. From the Construction component, select the Contract Administration link.

2. Search for and select the contract to activate.

3. Click the Contract ID link.

4. In the Contract Status field, click the drop-down arrow and select Archived Contract.

5. Click the Save button.